We have a scenario like this.  One of the operation works at the
subcontractor.

We create one item in the BOM called service with Vendor and create a
workcenter with type vendor

Regards

Kusman
Primacom

On Tue, Aug 18, 2009 at 1:12 PM, Shivam Tandon <shivamtando...@yahoo.in>wrote:

>
>
> No there is no need to create Spreate production order and purchase order
> for these items
> Create one bom type item.
> add all the items in these bom as an item or as a sub bom.
> create one production order for these bom.
>
>
> --- On *Mon, 17/8/09, visti Sethna <visti2...@gmail.com>* wrote:
>
>
> From: visti Sethna <visti2...@gmail.com>
> Subject: Re: [Axapta-Knowledge-Village] Re: sub contracting process
> To: Axapta-Knowledge-Village@yahoogroups.com
> Date: Monday, 17 August, 2009, 5:16 AM
>
>    Hi Friends,
>
> I need one help in AX 2009.
>
> I need to map a subcontracting screnario in which i need to send a couple
> of items to the vendors, for painting. I need a few clarifications
>
> As this is a machine building scenario, there are almost 500 parts that
> need to go for painting to the vendor.
>
> 1) Is it necessary to maintain seperate item code for all the 500 parts
> that go out for painting.
>
> 2) Is it necessary that all the 500 codes have seperate production and
> purchase and transfer orders for painting that go out which means about 1500
> orders would get generated.
>
> 3) Ps requesting your best advice on people who have worked on such
> scenarios.
>
> Awaiting reply from some experts on this
>
> Regards
> Vishtaspa Sethna
>
> On Mon, Aug 17, 2009 at 8:59 AM, NITIN DESALE <nitindesale@ yahoo.co. 
> in<http://in.mc950.mail.yahoo.com/mc/compose?to=nitindes...@yahoo.co.in>
> > wrote:
>
>>       Hi Rahul,
>> Thanks for update.
>>
>> Our scenarios is to send material as per BOM to sub contractor he will do
>> some process on that and send to us FG/Sub FG.
>> pls let me know  What is the standard processor to map above  scenario.
>>
>>
>> Thanks
>> Nitin
>>
>>
>>
>> --- On *Wed, 12/8/09, Rahul Mohta <rahulmohta_8@ 
>> yahoo.com<http://in.mc950.mail.yahoo.com/mc/compose?to=rahulmoht...@yahoo.com>
>> >* wrote:
>>
>>
>> From: Rahul Mohta <rahulmohta_8@ 
>> yahoo.com<http://in.mc950.mail.yahoo.com/mc/compose?to=rahulmoht...@yahoo.com>
>> >
>> Subject: [Axapta-Knowledge- Village] Re: sub contracting process
>> To: Axapta-Knowledge- vill...@yahoogro 
>> ups.com<http://in.mc950.mail.yahoo.com/mc/compose?to=axapta-knowledge-vill...@yahoogroups.com>
>> Date: Wednesday, 12 August, 2009, 4:37 PM
>>
>>    Hi Nitin,
>>
>> Subcontracting could be of several types:
>>
>> > Complete Order
>>
>> > Partial Order
>> All Operations
>> Part Operations
>> With materials
>> Without materials, etc
>>
>> Depending upon the scenarios, AX needs to be mapped and configured and
>> sometimes customise as well.
>>
>> Regards
>> RahulMohta
>>
>> --- In Axapta-Knowledge- vill...@yahoogro 
>> ups.com<http://in.mc945.mail.yahoo.com/mc/compose?to=Axapta-Knowledge-Village%40yahoogroups.com>,
>> NITIN DESALE <nitindesale@ ...> wrote:
>> >
>> > All,
>> >
>> > If  any one has the document of sub contracting process  let me know thw
>> same or explain in brief.
>> >
>> > Thankx
>> > Nitin
>> >
>> > Send free SMS to your Friends on Mobile from your Yahoo! Messenger.
>> Download Now! http://messenger. yahoo.com/ download. 
>> php<http://messenger.yahoo.com/download.php>
>> >
>>
>>
>> ------------------------------
>> See the Web's breaking stories, chosen by people like you. Check out Yahoo!
>> Buzz <http://in.rd.yahoo.com/tagline_buzz_1/*http://in.buzz.yahoo.com/>.
>>
>
>
>
> --
> With Regards,
> Mr. Vishtaspa Sethna
> Associate E..R.P. Consultant
> Godrej Infotech Ltd.
> Cell: +919833213532
>
>
> ------------------------------
> Love Cricket? Check out live scores, photos, video highlights and more. Click
> here <http://in.rd.yahoo.com/tagline_cricket_2/*http://cricket.yahoo.com>.
>
> 
>

Reply via email to