Jones writes:
"Here is a sanitized version of the story cleansed by LTI, but the true grit is 
worse than this
sounds. Bottom of Page 5 is where it gets interesting:"

http://dodfuelcell.cecer.army.mil/library_items/Thermo%282004%29.pdf

Frankly, I'd prefer to read the unsanitized 'true grit'!  Its usually much more 
interesting and
entertaining!

In the interest of fairness, I think we should put the text from that report 
here and let the
readers decide for themselves...

My reading of the text below is that its about as antiseptic as it gets!  It 
indicates that the New
Hampshire facility, which was set up by LTI and CTC (people in the USA) and 
under their control, had
the same kinds of manufacturing problems as occurred at the Italian 
manufacturer. Perhaps its
because Rossi hadn't given them the proper recipe for making the TE devices?

Did LTI 'sanitize' the Report to save face with the DoD because their decision 
to work with Rossi
turned sour and didn't produce anything of value???  Only the LTI Execs and 
Rossi know the answer to
that Q.

I do wonder why LTI/DoD didn't take the TE devices that were generating 20% 
efficiencies and
sacrifice one in order to perform XRD and other forensic analyses on it to 
determine if they had the
right 'recipe'...

It also wouldn't surprise me if the fire in Rossi's lab was caused by an early 
prototype of the
E-Cat going into a run-away condition and Rossi not being able to stop it in 
time.. Or it happening
at night when no one was there!

-Mark

========== EXCERPT FROM DOD REPORT ==================

Leonardo Technologies, Inc.

LTI was incorporated as a response to the thermoelectric power generation 
research
by Dr. Andre Rossi. Dr. Rossi indicated that his devices would produce 20
percent efficiencies, a vast increase from the current science of 4 percent 
conversion
of waste heat to electrical power. Dr. Rossi believed that he could increase
the physical size of the TE Devices and maintain superior power generation. In
furtherance of his research, in early 2000, LTI had tests conducted at the 
University
of New Hampshire (UNH), Durham, NH, using a small scale LTI TE Device.
Over a period of 7 days, the UNH power plant staff recorded voltage and
amperage readings every 1/2 hr. The TE Device produced approximately 100
volts and 1 ampere of current, providing 100 watts of power. After this initial 
success, and a fire that destroyed his Manchester, NH location, Dr. Rossi 
returned
to Italy to continue the manufacture of the TE Devices. 

In Italy, Dr. Rossi believed that LTI could manufacture more cost-effective TE 
generating devices with lower labor and assembly costs. Accordingly, Dr. Rossi 
engaged 
a subcontractor to fulfill the requirements of manufacturing and assembly.
Unfortunately, the Italian subcontractor was unable to provide second-generation
TE Devices with satisfactory power generation. Nineteen of 27 TE
devices shipped to CTC, Johnstown, PA, were incapable of generating electricity
for a variety of reasons, from mechanical failure to poor workmanship. The 
remaining
eight produced less than 1 watt of power each, significantly less than
the expected 800-1000 watts each. Appendix C documents TE Device testing.

In an effort to determine, and possibly correct the reasons for TE Device 
failures,
LTI personnel traveled to the Italian laboratory. The common theme that began
to emerge was the inability to upgrade from small-scale TE modules to large 
scale
multiple module TE Devices with large footprints. The most fundamental
reason for the LTI second-generation TE Devices' failure was the complex thermal
expansion interplay among the various components. Contributing to the TE
Device failure were the large number of soldered electrical connections (over 
80),
the inability to match the thermal expansion rates of the mono-block cooling
tanks to the circuit boards and to the semiconductor materials, all within the
clamp pressure or the retaining hardware in the grip of high temperature 
adhesives.

After a month of research and observation at the Italian laboratory, it was 
determined
that the best way to proceed would be to develop an independent laboratory
in New Hampshire so that two development facilities could work at the
problems from two separate locations and viewpoints. During this period of
time, the Italian laboratory continued to deliver TE materials, but none that 
exceed
the current science of TE power generation.

LTI Develops New Hampshire Laboratory

Beginning in mid-2002, the LTI-NH laboratory was designed with the technical
assistance of CTC personnel. By September, TE materials were being manufactured.
The final piece of equipment, the Directional Fusion Machine, was installed
by December of 2002, at which time ingot manufacture was possible. As
in Italy, the New Hampshire laboratory encountered manufacturing challenges.

Outside experts were engaged and were able to assist laboratory personnel in
working through the roadblocks. The New Hampshire laboratory equipment
was designed to allow for adjustments of almost every parameter in the TE
manufacturing process, including, but not limited to:
. various metals and their proportional blends
. times and depths of both the vacuum and backfilling with inert gases
. times, temperatures, and oscillation speeds for melting, compounding, and
recompounding
. size of P- and N-type semiconductors, varying both diameters and thickness
of the wafers
. size of TE Devices based on semiconductor geometry.
=============================================================


Reply via email to