Hi,

You have to set up the Cost Categories for doing the Product Costing 
in Axapta. You have to set up Cost Categories and then attach it to 
Work Centers. Only Process Cost, Quantity and Set up Costs can be 
currently set up in Axapta. Set them up and attach them to the work 
center.

When you post the Pick List, Route Cards, Job Cards and Report As 
Finished Journals the cost is accumulated and when Costing is run, 
only then the costing vouchers are posted.

As for the Indirect costs allocation, this is not available in 
Standard Axapta with Cost Accounting module being discontinued. At 
the most you can do is post indirect costs to certain accounts and 
then use the standard allocation of Ledger.

Regards,

Yusuf Mukadam

--- In [EMAIL PROTECTED], Koh Meng 
<[EMAIL PROTECTED]> wrote:
> Hi,
>  
> Really thanks for your reply.  May I know how does the system 
handle the ledger posting when :
>  
> 1. The Picking list is being posted.
> 2. The Route Card is being posted.
> 3. When Production is report as finished
> 4. When the Costing is run and the final product is being costed.
>  
> FYI, I've chosen Item + Workcenters to be my posting type.  
> 
> Thousands thanks. 
> Joel WU <[EMAIL PROTECTED]> wrote:
> This is only what my company is doing, just for reference.
>  
> One of the possible solution is to embed the production cost (not 
material) into the routing, and work centre, so when the production 
order complete and post to ledger module, it can capture the cost.
>  
> And if your company is use standard costing method (Every Single 
item have a standard cost of it), you can put the standard cost into 
the inventory->Price.
> So that everytime post a production order, it will separate the 
material cost and other cost.
>  
> Joel
>  
> ----- Original Message ----- 
> From: James Flavell 
> To: [EMAIL PROTECTED] 
> Sent: Wednesday, June 23, 2004 4:37 PM
> Subject: RE: [Axapta-Knowledge-Village] Product Costing and 
Posting in Production
> 
> 
> Its not very clear exactly where the indirect costs should show 
up....if they must be put as part of the inventory module cost then 
the only two options are via misc charges or via the inventory 
adjustment function.....  
>  
> 
>  -----Original Message-----
> From: mchiat [mailto:[EMAIL PROTECTED]
> Sent: Wednesday, June 23, 2004 10:18 AM
> To: [EMAIL PROTECTED]
> Subject: [Axapta-Knowledge-Village] Product Costing and Posting in 
Production
> 
> 
> Hi all,
> 
> Is there anyone knows about Product Costing in Axapta? My client 
is 
> using Absorption Costing method whereby Indirect Production Costs 
> will be inventorized into Final Product.  Can anyone tell me how 
can 
> it be applied to Axapta? 
> 
> I'm quite confused with Axapta Production Posting.  The demo data 
> doesn't make any sense with regard to ledger posting e.g. when FG 
> scrap is reported the system will post the scrap into Inventory 
Gain 
> (Credit Balance).  Do you have any write-up / comments for 
> Production Posting?
> 
> Thanks in advance and any feedback is much appreciated. 
> 
> 
> 
> 
> 
> Sharing the knowledge on Axapta. 
> 
> 
> 
> 
> Sharing the knowledge on Axapta. 
> 
> 
> 
> 
> Sharing the knowledge on Axapta. 
> 
> 
> Yahoo! Groups SponsorADVERTISEMENT
> 
> 
> ---------------------------------
> Yahoo! Groups Links
> 
>    To visit your group on the web, go to:
> http://groups.yahoo.com/group/Axapta-Knowledge-Village/
>   
>    To unsubscribe from this group, send an email to:
> [EMAIL PROTECTED]
>   
>    Your use of Yahoo! Groups is subject to the Yahoo! Terms of 
Service. 
> 
> 
>               
> ---------------------------------
> Do you Yahoo!?
> Yahoo! Mail is new and improved - Check it out!



------------------------ Yahoo! Groups Sponsor --------------------~--> 
Make a clean sweep of pop-up ads. Yahoo! Companion Toolbar.
Now with Pop-Up Blocker. Get it for free!
http://us.click.yahoo.com/L5YrjA/eSIIAA/yQLSAA/kGEolB/TM
--------------------------------------------------------------------~-> 

Sharing the knowledge on Axapta. 
Yahoo! Groups Links

<*> To visit your group on the web, go to:
     http://groups.yahoo.com/group/Axapta-Knowledge-Village/

<*> To unsubscribe from this group, send an email to:
     [EMAIL PROTECTED]

<*> Your use of Yahoo! Groups is subject to:
     http://docs.yahoo.com/info/terms/
 

Reply via email to