The documentation on workcenters is a little confusing to me. In my scenario I'm mixing powder. My mixer will handle 250 lbs and my finished product is 8 lbs. Does that mean I put in 32 (250/8) under capacity per cycle? Or do I put in 1 because I have 1 machine and increase the other values using the Effective Time mentioned below.
In the equation below what is C? Is that supposed to be = ET and not + TN_ * ET? How do I come up with the ET to then multiple the other fields by? Here is what the documentation says: "Effective time (ET): is a factor that is applied to the three times above to determine the real production time. This factor enables you to readjust the different times progressively and as a measure of machine utilization. You canât readjust the other times because generally theyâre taken from the machineâs data sheet. The total time for carrying out X operations is then given by the following formula: ((C / CA) * TC + TS + TN_ * ET. In this formula the result of the division is rounded upwards. Then if the capacity per cycle is 6 it takes 3 cycles to realize 15 operations." -------------------- m2f -------------------- -- http://www.openobject.com/forum/viewtopic.php?p=33832#33832 -------------------- m2f --------------------
_______________________________________________ Tinyerp-users mailing list http://tiny.be/mailman/listinfo/tinyerp-users