Hi,
If the Finite material checkbox is selected, then it means that an explosion is
run on the production before performing the job scheduling. If the sub
components of the production BOM are all on hand then it has no impact on the
scheduling, but if some items are not on hand and a planned
Will this also consider the lead time of the Items as specified for the item
type / service type items in the item master. Say if i have an item X of
type item that is required and is not avialabe will the lead time be
considered
On Tue, Apr 1, 2008 at 12:56 PM, Anders Sorensen [EMAIL PROTECTED]
If the items of type Item are not on hand then a planned Purchase order will be
generated and if the item has a lead time then it will get a futures date which
will be considered by production scheduling.
Regards,
Anders
This posting is provided AS IS with no warranties, and confers no
Can u please guide me in mapping Sub contracting process in Ax.
I have a client who follows sub-contracting process in which the material
from his own inventory are sent to vendor for job-work and then the material in
inwarded with a different item number.
E.g. I have a sub assemly
The checkbox for finite material can be found on the General tab of Job
Scheduling or Operation Scheduling forms (Production - Production orders -
Update - Job scheduling).
Regards,
Anders Sorensen
This posting is provided AS IS with no warranties, and confers no rights.
From:
Sir can you tell me what are the effects of ticking the finite material
checkbox. and what will the implications be.
Reply ASAP
Regards
Visti
On Mon, Mar 31, 2008 at 7:28 PM, Anders Sorensen [EMAIL PROTECTED]
wrote:
The checkbox for finite material can be found on the General tab of Job