Compromise without change?

Bring 4.3 forward by two months, leave 4.2 as it is.


DL


> -----Original Message-----
> From: Wei ZHOU [mailto:ustcweiz...@gmail.com]
> Sent: 30 May 2013 8:27 AM
> To: dev@cloudstack.apache.org
> Subject: Re: [PROPOSAL] Pushback 4.2.0 Feature Freeze
> 
> +1
> two weeks delay for  feature freeze,
> no extension for 4.3 release
> 
> -Wei
> 
> 
> 2013/5/30 John Burwell <jburw...@basho.com>
> 
> > All,
> >
> > Since we have taken an eight (8) week delay completing the 4.1.0
> > release, I would like propose that we re-evaluate the timelines for
> > the 4.2.0 release.  When the schedule was originally conceived, it was
> > intended that the project would have eight (8) weeks to focus
> > exclusively on 4.2.0 development.  Unfortunately, this delay has
> > created an unfortunate conflict between squashing 4.1.0 bugs and
> > completing 4.2.0 features.  I propose that we acknowledge this
> > schedule impact, and push back the 4.2.0 feature freeze date by eight
> > (8) weeks to 2 August 2013.  This delay will give the project time to
> > properly review merges and address issues holistically, and,
> > hopefully, relieve a good bit of the stress incurred by the
> > simultaneous
> > 4.1.0 and 4.2.0 activities.
> >
> > Thanks,
> > -John

Reply via email to