So i inquired about installing a "ham" tower, which is limited to 60ft in
the county I reside, damn. They still want their use permit & fee's, it's a
several month process with a open hearing and approval from the board of
supervisors. Also an environmental study??!?

On Wed, Dec 6, 2017 at 3:17 PM, Philip Rankin <[email protected]> wrote:

> Chuck, bureaucrats are not pricks!!!!  That's the best part of a
> man!!!!!!!  They are the excrement that secreats from bureaucrat's
> ASSHOLES!!!
>
> Phil
>
> On Tue, Dec 5, 2017 at 12:46 PM, <[email protected]> wrote:
>
>> One thing about bureaucrats, they love to have all the boxes checked and
>> all the pages filled out.  So rather than kick against the pricks, I have
>> learned to try to give them more than they ask for if there is no way
>> around it.
>>
>> *From:* TJ Trout
>> *Sent:* Tuesday, December 5, 2017 11:35 AM
>> *To:* [email protected]
>> *Subject:* [AFMUG] Conditional-use permit for tower
>>
>> I just purchased a 7ac price of land for my primary residence and the
>> site is a great location for a tower site, but the local government is
>> asking for a 30 page conditional use permit app with an environmental study
>> and a public comment period plus approval by the board of supervisors...
>>
>> After that I have to obtain a building permit obviously.
>>
>> Any tips on filling out this application so I can receive an approval?
>>
>> Three of my competitors have a tower within 1 mile of this site and none
>> of them have gone through the planning or conditional use permit nor have
>> they received a building permit as far as I know. So I don't think they
>> will be asking me to co locate.
>>
>> Any advice or tips? I guess this process can take as long as a year to be
>> completed and I'm not sure what the cost will be but I'm sure an
>> environmental impact study isn't cheap.
>>
>> Thanks,
>>
>> TJ
>>
>
>
>
> --
> Philip J. Rankin
> Wireless Telecommunications Services
> PO Box 24
> Pittsburg, KS  66762
>

Reply via email to