Hi Hans,

Thanks for the prompt reply. I just found that I can set rates on a per task
level in the work effort module.

Regards,

Pierre Smits


2010/9/21 Hans Bakker <[email protected]>

> Hi Pierre,
>
> Rates can be set global and can be overridden per resource and task and
> employee type. see accounting -> global -> rates
>
> Regards,
> Hans
>
> On Tue, 2010-09-21 at 10:03 +0200, Pierre Smits wrote:
> > Hi all,
> >
> > I have come across a situation where per project and per task in a
> project
> > different rates need to be set in order to do cost estimation and
> invoicing.
> > As far as I can see it now it is only possible to set a global rate for a
> > resource on the resources tab in projectmgr? Am I correct?
> >
> > Can anyone tell me if that is possible with current trunk?
> >
> > Regards,
> >
> > Pierre
>
> --
> Ofbiz on twitter: http://twitter.com/apache_ofbiz
> Myself on twitter: http://twitter.com/hansbak
> Antwebsystems.com <http://twitter.com/hansbak%0AAntwebsystems.com>:
> Quality services for competitive rates.
>
>

Reply via email to