We've had a project or three where we had to wrestle a certificate out
of the owner because the AHJs (Cobb and Gwinnett County, metro Atlanta)
require it be submitted with the sprinkler drawings.  This was after the
bid.

Bobby McCullough
Atlanta Sprinkler Inspection
[EMAIL PROTECTED] 



-----Original Message-----
From: [EMAIL PROTECTED]
[mailto:[EMAIL PROTECTED] On Behalf Of Thom
McMahon
Sent: Thursday, July 12, 2007 10:52 AM
To: [email protected]
Subject: Re: MIC test

Great question G.
How many of you ever see an Owners cert.? and of those that do how many
are 
after you've bid, and are trying to justify your bid vs. the storage or 
occupancy you see on the job?
Has anyone seen or been required to provide the owners cert. to get a 
permit?

Thom McMahon
Firetech, Inc.
2560 Copper Ridge Dr
Steamboat Springs, CO 80488-2136
Tel: 970-879-7952
Fax: 970-879-7926
----- Original Message ----- 
From: "George Church" <[EMAIL PROTECTED]>
To: <[email protected]>
Sent: Thursday, July 12, 2007 7:15 AM
Subject: RE: MIC test


> You raise a great point, Terry-
> I have yet to ever see an Owner's Certificate in a bid package.
>
> Is this something that others are seeing in more progressive
(compliant?)
> areas?
>
> glc
>
> -----Original Message-----
> From: [EMAIL PROTECTED]
> [mailto:[EMAIL PROTECTED] On Behalf Of Victor,

> Terry
> Sent: Thursday, July 12, 2007 8:40 AM
> To: [email protected]
> Subject: RE: MIC test
>
> George,
>
> We deliberately changed 13 to put the responsibility on the owner for
> conditions in the water supply that we as contractors may have to
> address. In the 1999 version of 13, if we as contractors had
'knowledge'
> that MIC was a problem in a given water supply, we were responsible
for
> testing and possibly treating that water supply when installing
systems
> connected to it. So if one contractor knew of a MIC problem, and
another
> one didn't, the bids would be apples and oranges. The 13 technical
> committee determined that any information regarding the need for
> treating or otherwise addressing MIC or corrosion issues in the water
> supply shall be provided in the owner's certificate, starting in the
> 2002 edition, section 4.3. All contractors would then be bidding with
> the same information.
>
> We do have a responsibility to test for MIC in the latest editions of
25
> (since 2002) if evidence of slime or tubercules is found during the 5
> year obstruction inspection.
>
> Terry Victor
> National Manager of Sprinkler Systems
> SimplexGrinnell
>
> [EMAIL PROTECTED]
>
> -----Original Message-----
> From: [EMAIL PROTECTED]
> [mailto:[EMAIL PROTECTED] On Behalf Of George
> Church
> Sent: Thursday, July 12, 2007 8:15 AM
> To: [email protected]
> Subject: RE: MIC test
>
> -----Original Message-----
> From: [EMAIL PROTECTED]
> [mailto:[EMAIL PROTECTED] On Behalf Of George
> Church
> Sent: Tuesday, July 10, 2007 4:09 AM
> To: [email protected]
> Subject: MIC test
>
> how are y'all covering the MIC testing in the new #13?
> Dump it on the Owner?
> Are water companies including MIC test in their QC monitoring
analysis?
> Are AHjs allowing the relaxation of the Addenda?
>
> George Church
> Rowe Sprinkler
>

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

Reply via email to