HI Chathura,

I completed both download and upload json file functionalities.now I am
working on few fixes that we discussed on last meeting.i will fix above
mention bugs too.

Thank You!

Regards,
Heshan Jayasinghe

On Mon, Aug 15, 2016 at 10:35 AM, Chathura Ekanayake <chath...@wso2.com>
wrote:

> Hi Heshan,
>
> It looks good so far.. However, there are few fixes to be done.
>
> - Properties box cannot be closed.
> - Circles in bending positions of edges have to be shown only when mouse
> gets over them
> - Gateways should allow multiple connection points (at least 4)
>
> Regards,
> Chathura
>
> On Fri, Aug 12, 2016 at 6:33 PM, Heshan Jayasinghe <shanu...@gmail.com>
> wrote:
>
>> Hi All,
>> After 3 months contributing on Web based BPMN editor i completed
>> following tasks
>>
>>    - drag and drop elements(start event/end event/gateway/task) from
>>    tool box to drawing canvas
>>    - display popup tool box with element(start event/end
>>    event/gateway/task) on click event
>>    - flow drawing to connect elements
>>    - Implement element deleting functionality (using delete button in
>>    toolbox)
>>
>>             -    delete only element if there no any flow connections
>>             -    delete element with flows if there any flows connected
>> to that element
>>             -    delete flows separately
>>
>>    - drag elements in the Canvas to change position
>>    - add flow button to toolbox and give flow drawing using toolbox
>>    shortcut
>>    - add property button to tool box and give change properties of the
>>    elements one by one (properties changed according to to element so popup
>>    window changed according to the element)
>>    - add all sub elements to the toolbox and add all above
>>    functionalities to those sub element (sub element icons changed with sub
>>    element type)
>>
>>            -  start events (default start events,error start
>> events,message start events,time start events)
>>            -  end event (default end events,error end events,terminate
>> end events,cancel end events)
>>            -  gateway (parallel gateway , exclusive gateway, inclusive
>> gateway ,event gateway )
>>            -  task (user task, script task, mail task, manual task)
>>
>>    - add task resizing functionality
>>    - add text to task (user can change text of the task text entered in
>>    the task element)
>>    - change flow connections with element drag events (if we change
>>    element position using drag and drop,flows connected to that element also
>>    changed according to element new position)
>>    - flow can be changed using multiple connection points
>>    - create JSON array and record all date one by one inside that
>>    array(element x/y coordinates,width,height,element type,element
>>    subtype,properties,etc..)
>>    - JSON array update x,y coordinates when we drag a element
>>
>> task on prosess
>>
>>    - download json file
>>    - upload json file and draw graph according to json file
>>
>>
>>
>>
>>
>>
>>
>> On Sat, Jul 30, 2016 at 11:46 PM, Heshan Jayasinghe <shanu...@gmail.com>
>> wrote:
>>
>>> HI Hasitha,
>>>
>>> My git repo is up to date .please check develop
>>> <https://github.com/heshanjse/BPMNEditor/tree/develop> branch in
>>> GitHub.I completed task text and new flow drawing.now i am working on flow
>>> change with element drag events and text area resize with task resizing.
>>>  Thank you!
>>> regards,
>>> Heshan Jyasinghe
>>>
>>>
>>> On Thu, Jul 28, 2016 at 12:27 PM, Hasitha Aravinda <hasi...@wso2.com>
>>> wrote:
>>>
>>>> Heshan,
>>>>
>>>> Could you please update this mail with your current progress ? Also can
>>>> you update the git repo with latest code base. It was last updated 23 days
>>>> ago.
>>>>
>>>> Thanks,
>>>> Hasitha.
>>>>
>>>> On Thu, Jul 14, 2016 at 9:25 AM, Heshan Jayasinghe <shanu...@gmail.com>
>>>> wrote:
>>>>
>>>>> Hi,
>>>>> I added following element to BPMN tool box.I added only boundary
>>>>> events instead of Intermediate event because both look like same and last
>>>>> discussion we plan to come up with only boundary events.
>>>>> Intermediate event have
>>>>>   time catching event
>>>>>   Signal catching event
>>>>>   Message catching Event,etc.
>>>>> Boundary event have
>>>>>  Time Boundary Event
>>>>>  Error Boundary Event
>>>>>  Message Boundary Event
>>>>>  Signal Boundary Event,etc.
>>>>> Do I need to add both intermediate event and boundary event or only
>>>>> boundary event is enough?
>>>>> If there any changes in tool box please let me know.
