I think we're all set, Ill bring it up in standup today, but I'm pretty
sure the Android ones that Joey/Tim pushed were all that we really
needed.


On Mon, 2015-08-03 at 16:19 +0000, Lankswert, Patrick wrote:
> Erich,
> 
>  
> 
> Do you have a list of fixes that you think are high priority for
> 0.9.2? If so, get them pushed.
> 
>  
> 
> Pat
> 
>  
> 
> From:??? [mailto:juney at samsung.com] 
> Sent: Monday, August 03, 2015 11:30 AM
> To: Lankswert, Patrick; ???; Keane, Erich;???
> Cc: iotivity-dev at lists.iotivity.org; Mirani, Jawid
> Subject: Re: RE: [dev] About preparing 0.9.2 Release Schedule
> 
> 
>  
> 
> Pat, Jawid,
> 
>  
> 
> 
> We have no option now anyway.
> 
> 
> Samsung have fixed some issues that occurred on RC2, so could you fix
> your all the issues by around 17:00 PST?
> 
> 
> Then after that we will tag RC3 tomorrow morning(Korea time)
> 
> 
>  
> 
> 
> Regards
> 
> 
> June
> 
> 
> Sent from Mobiledesk
> 
> 
>  
> 
> ---?? ???---
> ??? : Lankswert, Patrick/patrick.lankswert at intel.com
> ???? : 2015/08/03 23:39 (GMT+09:00)
> ?? : RE: [dev] About preparing 0.9.2 Release Schedule
> 
> June,
> 
> I do not have that information. I need to defer to Jawid.
> 
> Pat
> 
> > -----Original Message-----
> > From: iotivity-dev-bounces at lists.iotivity.org [mailto:iotivity-dev-
> > bounces at lists.iotivity.org] On Behalf Of ???(June Yong Young)
> > Sent: Friday, July 31, 2015 11:18 PM
> > To: Keane, Erich; soonhwang.choi at samsung.com
> > Cc: iotivity-dev at lists.iotivity.org; Mirani, Jawid
> > Subject: Re: [dev] About preparing 0.9.2 Release Schedule
> > 
> > Hi Pat, Jawid,
> > 
> > Could you urgently let us know when Intel?s QA will complete 2nd
> round test and
> > when 3rd QA will be completed if it starts on 8/3 again, so that we
> can judge
> > whether or not we can make a 0.9.2 release before 8/7?
> > 
> > You know, if we cannot deliver 0.9.2 to SWG on 8/7, then PF#3 will
> be at risk.
> > 
> > June Yong Young
> > OIC Open Sourece WG Project Planning & Requirement TG Chair IoTivity
> Release
> > Function Lead
> > 
> > Samsung Electronics Co.,Ltd.
> > Software R&D Center, IoT Solution Lab. | Web & Convergence Team
> Principal
> > Engineer
> > 
> > T: +82-31-301-6107, M: +82-10-9530-6107
> > E-mail :juney at samsung.com
> > 
> > -----Original Message-----
> > From: Keane, Erich [mailto:erich.keane at intel.com]
> > Sent: Saturday, August 01, 2015 1:20 AM
> > To: soonhwang.choi at samsung.com
> > Cc: sungkyu.ko at samsung.com; woochul.shim at samsung.com; iotivity-
> > dev at lists.iotivity.org; Mirani, Jawid; juney at samsung.com; Agrawal,
> Sachin
> > Subject: Re: [dev] About preparing 0.9.2 Release Schedule
> > 
> > We have an issue in the resource model with the Android stack as
> well that
> > we're waiting on, plus a handful of bug-fixes that have been pushed
> since the
> > RC2. I would be very much FOR an RC3.
> > 
> > -Erich
> > 
> > 
> > On Fri, 2015-07-31 at 08:37 +0000, SOON HWANG CHOI wrote:
> > > Dear All
> > >
> > >
> > >
> > > Test result of 2nd round test for Samsung modules may be reported
> at
> > > next Monday (8/3) because consent of 2nd roud test was delayed.
