Hi committers,

There doesn't seem to be consensus on how release cycle should be
managed. In the survey [0] about release cycle there were following
proposed schemes:

#1. 6 months release cycle + current stable release scheme
#2. 6 months release cycle + LTS scheme
#3. 6 months release cycle + extended security support
#4. 9 months release cycle + current stable release scheme (no change
    at all)

And the tally:

                #1      #2      #3      #4
George          +1      +2              -2
Dario           +1      +2              -2
Stefano         +1      +2              -2
Ian C           +1      +1      +1      -1
Olaf            +1       0      +1       0
Juergen          0      -1              +1
Ian J           +2      +1      +1      -2
Andrew          +1      +1              -1
Jan             -1      -1       0      +1


There are comments made by individuals that couldn't be clearly
represent in tally. The most acceptable option to stable tree
maintainers is #1.

So I propose we use the following scheme:

- 6 months release cycle from unstable branch.
  - 4 months development.
  - 2 months freeze.
  - Eat into next cycle if doesn't release on time.
- Fixed cut-off date: the Fridays of the week in which the last day of
  March and September falls.
- No more freeze exception, but heads-up mails about freeze will be
  sent a few weeks before hand.
- Stable branch maintained for 18 months full support plus 18 months
  security support. No mixed maintainership for stable trees.


Please vote to ack or nack this proposal.


Thanks
Wei.

[0]: <20151012173222.ge2...@zion.uk.xensource.com>

_______________________________________________
Xen-devel mailing list
Xen-devel@lists.xen.org
http://lists.xen.org/xen-devel

Reply via email to