I provided a drawing for an architect that was used for bid purposes. The intent was to have the fire sprinkler contractors all bid "apples-to-apples".
That sort of happened and now the project has been awarded. The FSC has contacted me asking for the drawings of the fire sprinkler layout. I was wondering if any other designers have done this and how you might have treated this situation. Do you provided the drawings upon request? The contractor wants them for free, of course. Is there a liability that I need to be concerned with? The drawings show pipe routing and sizes, but not hydraulic information. Basically, there about 30% drawings with notes. Any other thoughts and comments will be appreciated. Thank you, Bob Knight, CET III 208-318-3057 FBK-LOGO-SMALL