In Dynamics AX you can run a Master scheduling, which is the MRP part, that 
calculates planned purchase and production orders based on the sales orders, 
forecast and min. item inventory quantities. The planned production orders can 
then be firmed to be real production orders. Then you can use the Production 
module to do operation or job scheduling on the real production orders.

Hope this answers your question,
Anders Sørensen

This posting is provided "AS IS" with no warranties, and confers no rights.

From: Axapta-Knowledge-Village@yahoogroups.com [mailto:[EMAIL PROTECTED] On 
Behalf Of Vijay Bhankur
Sent: 25. juni 2007 11:39
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: [Axapta-Knowledge-Village] Is there seperate MPS and MRP Planning


Hi Friends,

In Microsoft Dynanics-AX, is there seperate MPS and MRP running?
What I find is one can run for Forecast scheduling and then Master Scheduling.

Thans in advance.

Vijat



---------------------------------
Did you know? You can CHAT without downloading messenger. Click here

[Non-text portions of this message have been removed]



[Non-text portions of this message have been removed]

Reply via email to