I am about to install heat trace in two isolated areas in nursing homes,
both on branch lines and monitored. Same response as Bobby Gillett about $:
glad I got the total cost right.  According to the Raychem distributor the
only way to properly provide monitoring is with the controller and they
think highly of it.  The wiring, sensors, etc. is very similar to kits
installed many years ago.

Bobby McCullough



-----Original Message-----
From: [email protected]
[mailto:[email protected]] On Behalf Of Steve
Leyton
Sent: Thursday, August 01, 2013 3:16 PM
To: [email protected]
Subject: RE: Heat trace question

These are two isolated areas at a hospital - one over some outdoor seating
at the dining common and the other a canopy that covers trash
enclosures and a couple of service enclosures.   Both are a couple
hundred feet from the service entry and if we built a dry riser there, we
don't have enough room to slope the long run of main to the protected
spaces.   The AHJ is one of those state agencies that has <ahem>
interpreted the standard liberally, and they don't want any dry system that
may be downstream of the riser room no matter how it's configured, so I'm
thinking that trace may be an alternative to the auxiliary drainage and
maintenance issues associated with dry-pipe in this particular application.

Steve 




-----Original Message-----
From: [email protected]
[mailto:[email protected]] On Behalf Of Bobby
Gillett
Sent: Thursday, August 01, 2013 12:03 PM
To: [email protected]
Subject: Re: Heat trace question

Steve,

 I had priced a system about two years ago and learned a lot. I found the
Tyco Raychem system was the best for my scenario; a lot of factors go in to
it - depends on size of piping and length, how much (if any) insulation will
be used, temperatures, and don't forget it has to be listed for FP and
supervised per NFPA 13. We had a local Tyco distributor work up the pricing
- we gave him our plans and he took it off and priced it. I'm glad he did.
I would have missed a lot - this was a big system in a 100'-0+ tower
w/standpipes etc.. It ended up needing two panels for supervisory due to the
length of the cables, etc.

Bobby


On Thu, Aug 1, 2013 at 1:53 PM, Steve Leyton
<[email protected]>wrote:

> Help a warm weather brother out please, with recommendations for heat
> trace systems.   Price, reliability, branch line listings?
>
>
>
> Steve Leyton
>
> PROTECTION DESIGN & CONSULTING
>
> 2851 Camino del Rio South, Suite 400
>
> San Diego, CA 92108
>
> -------------------------------------------------------------
>
> Ph:      858.751.2930 - ext. 102
>
> Fax:    858.751.2933
>
> Cell:  619.972.5696
>
>
>
>
>
>
>
>
>
> _______________________________________________
> Sprinklerforum mailing list
> [email protected]
>
> http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkl
> er.org
>



--
Bobby Gillett
*Living Water Fire Protection, LLC*
1160 McKenzie Rd.
Cantonment, FL 32533
(850) 937-1850
livingwaterfp.com  <http://livingwaterfp.com/>
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler
.org
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to