Hi

It is a good and nearest solution, I appreciate the thought process.



 
--- In Axapta-Knowledge-Village@yahoogroups.com, Anton Ivanov 
<anton_ivanov...@...> wrote:
>
> Hi,
> One possible solution could be to use field “Efficiency percentage” in 
> work center card.
> This is the short description about the field in AX help file: “You can 
> reduce or increase the processing time of individual jobs per day by using 
> the efficiency percentage. Example If a job requires six hours according to 
> the setup for the operation, and the efficiency percentage for the work 
> center is 50 percent, the job will then reserve capacity for three hours on 
> the first day and three hours on the second day.”
>  Best regards,
> AI
> P.S. Such parameter is available also in Calendars
> 
> --- On Wed, 6/3/09, cüneyt köker <c_ko...@...> wrote:
> 
> 
> From: cüneyt köker <c_ko...@...>
> Subject: [Axapta-Knowledge-Village] Alternative workcenter with different 
> process time
> To: Axapta-Knowledge-Village@yahoogroups.com
> Date: Wednesday, June 3, 2009, 5:33 AM
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> Hi All,
>  
> Is there any way to set up the following case in AX? 
>   
> A specific product can be produced on Machine1 (10 min/pcs), Machine2 (15 
> min/pcs) and Machine3 (8 min/pcs) with different process times. Machine1 is 
> selected as work center on the route operation. I want to make AX consider 
> other two machines too if they are available when scheduling. And when doing 
> this, it must consider their different process times and schedule them that 
> way. 
>   
> I know that task groups are used for similar purpose but it is not possible 
> to define different times by machine there. 
>  
>  
> Thank you in advance,
>  
> Cuneyt
>