> > >
> > > Currently we found below major defects. so we think RC3 should be
> > > released for 0.9.2 Official release.
> > >
> > >
> > >
> > > 1. PPM Tizen sample app is not working if Invoke button is pushed
> > >
> > > 2. PPM Android sample app is not working if "START PLUGIN" button
> is
> > > pushed
> > >
> > > 3. RM's build error in linux 64ibt environment
> > >
> > >
> > >
> > > Thanks
> > >
> > > Soonhwang Choi
> > >
> > >
> > >
> > >
> > >
> > > ------- Original Message -------
> > >
> > > Sender : ???<juney at samsung.com> S6(??)/??/IoT Solution
> Lab(S/W
> > > ??)/????
> > >
> > > Date : 2015-07-31 09:51 (GMT+09:00)
> > >
> > > Title : About preparing 0.9.2 Release Schedule
> > >
> > >
> > >
> > > Hi Pat, George, Jawid,
> > >
> > > When will Intel?s QA complete 2nd round test?
> > >
> > >
> > >
> > > Hi Pat, Jawid, SoonHwang,
> > >
> > > Could you let us know the 2nd round test result by 7/31, so that
> we
> > > can find out whether or not we need RC3?
> > >
> > >
> > >
> > >
> > >
> > > 0.9.2 : ?Spec vA Compliant + Spec vB Partial?
> > >
> > > ? Type for Release : Minor release, Schedule Driven, PlugFest #3
> > >
> > > ? Schedule (5 weeks ahead of QA completion) (cf. Original QA
> request
> > > is 6 weeks ahead of QA start)
> > >
> > > ? 6/22, API freeze & Programmer?s guide freeze
> > >
> > > ? 7/20, Feature complete & Review Complete and make ?0.9.2-RC1?
> > > release to QA
> > >
> > > ? 7/24, QA 1st round complete
> > >
> > > ? 7/27->7/28, 0.9.2-RC2 release to QA
> > >
> > > ? 7/31, QA 2nd round complete
> > >
> > > ? 8/03, Website Open (if no issue)
> > >
> > > ? 8/17 week, Plug Fest #3
> > >
> > >
> > >
> > >
> > >
> > > June Yong Young
> > > OIC Open Sourece WG Project Planning & Requirement TG Chair
> > >
> > > IoTivity Release Function Lead
> > >
> > >
> > > Samsung Electronics Co.,Ltd.
> > >
> > > Software R&D Center, IoT Solution Lab. | Web & Convergence Team
> > >
> > > Principal Engineer
> > >
> > > T: +82-31-301-6107, M: +82-10-9530-6107
> > >
> > > E-mail :juney at samsung.com
> > >
> > >
> > >
> > > From: iotivity-dev-bounces at lists.iotivity.org
> > > [mailto:iotivity-dev-bounces at lists.iotivity.org] On Behalf Of ??
> > > ?(June Yong Young)
> > > Sent: Wednesday, July 29, 2015 4:50 PM
> > > To: 'Agrawal, Sachin'; '???'; Jawid Mirani_Intel; ?????;
> ??
> > ???_SE
> > > Cc: iotivity-dev at lists.iotivity.org
> > > Subject: Re: [dev] About preparing 0.9.2 Security Release
> > >
> > >
> > >
> > >
> > > Hi Sachin,
> > >
> > > Thank you for the tagging 0.9.2-RC2.
> > >
> > >
> > >
> > > Hi Pat, George, Jawid,
> > >
> > > I think still there is no more schedule delay required although
> RC2
> > > has been 1 day delayed.
> > >
> > > However I am not sure what is Intel QA?s position about 7/31 QA
> 2nd
> > > round completion date although Samsung QA is positive.
> > >
> > >
> > >
> > > 0.9.2 : ?Spec vA Compliant + Spec vB Partial?
