Gentlemen,as per NFPA 12, 4.6.1.2 Where the authority having jurisdiction 
determinesthat continuous protection is required, the quantity of reservesupply 
shall be as many multiples of the quantities required in4.6.1 and 4.6.1.1 as 
the authority having jurisdiction considersnecessary. what  are the factor 
which determines that the continuity as must, since AHJ sometime they have some 
unprofessional reason to affect the contractor?is there another statement or 
code determine this?
knowing that my current project is at the middle of the city with less than 
20km from the CO2, FM200 cylinder supplier.

Eng Belal K. AlrwadiehMSc Design Of Steel StructureBSc Mechanical Engineering 
Address:  KSA-RiyadhAl-Yarmouk, Abu Ja'afr 
AlmansourJordan-AmmamTabrbour-Alkhazna NeighborhoodAlkhaldeen St-Bldg 32h email 
Address:[email protected] Mobile Number:KSA-+966-549-326055Jordan: 
+962-776-498924               +962-795-630998
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to