+1 two weeks delay for feature freeze, no extension for 4.3 release -Wei
2013/5/30 John Burwell <jburw...@basho.com> > All, > > Since we have taken an eight (8) week delay completing the 4.1.0 release, > I would like propose that we re-evaluate the timelines for the 4.2.0 > release. When the schedule was originally conceived, it was intended that > the project would have eight (8) weeks to focus exclusively on 4.2.0 > development. Unfortunately, this delay has created an unfortunate conflict > between squashing 4.1.0 bugs and completing 4.2.0 features. I propose that > we acknowledge this schedule impact, and push back the 4.2.0 feature freeze > date by eight (8) weeks to 2 August 2013. This delay will give the project > time to properly review merges and address issues holistically, and, > hopefully, relieve a good bit of the stress incurred by the simultaneous > 4.1.0 and 4.2.0 activities. > > Thanks, > -John