Hi,

U can create 3 diferent route versions for the same item and then while running 
the master planning u can select the option of "route versions" or while 
updating the status of production order u can select the appropriate route out 
of the 3 versions and can see the different process times as per the route 
selected in capacity reservations. Hope this will help..... 

-Tushar

--- On Wed, 3/6/09, cüneyt köker <c_ko...@yahoo.com> wrote:

From: cüneyt köker <c_ko...@yahoo.com>
Subject: [Axapta-Knowledge-Village] Alternative workcenter with different 
process time
To: Axapta-Knowledge-Village@yahoogroups.com
Date: Wednesday, 3 June, 2009, 1:03 PM











    
            
            


      
      

Hi All,
 
Is there any way to set up the following case in AX?
  
A specific product can be produced on Machine1 (10 min/pcs), Machine2 (15 
min/pcs) and Machine3 (8 min/pcs) with different process times. Machine1 is 
selected as work center on the route operation. I want to make AX consider 
other two machines too if they are available when scheduling. And when doing 
this, it must consider their different process times and schedule them that way.
  
I know that task groups are used for similar purpose but it is not possible to 
define different times by machine there.
 
 
Thank you in advance,
 
Cuneyt


      
 

      

    
    
        
         
        
        








        


        
        