At SONGS, the outage dose goal is set prior to the outage like all sites.  At the onset of the outage, we had  higher than expected dose rates (crud burst with new generators) and revised our outage dose goal accordingly.   Would your site have revised the outage goal is similar event occurred?  

In addition, during the outage it has been determined that additional emergent work will be required to support increased inspections on our steam generators which is dose impacting.  Would your site revise your outage dose goal a second time based upon the increased emergent work expected?  Or would your site maintain your revised dose goal as is and track the emergent dose as separate goal?