Hi All, I have a utility that is hinting that they are going to deny my interconnection application with a supply side connection and require a load side. Has anyone seen this before?
(Proposed interconnection would be with Milbank step lugs in a 200 A socket and a 60 A fused disconnect within 10 feet.) If they refuse it, i am thinking that registering a complaint with the Wisconsin PSC may be appropriate. Kris Shine On! Kris Schmid Legacy Solar, LLC 137 West 1st Avenue Luck, WI 54853 www.legacysolar.com 715-653-4295 NABCEP Certified PV Installation Professional Licensed Wisconsin Master Electrician BSEE
_______________________________________________ List sponsored by Redwood Alliance List Address: RE-wrenches@lists.re-wrenches.org Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org There are two list archives for searching. When one doesn't work, try the other: https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/ http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org List rules & etiquette: http://www.re-wrenches.org/etiquette.htm Check out or update participant bios: http://www.members.re-wrenches.org