Hi Pierre,

Rates can be set global and can be overridden per resource and task and
employee type. see accounting -> global -> rates

Regards,
Hans

On Tue, 2010-09-21 at 10:03 +0200, Pierre Smits wrote:
> Hi all,
> 
> I have come across a situation where per project and per task in a project
> different rates need to be set in order to do cost estimation and invoicing.
> As far as I can see it now it is only possible to set a global rate for a
> resource on the resources tab in projectmgr? Am I correct?
> 
> Can anyone tell me if that is possible with current trunk?
> 
> Regards,
> 
> Pierre

-- 
Ofbiz on twitter: http://twitter.com/apache_ofbiz
Myself on twitter: http://twitter.com/hansbak
Antwebsystems.com: Quality services for competitive rates.