Hi guys.  In case anybody else was following the thread about how change
risk is rounded, looks like we got some bad information.  Here is the
real answer, a KB was written on this as well.

 

How is the Risk calculation in Change 7.0 handled in terms of rounding? 
Product / Categories 


LP - Licensed Product

BMC Remedy Change Management Application

7.0.02


P R O B L E M 

  _____  

How is Risk calculated in Change 7.0 in terms of setting what Risk level
it is? For example is 3.4 rounded down to 3 and 3.5 rounded up to 4?



S O L U T I O N 

  _____  

Risk is not rounded as such. Risk is looked up. When risk is calculated,
it does the math and comes up with say 3.36 (for example). It then looks
up the value on the form CHG:ChangeRiskRanges to determine where that
value falls in. The result is then used from the table.

 

The values in the table can be customized to make 3.36 become a 4 or a 3
depending on the administrator's intent.

 

By default 3.0 is a 3 and anything from 3.000001 to 4 becomes a 4.

 

Attachments 

  _____  

*       change_risk_ranges.jpg
<http://hou-kmrprd-01.adprod.bmc.com/KMSAttachments/KM-000010037111/chan
ge_risk_ranges.jpg> 

 


Environment:

 

All


Creation Date:

 

06/27/2007 08:42:36


Last Modified Date:

 

06/27/2007 08:53:34


Last Promoted Date:

 

06/27/2007 08:53:34


Review Date:

 

06/27/2008


Document ID:

 

KM-000010037111


 

 

sseitz

 

 

Corporate IT

Enterprise Systems Management

Remedy Support Team

 

 

Remedy Support Team Home Page

 <http://collaborate.mckesson.com/sites/esm/remedy>
http://collaborate.mckesson.com/sites/esm/remedy

 


_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org ARSlist:"Where the 
Answers Are"

Reply via email to