Thanks.

But it is not possible to choose the desired route version every time we run 
the master planning. we want mp choose the best route automatically.       





--- In Axapta-Knowledge-Village@yahoogroups.com, Tushar Joshi 
<tushar_s_jo...@...> wrote:
>
> Hi,
> 
> U can create 3 diferent route versions for the same item and then while 
> running the master planning u can select the option of "route versions" or 
> while updating the status of production order u can select the appropriate 
> route out of the 3 versions and can see the different process times as per 
> the route selected in capacity reservations. Hope this will help..... 
> 
> -Tushar
> 
> --- On Wed, 3/6/09, cüneyt köker <c_ko...@...> wrote:
> 
> From: cüneyt köker <c_ko...@...>
> Subject: [Axapta-Knowledge-Village] Alternative workcenter with different 
> process time
> To: Axapta-Knowledge-Village@yahoogroups.com
> Date: Wednesday, 3 June, 2009, 1:03 PM
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
> 
>     
>             
>             
> 
> 
>       
>       
> 
> Hi All,
>  
> Is there any way to set up the following case in AX?
>   
> A specific product can be produced on Machine1 (10 min/pcs), Machine2 (15 
> min/pcs) and Machine3 (8 min/pcs) with different process times. Machine1 is 
> selected as work center on the route operation. I want to make AX consider 
> other two machines too if they are available when scheduling. And when doing 
> this, it must consider their different process times and schedule them that 
> way.
>   
> I know that task groups are used for similar purpose but it is not possible 
> to define different times by machine there.
>  
>  
> Thank you in advance,
>  
> Cuneyt
> 
> 
>       
>  
> 
>       
> 
>     
>     
>       
>        
>       
>       
> 
> 
> 
> 
> 
> 
> 
> 
>       
> 
> 
>       
>       
> 
> 