>>>>>
>>>>> Start Event
>>>>>
>>>>>    -      Start Event
>>>>>    -      Time Event
>>>>>    -      Message Start Event
>>>>>    -      Error Start Event
>>>>>
>>>>> End Event
>>>>>
>>>>>    -      End Event
>>>>>    -      Error End Event
>>>>>    -      Terminate End Even
>>>>>    -      Cancel End Event
>>>>>
>>>>> Task
>>>>>
>>>>>    -       User Task
>>>>>    -       Script Task
>>>>>    -       Mail Task
>>>>>    -       Receive Task
>>>>>
>>>>> Boundary Event
>>>>>
>>>>>    -      Time Boundary Event
>>>>>    -      Error Boundary Event
>>>>>    -      Message Boundary Event
>>>>>    -      Signal Boundary Event
>>>>>
>>>>> Gateway
>>>>>
>>>>>    -      Parallel Gateway
>>>>>    -       Exclusive Gateway
>>>>>    -       Inclusive Gateway
>>>>>    -       Event Gateway
>>>>>
>>>>> Connections
>>>>>
>>>>>    -       Sequence Flow
>>>>>
>>>>>
>>>>> Thank you!
>>>>> regards,
>>>>> Heshan jayasinghe
>>>>>
>>>>> On Thu, Jul 7, 2016 at 8:50 AM, Isuru Wijesinghe <isur...@wso2.com>
>>>>> wrote:
>>>>>
>>>>>> Hi Heshan,
>>>>>>
>>>>>> Please add only *general*, *main config* and *form* properties for
>>>>>> each component as you mentioned in your proposal.
>>>>>>
>>>>>> Thanks,
>>>>>> Isuru.
>>>>>>
>>>>>> On Wed, Jul 6, 2016 at 9:42 AM, Heshan Jayasinghe <shanu...@gmail.com
>>>>>> > wrote:
>>>>>>
>>>>>>> Hi,
>>>>>>> As we discussed in last meeting this week we plan to finish
>>>>>>>
>>>>>>>    - flow reposition when BPMN element position changes.
>>>>>>>    - task resizing
>>>>>>>    - text attaching
>>>>>>>    - changing task/event/gateway type using property (element icon
>>>>>>>    changed with property)
>>>>>>>
>>>>>>>
>>>>>>> I created "flow reposition when BPMN element position changes" and
>>>>>>> "task resizing" but not totally completed.I think i can finish it with 
>>>>>>> in
>>>>>>> this week.Can you please send me what are the properties you need for 
>>>>>>> each
>>>>>>> element.Then i can complete it with in this week.
>>>>>>>
>>>>>>> github url = https://github.com/heshanjse/BPMNEditor  ( last week
>>>>>>> update)
>>>>>>>
>>>>>>> Thank You!
>>>>>>> regards,
>>>>>>> Heshan Jayasinghe
>>>>>>>
>>>>>>> On Tue, Jun 21, 2016 at 6:59 AM, Heshan Jayasinghe <
>>>>>>> shanu...@gmail.com> wrote:
>>>>>>>
>>>>>>>> github url - https://github.com/heshanjse/BPMNEditor
>>>>>>>>
>>>>>>>> On Tue, Jun 21, 2016 at 6:57 AM, Heshan Jayasinghe <
>>>>>>>> shanu...@gmail.com> wrote:
>>>>>>>>
>>>>>>>>> Hi Isuru,
>>>>>>>>>
>>>>>>>>> This is the milestone plan we discussed in the last week.
>>>>>>>>>
>>>>>>>>> 24/6  - draw flows when moving a node
>>>>>>>>>          - add properties to the flow
>>>>>>>>>          - create delete functionality to every node.
>>>>>>>>>          - add arrow and text to the toolbox
>>>>>>>>> 1/7    - add text to the task
>>>>>>>>>          - task resizing
>>>>>>>>>          - change task/event/gateway icon according to the
>>>>>>>>> selected property type
>>>>>>>>> 8/7    - change flow shape from start and end point
>>>>>>>>>          - add mutiple connection points in the nodes
>>>>>>>>> 15/7  - add zoom event to svg and scroll
>>>>>>>>> 29/7  - create property list
>>>>>>>>> 5/8    - export json in to BPMN
>>>>>>>>> 19/8  - redraw element using json array after upload a BPMN file
>>>>>>>>>
>>>>>>>>> Thanks
>>>>>>>>> regards,
>>>>>>>>> Heshan Jayasinghe
>>>>>>>>>
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> On Mon, Jun 20, 2016 at 2:32 PM, Isuru Wijesinghe <
>>>>>>>>> isur...@wso2.com> wrote:
>>>>>>>>>
>>>>>>>>>> Hi Heshan,
>>>>>>>>>>
>>>>>>>>>> Please update the meeting notes. In addition to that can you
>>>>>>>>>> please share with us the milestone plan as we discussed in the last 
>>>>>>>>>> week.
>>>>>>>>>>
>>>>>>>>>> Thanks,
>>>>>>>>>> Isuru.
