I am looking at a building that has 12' ceilings (per floor). In one area there 
is a vertical opening to the second floor that is protected with closely spaced 
sprinklers and draft stops. Is it still acceptable to use the quick response 
area reduction or does the opening to the second floor count as a ceiling in 
excess of 20'?

If it is acceptable to use the quick response reduction, can you apply the 
reduction to the length of closely spaced sprinkler heads that must be calc'd?

Matt Grisé PE*, LEED AP, NICET II  
Sales Engineer 
Alliance Fire Protection 
130 w 9th Ave.
North Kansas City, MO 64116

*Licensed in KS & MO 

913.888.0647 ph 
913.888.0618 f 
913.927.0222 cell 
www. AFPsprink.com 