Hi,

On Mon, Jul 11, 2011 at 2:47 PM, Fabian Christ
<[email protected]> wrote:
> ...the IKS project would like to do a release around August 22, 2011.
> Since the IKS project is based on Stanbol it would be nice to have an
> official Stanbol release at the same time.
>
> Proposal: Release Stanbol 0.9 at August 22, 2011...

Note that a release from the incubator takes 72 hours as it needs a
double vote (PPMC + Incubator PMC).

I would suggest making a full release (if possible, see below) as soon
as we're ready, and if needed re-release individual modules if there
are significant changes later. The first release might be a lot of
work but later ones should be much easier.

>
> I think we should use the Stanbol "stable" launcher as a reference for
> this release. Everything included in this launcher would be part of
> the release....

We need to check our code and dependencies before deciding what can be
released, this means at least

a) Checking license headers in the stanbol code using RAT (
http://incubator.apache.org/rat/ )

b) Checking based on mvn dependency:tree that all our dependencies are
ok according to http://apache.org/legal/resolved.html

-Bertrand