>>>>>>>>>>
>>>>>>>>>> On Thu, May 26, 2016 at 11:04 PM, Heshan Jayasinghe <
>>>>>>>>>> shanu...@gmail.com> wrote:
>>>>>>>>>>
>>>>>>>>>>> github url - https://github.com/heshanjse/BPMNEditor
>>>>>>>>>>>
>>>>>>>>>>> On Thu, May 19, 2016 at 12:52 PM, Heshan Jayasinghe <
>>>>>>>>>>> shanu...@gmail.com> wrote:
>>>>>>>>>>>
>>>>>>>>>>>> Hi Isuru,
>>>>>>>>>>>> I completed Start Event,End Event,Gateways and Task.Currently
>>>>>>>>>>>> these component can move in the canvas.As we discussed in our last 
>>>>>>>>>>>> meeting
>>>>>>>>>>>> I am working for packaging the current source code,drawing 
>>>>>>>>>>>> flows,component
>>>>>>>>>>>> re-sizing,creating property window and adding text areas to
>>>>>>>>>>>> Task component.After I applying packaging structure i will
>>>>>>>>>>>> share my github code.Hope I can send it soon.
>>>>>>>>>>>> Thank you,
>>>>>>>>>>>> Regards,
>>>>>>>>>>>> Heshan Jayasinghe
>>>>>>>>>>>>
>>>>>>>>>>>> On Wed, May 18, 2016 at 10:04 AM, Isuru Wijesinghe <
>>>>>>>>>>>> isur...@wso2.com> wrote:
>>>>>>>>>>>>
>>>>>>>>>>>>> Hi Heshan,
>>>>>>>>>>>>>
>>>>>>>>>>>>> Any update on your progress? Could you please share with us
>>>>>>>>>>>>> your code through github. Then we can give some feedback.
>>>>>>>>>>>>>
>>>>>>>>>>>>> Thanks,
>>>>>>>>>>>>> Isuru
>>>>>>>>>>>>>
>>>>>>>>>>>>> On Thu, Mar 24, 2016 at 1:23 PM, Heshan Jayasinghe <
>>>>>>>>>>>>> shanu...@gmail.com> wrote:
>>>>>>>>>>>>>
>>>>>>>>>>>>>> Hi,
>>>>>>>>>>>>>> I submit my final proposal through GSOC site.Could you please
>>>>>>>>>>>>>> read my proposal and add some comments.
>>>>>>>>>>>>>> Thank you!
>>>>>>>>>>>>>> regards,
>>>>>>>>>>>>>> Heshan Jayasinghe
>>>>>>>>>>>>>>
>>>>>>>>>>>>>> On Wed, Mar 23, 2016 at 8:38 AM, Isuru Wijesinghe <
>>>>>>>>>>>>>> isur...@wso2.com> wrote:
>>>>>>>>>>>>>>
>>>>>>>>>>>>>>> Hi Heshan,
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>> We have already added few comments. Could you please fix
>>>>>>>>>>>>>>> them and share the updated proposal ?
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>> Thanks and Best Regards,
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>> On Fri, Mar 18, 2016 at 9:48 PM, Isuru Wijesinghe <
>>>>>>>>>>>>>>> isur...@wso2.com> wrote:
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>> Hi Heshan,
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>> We appreciate your quick response. The main deliverable of
>>>>>>>>>>>>>>>> this project is a javascript/D3 based BPMN editor which allows 
>>>>>>>>>>>>>>>> Process
>>>>>>>>>>>>>>>> Center users to define business processes using a graphical 
>>>>>>>>>>>>>>>> notation from
>>>>>>>>>>>>>>>> the *web UI*. (No server side involvement). Keep on
>>>>>>>>>>>>>>>> progressing on the project and if you get stuck at any point, 
>>>>>>>>>>>>>>>> don't
>>>>>>>>>>>>>>>> hesitate to contact us.
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>> Thanks and Best Regards,
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>> On Fri, Mar 18, 2016 at 11:35 AM, Heshan Jayasinghe <
>>>>>>>>>>>>>>>> shanu...@gmail.com> wrote:
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>> HI,
>>>>>>>>>>>>>>>>> Could you please tell me how server side involve in this
>>>>>>>>>>>>>>>>> project? Web Editor can developed as a single page 
>>>>>>>>>>>>>>>>> application and we can
>>>>>>>>>>>>>>>>> run it in java server.hope this application haven't any 
>>>>>>>>>>>>>>>>> server side
>>>>>>>>>>>>>>>>> development.Please let me know if there server side 
>>>>>>>>>>>>>>>>> development involve.if
>>>>>>>>>>>>>>>>> there any server side development i willing to complete that 
>>>>>>>>>>>>>>>>> task too.
