Hi cüneyt köker,

Are you using operation scheduling or job scheduling? In my opinion, it is 
better to use operation scheduling, means that the system will calculate the 
scheduling based on the total availability of work centers in a work center 
group (for example, if the machine2 is not available at this time, when you run 
the schedule, the system will calculate the availability of the related work 
group of these 3 machines, and only consider availability of machine1 and 
machine3). You may try this one. And don't forget to select 'finite capacity' 
on the Production Parameter (on tab Standard Update). Hope can help.


Best Regards,



Ferry Widjaja

--- In Axapta-Knowledge-Village@yahoogroups.com, cüneyt köker <c_ko...@...> 
wrote:
>
> 
> 
> Hi All,
>  
> Is there any way to set up the following case in AX?
>  
> A specific product can be produced on Machine1 (10 min/pcs), Machine2 (15 
> min/pcs) and Machine3 (8 min/pcs) with different process times. Machine1 is 
> selected as work center on the route operation. I want to make AX consider 
> other two machines too if they are available when scheduling. And when doing 
> this, it must consider their different process times and schedule them that 
> way.
>  
> I know that task groups are used for similar purpose but it is not possible 
> to define different times by machine there.
>  
>  
> Thank you in advance,
>  
> Cuneyt
>