Michael

 

  Great questions. We have had great success with the Sol-Arks, starting with 
the 8’s. Have completed several with twin 15’s and the systems have been great. 
There was a software/ firmware issues when they first came out.

 

  Having spent years installing AC coupled systems ( thought they were great at 
the time ) the SA’s have made delivering power so much better.

 

Thx

peter

 

From: RE-wrenches <re-wrenches-boun...@lists.re-wrenches.org> On Behalf Of 
Michael Morningstar via RE-wrenches
Sent: Monday, September 18, 2023 1:13 PM
To: RE-wrenches <re-wrenches@lists.re-wrenches.org>
Cc: Michael Morningstar <mjmornings...@gmail.com>
Subject: [RE-wrenches] GT w/ BB

 

I've been asked to build a back up system for a grid connected estate. We 
haven't done many of these and I thought it best to ask those who have some 
questions before I go about reinventing the wheel.

 

Here's the existing infrastructure.

1) 400amp Metered Main Distribution Panel with six 200amp feeders to various 
sub-panels on the property

2) 400amp ATS and 100kw Kohler rapid response generator 

3) 20kw ground mount array with (2) SE Inverters located at the array. Feeder 
from array is 1,000 ft to Service. Six years old and wiring is janky.

4) Data logging for the last year shows peak demands of almost 40kw. This could 
increase as several of formerly vacant  guest residences could be occupied.

 

My go to is almost always Schneider, however in this instance when I looked 
into a quad stack, or more It seems like some type of controller is needed to 
prevent imbalanced current passing through the relays during transfer. That 
left me a bit concerned. Has anyone successfully stacked 4 or more XWPROs?

 

Then there is the matter of AC or DC coupling? I really want no part in having 
anything to do with SE. The inverters are already looking pretty weathered 
taking the brunt of the prevailing winds and storms (they are mounted to one of 
the ground mount poles). Seems like a great waste to pull out the 4/0 feeders 
and replace strings. My other hesitancy with AC coupling is that we would lose 
PV monitoring and control.

 

I've also considered Sol Ark 15's, like three of them. We've got some SA 
systems under are belt now and the only thing I can say that I like is the 
speed of installation and the 200amp pass through. Other than that, they leave 
me uninspired. One very large system continues to have glitches that SA just 
shrugs their shoulders about. If we were to do three 15's, what's the preferred 
combining method? All that I can come up with is a custom 400a panelboard w/ 
three 200a breakers. 

 

Price is not a consideration for this project. The new owners of this property 
(which is plagued with outages) have tasked me with building something that is 
ultra reliable and good take over in a situation where the grid is no longer 
available.

 

Any suggestions or tips are appreciated.

 

Michael

 

-- 

Michael Morningstar

 

Morningstar Electric

PO Box 1494

Mount Shasta, CA 96067

530-921-0560

mjmornings...@gmail.com <mailto:mjmornings...@gmail.com> 



_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

Reply via email to