At DC Cook our initial setpoints are also based on historical data, but
our ALARA procedure contains the following guidance.
This is intended primarily to ensure the dose estimates are still
accruate, but there is a subsequent step that says to revise RWPs as
necessary (which would certainly include ED setpoints)
3.4.2 In the early stages of a refueling outage, such as post
shutdown/post crud
burst, the actual as-found radiological conditions should be
compared to the
projected/estimated radiological conditions for each job
reviewed by the
ALARA Subcommittee/ALARA Committee.
a. The following radiological
conditions should be evaluated.
· work area dose rates
· travel path dose rates
· work area conditions that may
affect personnel time in the area
"Thompson, David A" <[email protected]>
Sent by: [email protected]
09/29/2010 07:24 AM
Please respond to
[email protected]
To
" ([email protected])" <[email protected]>
cc
Subject
Powernet: RWP Setpoint Changes
Duke currently establishes RWP dose and dose rate setpoints based on
historical data for outages, with various tasks under the RWP having
setpoints commensurate with the area work is to be performed. Does anybody
have a process where they would adjust these established setpoints once
the unit is off-line, and initial surveys are completed, dependent on
conditions identified?
David A. Thompson, CHP
Manager Nuclear Fleet RP/Chemistry
[email protected]
704-382-6773
----------------------------------------------------------------
This e-mail message and all attachments transmitted with it from the
Nuclear Generation Group of American Electric Power are for the sole
use of the intended recipient(s) and may contain confidential and
privileged information. Any unauthorized review, use, disclosure or
distribution is prohibited. If you are not the intended recipient, please
contact the sender by reply e-mail and destroy all copies of the original
message.