Gentlemen,as per NFPA 12, 4.6.1.2 Where the authority having jurisdiction determinesthat continuous protection is required, the quantity of reservesupply shall be as many multiples of the quantities required in4.6.1 and 4.6.1.1 as the authority having jurisdiction considersnecessary. what are the factor which determines that the continuity as must, since AHJ sometime they have some unprofessional reason to affect the contractor?is there another statement or code determine this? knowing that my current project is at the middle of the city with less than 20km from the CO2, FM200 cylinder supplier.
Eng Belal K. AlrwadiehMSc Design Of Steel StructureBSc Mechanical Engineering Address: KSA-RiyadhAl-Yarmouk, Abu Ja'afr AlmansourJordan-AmmamTabrbour-Alkhazna NeighborhoodAlkhaldeen St-Bldg 32h email Address:[email protected] Mobile Number:KSA-+966-549-326055Jordan: +962-776-498924 +962-795-630998 _______________________________________________ Sprinklerforum mailing list [email protected] http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org