Hi,

If the Finite material checkbox is selected, then it means that an explosion is 
run on the production before performing the job scheduling. If the sub 
components of the production BOM are all on hand then it has no impact on the 
scheduling, but if some items are not on hand and a planned order has been made 
for those items, then the scheduling will start from the Futures date of the 
planned orders.

Hope this answers your questions, otherwise look in the help file for the Job 
scheduling form where it is explained pretty good.

Regards,
Anders


This posting is provided "AS IS" with no warranties, and confers no rights.
From: visti Sethna [mailto:[EMAIL PROTECTED]
Sent: 1. april 2008 07:11
To: Axapta-Knowledge-Village@yahoogroups.com; Anders Sorensen; thurmalla nagesh
Subject: Re: [Axapta-Knowledge-Village] Lead Time in planning for Scheduling of 
operations


Sir can you tell me what are the effects of ticking the finite material 
checkbox. and what will the implications be.

Reply ASAP
Regards
Visti



On Mon, Mar 31, 2008 at 7:28 PM, Anders Sorensen <[EMAIL 
PROTECTED]<mailto:[EMAIL PROTECTED]>> wrote:

The checkbox for finite material can be found on the General tab of Job 
Scheduling or Operation Scheduling forms (Production - > Production orders -> 
Update -> Job scheduling).



Regards,

Anders Sorensen





This posting is provided "AS IS" with no warranties, and confers no rights.





From: 
Axapta-Knowledge-Village@yahoogroups.com<mailto:Axapta-Knowledge-Village@yahoogroups.com>
 
[mailto:Axapta-Knowledge-Village@yahoogroups.com<mailto:Axapta-Knowledge-Village@yahoogroups.com>]
 On Behalf Of visti Sethna
Sent: 31. marts 2008 07:35
To: 
Axapta-Knowledge-Village@yahoogroups.com<mailto:Axapta-Knowledge-Village@yahoogroups.com>
Subject: [Axapta-Knowledge-Village] Lead Time in planning for Scheduling of 
operations



Can someone tell me how will the time be captured for the subcontracting 
(Service type) item please. Coz My gant chart should capture the lead time for 
procurement of the subcontracted item when I schedule  the jobs. Instead, it 
schedules the first operation instantly after the second operation. There is 
something called finite material and finite capacity planing. Where do i select 
the checkbox for finite material planning.



Please suggest.


--
With Regards,
Mr. Vishtaspa Sethna
Associate E.R.P. Consultant
Godrej Infotech Ltd.
Cell: +919718010823




--
With Regards,
Mr. Vishtaspa Sethna
Associate E.R.P. Consultant
Godrej Infotech Ltd.
Cell: +919718010823

Reply via email to