> > >
> > > ? Type for Release : Minor release, Schedule Driven, PlugFest #3
> > >
> > > ? Schedule (5 weeks ahead of QA completion) (cf. Original QA
> request
> > > is 6 weeks ahead of QA start)
> > >
> > > ? 6/22, API freeze & Programmer?s guide freeze
> > >
> > > ? 7/20, Feature complete & Review Complete and make ?0.9.2-RC1?
> > > release to QA
> > >
> > > ? 7/24, QA 1st round complete
> > >
> > > ? 7/27->7/28, 0.9.2-RC2 release to QA
> > >
> > > ? 7/31, QA 2nd round complete
> > >
> > > ? 8/03, Website Open (if no issue)
> > >
> > > ? 8/17 week, Plug Fest #3
> > >
> > >
> > >
> > >
> > >
> > > June Yong Young
> > > OIC Open Sourece WG Project Planning & Requirement TG Chair
> > >
> > > IoTivity Release Function Lead
> > >
> > >
> > > Samsung Electronics Co.,Ltd.
> > >
> > > Software R&D Center, IoT Solution Lab. | Web & Convergence Team
> > >
> > > Principal Engineer
> > >
> > > T: +82-31-301-6107, M: +82-10-9530-6107
> > >
> > > E-mail :juney at samsung.com
> > >
> > >
> > >
> > > From: Agrawal, Sachin [mailto:sachin.agrawal at intel.com]
> > > Sent: Wednesday, July 29, 2015 3:24 AM
> > > To: juney at samsung.com; ???
> > > Cc: iotivity-dev at lists.iotivity.org
> > > Subject: RE: Re: [dev] About preparing 0.9.2 Security Release
> > >
> > >
> > >
> > >
> > > Hi All,
> > >
> > >
> > >
> > > I created the ?0.9.2-RC2? tag and pushed it to Iotivity repo.
> > >
> > >
> > >
> > > Thanks
> > >
> > > Sachin
> > >
> > >
> > >
> > >
> > > From: Agrawal, Sachin
> > > Sent: Tuesday, July 28, 2015 9:36 AM
> > > To: 'juney at samsung.com'; ???
> > > Cc: iotivity-dev at lists.iotivity.org
> > > Subject: RE: Re: [dev] About preparing 0.9.2 Security Release
> > >
> > >
> > >
> > >
> > > Since all the existing tags have upper-case letters ?RC?, I assume
> > > June meant to tag it with ?0.9.2-RC2?.
> > >
> > > Am I right?
> > >
> > >
> > >
> > > Thanks
> > >
> > > Sachin
> > >
> > >
> > >
> > >
> > > From: ??? [mailto:juney at samsung.com]
> > > Sent: Tuesday, July 28, 2015 8:01 AM
> > > To: ???; Agrawal, Sachin; ???
> > > Cc: iotivity-dev at lists.iotivity.org
> > > Subject: Re: Re: [dev] About preparing 0.9.2 Security Release
> > >
> > >
> > >
> > >
> > > Hi Sachin
> > >
> > >
> > >
> > >
> > > What is the progress?
> > >
> > >
> > > As soon as the review is completed, please tag "0.9.2-rc2".
> > >
> > > Sent from Mobiledesk
> > >
> > >
> > >
> > >
> > > ---?? ???---
> > > ??? : ???(June Yong Young)
> > > ???? : 2015/07/28 15:31 (GMT+09:00)
> > > ?? : Re: [dev] About preparing 0.9.2 Security Release
> > >
> > > Hi Sachi,
> > >
> > >
> > >
> > > When will the review be finished? Everybody is waiting for the
> > > completion by today.
> > >
> > >
> > >
> > > Regards
> > >
> > > June
> > >
> > >
> > >
> > > June Yong Young
> > > OIC Open Sourece WG Project Planning & Requirement TG Chair
> > >
> > > IoTivity Release Function Lead
> > >
> > >
> > > Samsung Electronics Co.,Ltd.
