Apologies if this has been discussed previously.  Is anyone aware of a code
requirement for a "main" flow switch?  This would only occur in a building
with multiple systems (such as 1 wet and 1 dry, or 3 wet, etc).  The "main"
flow switch would be located upstream of the individual system risers and
would be in addition to the flow switches/pressure switches on the wet/dry
systems.  I've seen a number of projects where they are called for, but am
curious if it's a code requirement or not.

 