My installer updates a (Google) spreadsheet and notifies me to look at
it saying we're getting low.  I buy what we're low on and it fills
back up.

Josh Luthman
Office: 937-552-2340
Direct: 937-552-2343
1100 Wayne St
Suite 1337
Troy, OH 45373

“Success is not final, failure is not fatal: it is the courage to
continue that counts.”
--- Winston Churchill



On Tue, Jul 6, 2010 at 2:30 PM, Marlon K. Schafer <o...@odessaoffice.com> wrote:
> Hi Lori,
>
> We do 100 to 200 new subs per year.  Closer to 100 now, the new installs are
> slowing down.
>
> We have a very small number of components that we normally use so inventory
> tracking is mostly as simple as looking at the shelves.
>
> When we get to a certain level (about 2 weeks work) we order more product.
> It's all handled by the tech (me) and an office manager.
>
> I used to manage a large warehouse.  We used all kinds of fancy software
> there.
>
> However, here in this business I've found that my work is far too bursty for
> that.  Keeping minimal amounts on the shelf (to conserve cash) but never
> running out requires close coordination between the installer and the
> scheduler.
>
> Hope that's helpful.
> marlon
>
> ----- Original Message -----
> From: "Lori Bridegroom" <loribridegr...@gabcompany.com>
> To: <wireless@wispa.org>
> Sent: Tuesday, June 29, 2010 12:54 PM
> Subject: [WISPA] ISP seeking MRP (material requirements planning) software
>
>
>>I have spent most of career in the manufacturing business sector.   I was
>> recently assigned to manage the purchasing and inventory control for my
>> company.  Before I try to re-invent the wheel in the ISP Industry, I want
>> to
>> know if there is a canned MRP (Material Requirements Planning) Package
>> that
>> others are using that works for the wireless internet providers.  I want
>> it
>> to include the following:
>>
>>
>>
>> .         A configuration input for special projects and additions to
>> typical installs
>>
>> .         Input for forecasting
>>
>> .         Ability to set planning horizons
>>
>> .         Lead times, re-order point, lots, etc.
>>
>> .         A pick list for each standard install type
>>
>> .         A pick list from special configurations
>>
>> .         An MRP explosion - compares demand and supply which eventually
>> creates a suggested purchasing list along with an exception list that
>> suggests to "pull-in orders" and "push-out orders"
>>
>>
>>
>>
>>
>> Lori D. Bridegroom, MBA-ACC
>>
>> Great American Broadband  d/b/a
>>
>> Only Internet
>>
>> Supernova Technologies
>>
>> CorpSite/Name My Dots
>>
>> MapleNet Broadband
>>
>>
>>
>>
>>
>> --------------------------------------------------------------------------------
>> WISPA Wants You! Join today!
>> http://signup.wispa.org/
>> --------------------------------------------------------------------------------
>>
>> WISPA Wireless List: wireless@wispa.org
>>
>> Subscribe/Unsubscribe:
>> http://lists.wispa.org/mailman/listinfo/wireless
>>
>> Archives: http://lists.wispa.org/pipermail/wireless/
>
>
>
> --------------------------------------------------------------------------------
> WISPA Wants You! Join today!
> http://signup.wispa.org/
> --------------------------------------------------------------------------------
>
> WISPA Wireless List: wireless@wispa.org
>
> Subscribe/Unsubscribe:
> http://lists.wispa.org/mailman/listinfo/wireless
>
> Archives: http://lists.wispa.org/pipermail/wireless/
>


--------------------------------------------------------------------------------
WISPA Wants You! Join today!
http://signup.wispa.org/
--------------------------------------------------------------------------------
 
WISPA Wireless List: wireless@wispa.org

Subscribe/Unsubscribe:
http://lists.wispa.org/mailman/listinfo/wireless

Archives: http://lists.wispa.org/pipermail/wireless/

Reply via email to