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>> I already complete my proposal and now I am doing final
>>>>>>>>>>>>>>>>> fine tuning of my proposal.I will send it tomorrow.from today 
>>>>>>>>>>>>>>>>> onwards I
>>>>>>>>>>>>>>>>> start my development  for first iteration.
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>> Thank you!
>>>>>>>>>>>>>>>>> regards,
>>>>>>>>>>>>>>>>> Heshan Jayasinghe
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>> On Tue, Mar 15, 2016 at 9:37 AM, Isuru Wijesinghe <
>>>>>>>>>>>>>>>>> isur...@wso2.com> wrote:
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>> Great. My contact number :
>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>> *0710933706*
>>>>>>>>>>>>>>>>>> Thanks and Best Regards,
>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>> On Tue, Mar 15, 2016 at 9:30 AM, Heshan Jayasinghe <
>>>>>>>>>>>>>>>>>> shanu...@gmail.com> wrote:
>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>> Hi Isuru,
>>>>>>>>>>>>>>>>>>> My proposal 70% over now.I will send you copy soon.could
>>>>>>>>>>>>>>>>>>> you please send me your contact number to get more 
>>>>>>>>>>>>>>>>>>> information.
>>>>>>>>>>>>>>>>>>> Thank you!
>>>>>>>>>>>>>>>>>>> regards,
>>>>>>>>>>>>>>>>>>> Heshan jayasinghe
>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>> --
>>>>>>>>>>>>>>>>>> Isuru Wijesinghe
>>>>>>>>>>>>>>>>>> *Software Engineer*
>>>>>>>>>>>>>>>>>> WSO2 inc : http://wso2.com
>>>>>>>>>>>>>>>>>> lean.enterprise.middleware
>>>>>>>>>>>>>>>>>> Mobile: 0710933706
>>>>>>>>>>>>>>>>>> isur...@wso2.com
>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>> --
>>>>>>>>>>>>>>>> Isuru Wijesinghe
>>>>>>>>>>>>>>>> *Software Engineer*
>>>>>>>>>>>>>>>> WSO2 inc : http://wso2.com
>>>>>>>>>>>>>>>> lean.enterprise.middleware
>>>>>>>>>>>>>>>> Mobile: 0710933706
>>>>>>>>>>>>>>>> isur...@wso2.com
>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>> --
>>>>>>>>>>>>>>> Isuru Wijesinghe
>>>>>>>>>>>>>>> *Software Engineer*
>>>>>>>>>>>>>>> WSO2 inc : http://wso2.com
>>>>>>>>>>>>>>> lean.enterprise.middleware
>>>>>>>>>>>>>>> Mobile: 0710933706
>>>>>>>>>>>>>>> isur...@wso2.com
>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>
>>>>>>>>>>>>>>
>>>>>>>>>>>>>
>>>>>>>>>>>>>
>>>>>>>>>>>>> --
>>>>>>>>>>>>> Isuru Wijesinghe
>>>>>>>>>>>>> *Software Engineer*
>>>>>>>>>>>>> WSO2 inc : http://wso2.com
>>>>>>>>>>>>> lean.enterprise.middleware
>>>>>>>>>>>>> Mobile: 0710933706
>>>>>>>>>>>>> isur...@wso2.com
>>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>>
>>>>>>>>>>>
>>>>>>>>>>
>>>>>>>>>>
>>>>>>>>>> --
>>>>>>>>>> Isuru Wijesinghe
>>>>>>>>>> *Software Engineer*
>>>>>>>>>> WSO2 inc : http://wso2.com
>>>>>>>>>> lean.enterprise.middleware
>>>>>>>>>> Mobile: 0710933706
>>>>>>>>>> isur...@wso2.com
>>>>>>>>>>
>>>>>>>>>
>>>>>>>>>
>>>>>>>>
>>>>>>>
>>>>>>
>>>>>>
>>>>>> --
>>>>>> Isuru Wijesinghe
>>>>>> *Software Engineer*
>>>>>> WSO2 inc : http://wso2.com
>>>>>> lean.enterprise.middleware
>>>>>> Mobile: 0710933706
>>>>>> isur...@wso2.com
>>>>>>
>>>>>
>>>>>
>>>>> _______________________________________________
>>>>> Dev mailing list
>>>>> Dev@wso2.org
>>>>> http://wso2.org/cgi-bin/mailman/listinfo/dev
>>>>>
>>>>>
>>>>
>>>>
>>>> --
>>>> --
>>>> Hasitha Aravinda,
>>>> Associate Technical Lead,
>>>> WSO2 Inc.
>>>> Email: hasi...@wso2.com
>>>> Mobile : +94 718 210 200
>>>>
>>>
>>>
>>
>
_______________________________________________
Dev mailing list
Dev@wso2.org
http://wso2.org/cgi-bin/mailman/listinfo/dev

Reply via email to