> > >
> > > Software R&D Center, IoT Solution Lab. | Web & Convergence Team
> > >
> > > Principal Engineer
> > >
> > > T: +82-31-301-6107, M: +82-10-9530-6107
> > >
> > > E-mail :juney at samsung.com
> > >
> > >
> > >
> > > From: Agrawal, Sachin [mailto:sachin.agrawal at intel.com]
> > > Sent: Tuesday, July 28, 2015 2:52 AM
> > > To: juney at samsung.com; ???
> > > Cc: iotivity-dev at lists.iotivity.org
> > > Subject: RE: About preparing 0.9.2 Security Release
> > >
> > >
> > >
> > >
> > > Hi June,
> > >
> > >
> > >
> > > SRM/Provisioning Mgr API is unable to discover the secure port of
> the
> > > new device.
> > >
> > > Jira ticket: https://jira.iotivity.org/browse/IOT-626
> > >
> > >
> > >
> > > It is SpecA mandatory as Provisioning Tool is dependent on this.
> > >
> > >
> > >
> > > Code change is currently under review and will be pushed in
> 0.9.2-dev
> > > as soon as it finishes review process.
> > >
> > >
> > >
> > > Thanks
> > >
> > > Sachin
> > >
> > >
> > > From: ??? [mailto:juney at samsung.com]
> > > Sent: Monday, July 27, 2015 9:12 AM
> > > To: ???; Agrawal, Sachin; iotivity-dev at lists.iotivity.org
> > > Cc: Kesavan, Vijay S; Heldt-Sheller, Nathan; ???; ???; ??
> ?; ???;
> > ???;
> > > ???; ???; ??
> > > Subject: Re: About preparing 0.9.2 Security Release
> > >
> > >
> > >
> > >
> > > Hi Sachin, WooCheol,
> > >
> > >
> > >
> > >
> > > Please share the security issues in iotivity mailing list.
> > >
> > >
> > > - what is the security issue?
> > >
> > >
> > > - SpecA mandatory related issue? Or not?
> > >
> > >
> > > - When will it be fixed?
> > >
> > >
> > >
> > >
> > >
> > > Regards
> > >
> > >
> > > June
> > >
> > >
> > > Sent from Mobiledesk
> > >
> > >
> > >
> > >
> > > ---?? ???---
> > > ??? : ???
> > > ???? : 2015/07/27 16:58 (GMT+09:00)
> > > ?? : About preparing 0.9.2 Security Release
> > >
> > > Hi Sachin,
> > >
> > >
> > >
> > > June (release manager) asked me when the gerrit review #1680 will
> be
> > > cherry-picked to 0.9.2-dev for testing and RC2.
> > >
> > > We confirmed that provisioning tool is working with
> > > https://gerrit.iotivity.org/gerrit/#/c/1680 but, without 1680, we
> > > failed to run it.
> > >
> > > If possible, could you please share the plan about this change?
> > >
> > > Thank you.
> > >
> > >
> > >
> > > BR, Woochul
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > > Choi, Soon Hwang
> > >
> > >
> > > Senior Engineer / Ph. D.
> > >
> > > Software Engineering Team (SE Team)
> > > Software R&D Center
> > >
> > > SAMSUNG ELECTRONICS CO.,LTD
> > >
> > > AnyCall +82-10-7311-0206
> > > e-mail soonhwang.choi at samsung.com
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > > _______________________________________________
> > > iotivity-dev mailing list
> > > iotivity-dev at lists.iotivity.org
> > > https://lists.iotivity.org/mailman/listinfo/iotivity-dev
> > 
> > 
> > _______________________________________________
> > iotivity-dev mailing list
> > iotivity-dev at lists.iotivity.org
> > https://lists.iotivity.org/mailman/listinfo/iotivity-dev
> 
> 
> 
> 
> 
> 
> 
> 