Meeting Date: 

        6/30/06 11:00 a.m. EDT

Attendees:

        Andrew Eberbach
        Joel Hawkins
        Dan Jemiolo
        Jervis Liu
        Dennis O'Flynn
        Balan Subramanian
        Mark Weitzel

Topics:

        1. Define a milestone schedule and deadlines for future 
features/bugs in JIRA.

        2. Microsoft/OASIS reconcilation specs and how this affects the 
Muse roadmap.

        3. Relationship between Muse, Tuscany, and Eclipse Corona


News & Decisions:

        1. The team has agreed to the following milestones and content:

                a. Milestone #2 (M2) - Friday, 8/4/06

                        i. OSGi support
                        ii. Error message cleanup/accuracy
                        iii. Persistence API
                        iv. More! - see JIRA

                b. Release 2.0 (R2) - Friday, 9/1/06

                        i. Just bug fixes and documentation improvements 
from M2.

        2. The team agreed that all requests and bugs must have their own 
entry in JIRA, where they will be assigned to developers working on the 
project. Anyone can have a JIRA account, so this is not an issue.

                a. All requests/fixes that are to be considered for M2 
must be in JIRA by EOD Thursday, 7/13/06.

                b. Any code or artifacts that contributors have for M2 
requests/fixes can be put in JIRA before 7/13/06.

                c. The team will prioritize any incomplete 
features/requests during its 7/13/06 meeting.


        3. Microsoft/HP/IBM/Intel are trying to reconcile the WSDM vs 
WS-Management war by drafting a new set of merged specifications and then 
putting them through ratification (the standards body is not yet known). 
We do not know exactly when the specs will be published, but we do know 
that they will build heavily on the current specs; we can start to discuss 
plans for implementing them using the Muse programming model and propose a 
roadmap based on Date X (where X = whenever the first drafts are 
published).

        Dan will send out an initial proposal on this, and the team will 
debate/modify it until it comes to a plan everyone agrees on. We hope to 
have most of this plan agreed on for 7/13/06.

        4. Joel, Jervis, and Mark led a discussion on implementing 
manageability capabilities for Tuscany using Muse/OSGi. It was decided 
that most of this work should be done in Tuscany, using Muse's core 
conceptual programming model as the basis for the non-web-services-based 
manageability features. Joel and Jervis will work together to create 
working PoC of Tuscany manageability by 7/21/06; the manageability 
capability will include start/stop operations and status properties (may 
map to MUWS State or OperationalStatus).

        5. Mark reviewed how the tooling story would work given a 
WSDL-to-Java-like code generation tool in Apache: how this would be used 
by an Eclipse IDE, how we would import/export units of manageability, how 
it could be extended to support less common use cases w/o rewriting a lot 
of model/generation code. This was brought up in the context of the 
Tuscany PoC discussion when trying to determine how much web services 
spec/plumbing code would need to be included to do non-web-services 
manipultation of the manageability components.

        6. With many people on vacation, next week's call is cancelled.


Action Items:

        1. Dan will post the milestone schedule on the web site. For now, 
we will include a link to JIRA as a reference to content; as we get closer 
to the end of July, we will provide the final list of M2 content.

        2. Dan, Andrew, and Joel will post their known features/bugs into 
JIRA, along with any code they have supporting the requests.

        2a. Other Muse contributors should add their requests to JIRA as 
well.

        3. Dan will send out the initial reconcilation roadmap proposal 
for the team to revise.

        4. Joel and Jervis will start work on the Tuscany/Muse PoC and 
update us on progress on 7/13/06.


If you have any questions or clarifications about these minutes, please 
send them along!

Thanks,
Dan



Dan Jemiolo
IBM Corporation
Research Triangle Park, NC


+++ I'm an engineer. I make slides that people can't read. Sometimes I eat 
donuts. +++



---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]
For additional commands, e-mail: [EMAIL PROTECTED]

Reply via email to