Dear Mr. Vyas:

 

I suggest you review the definitions for SELV and PELV in IEC 62052.  These 
definitions are not the same throughout IEC standards.  (I don’t have IEC 
62052.)

 

In some standards, SELV is isolated from protective earth, and PELV is 
connected to protective earth.  If these are the definitions in IEC 62052, then 
SELV must be isolated from earth by Basic Insulation.  (I have never understood 
why we have both SELV and PELV as only the voltage and the isolation are the 
essential parameters for protection against electric shock.)  

 

In other standards, SELV is determined by the voltage and the isolation from 
higher voltages; earthing (or not) of SELV does not enter into this 
determination.   

 

Good luck and best regards,

Rich

 

 

 

From: Balmukund Vyas <balmukund.v...@ymllabs.com> 
Sent: Tuesday, March 13, 2018 5:56 AM
To: EMC-PSTC@LISTSERV.IEEE.ORG
Subject: [PSES] insulation between SELV and protective earthed accessible part- 
IEC 62052-31

 

 

 

Dear All,

IEC 62052-31 is standard for product safety requirements for electricity 
metering equipment. It has a table 20 (given below) which details out 
insulation requirements between various types of circuits.

My question is, why Basic insulation is required between SELV circuit and 
protective earthed accessible parts? Isn’t a functional insulation is 
sufficient for this?

 

Thanks

 

B M Vyas

 

Table 20 – Insulation requirements between circuits and between circuits and 
accessible parts


 

HLV 
mains-circuit1)

ELV circuit

SELV circuit

PELV circuit

PEB circuit2)

Protective earthed HLV non-mains-circuit2), 3)

Unearthed HLV non-mains circuit3)


HLV mains-circuit 1)

F/B1) 6)

Table 8Table 9

B

Table 8Table 9

D

Table 8Table 9

D

Table 8Table 9

B5)

Table 8Table 9

B

Table 8Table 9

B

Table 8Table 9


ELV circuit

B

Table 8Table 9

F/B6)

Table 13Table 14

B

Table 13Table 14

B

Table 13Table 14

F/B5), 6)

Table 13Table 14

B

Table 13Table 14

B

Table 13Table 14


SELV circuit

D

Table 8Table 9

B

Table 13Table 14

F/B6)

Table 13Table 14

F/B8)

Table 13Table 14

B

Table 13Table 14

D

Table 13Table 14

D

Table 13Table 14


PELV circuit2)

D

Table 8Table 9

B

Table 13Table 14

F/B8)

Table 13Table 14

F/B6)

Table 13Table 14

B

Table 13Table 14

D

Table 13Table 14

D

Table 13Table 14


PEB circuit2)

B5)

Table 8Table 9

F/B5), 6)

Table 13Table 14

B

Table 13Table 14

B

Table 13Table 14

F/B5)

Table 13Table 14

B

Table 13Table 14

B

Table 13Table 14


Protective earthed HLV non-mains circuit2), 3)

B

Table 8Table 9

B

Table 8Table 9

D

Table 8Table 9

D

Table 8Table 9

B

Table 8Table 9

F/B6)

Table 8Table 9

B

Table 8Table 9


Unearthed HLV non-mains circuit3)

B

Table 13Table 14

B

Table 13Table 14

D

Table 13Table 14

D

Table 13Table 14

B

Table 13Table 14

B

Table 13Table 14

F/B6)

Table 13Table 14


Protective earthed accessible part2), 7)

B

Table 8Table 9

F/B6)

Table 13Table 14

B

Table 13Table 14

B

Table 13Table 14

F/B6)

Table 13Table 14

B

Table 13Table 14

B

Table 13Table 14


Unearthed accessible part7)

D

Table 8Table 9

B

Table 13Table 14

B

Table 13Table 14

F/B6)

Table 13Table 14

B

Table 13Table 14

D

Table 13Table 14

B/D 4)

Table 13Table 14


Abbreviations for insulations:

B: Basic insulation or supplementary insulation

D: double insulation or reinforced insulation

F: Functional insulation

S: Supplementary insulation


1)            If the functional voltage (not relative to earth/ground) is 
greater than the rated insulation voltage, the creepage distance for the 
functional insulation may be greater than that for the basic insulation. An 
example is a terminal block of a three-phase metering equipment with Un = 
230/400 V, where the functional phase-to-phase voltage is 400 V r.m.s. For an 
indoor meter with material group III, the creepage distance for basic 
insulation from Table 9 is 3,2 mm, but the creepage distance for functional 
insulationfrom Table 14 is 4,0 mm.

2)            Connections to the protective conductor shall comply with 
6.5.2.4. Otherwise, this shall be considered to be an unearthed circuit.

3)            There shall be at least basic insulation between HLV non-mains 
circuits and HLV mains circuits.

4)            Insulation between an unearthed non-mains circuit at hazardous 
voltage and an unearthed accessible conductive part shall satisfy the more 
onerous of the following:

-       double/reinforced insulation, the working voltage of which is equal to 
the hazardous voltage; or

-       supplementary insulation, the working voltage of which is equal to the 
voltage between the non-mains circuit athazardous voltage; and

*  another non-mains circuit at hazardous voltage; or

*  a mains circuit.

5)            See Annex Bfor the conditional use of basic insulation for PEB.

6)            Supplementary or basic insulation shall be used if one of the 
circuits is an independent circuit or is adjacent to a conductive part which 
may be earthed when the equipment is installed. 

7)            A functional earthed circuit shall be treated as an unearthed 
accessible part. The exception is where the functional earth is bonded to the 
protective conductor and this meets the relevant requirements, then it may be 
treated as an earthed accessible part.

8)            For a PELV system earthed at one end of a cable run, it would be 
permissible to connect a SELV system at the other end.


NOTE    Reference is made to the respective tables specifying clearances and 
creepage distances.

 


-
----------------------------------------------------------------
This message is from the IEEE Product Safety Engineering Society emc-pstc 
discussion list. To post a message to the list, send your e-mail to 
<emc-p...@ieee.org>

All emc-pstc postings are archived and searchable on the web at:
http://www.ieee-pses.org/emc-pstc.html

Attachments are not permitted but the IEEE PSES Online Communities site at 
http://product-compliance.oc.ieee.org/ can be used for graphics (in well-used 
formats), large files, etc.

Website:  http://www.ieee-pses.org/
Instructions:  http://www.ieee-pses.org/list.html (including how to unsubscribe)
List rules: http://www.ieee-pses.org/listrules.html

For help, send mail to the list administrators:
Scott Douglas <sdoug...@ieee.org>
Mike Cantwell <mcantw...@ieee.org>

For policy questions, send mail to:
Jim Bacher:  <j.bac...@ieee.org>
David Heald: <dhe...@gmail.com>

Reply via email to