Surry Power Station would like to know if you require survey instruments used 
to down post High Radiation Areas to be source checked after the down posting 
survey is completed?

At Surry, survey instruments used to down post HRA are source checked after the 
down posting survey is completed.

Thanks,


John M. Sukosky, CHP
Health Physicist III
Radiological Protection, Surry Power Station

Dominion Generation
Phone: 757-365-2594; Internal: 8-798-2594
Fax: 757-365-2668
Pager: 804-273-3030 3636; E-mail: 
[email protected]<mailto:[email protected]>



From: [email protected] [mailto:[email protected]] On Behalf Of 
[email protected]
Sent: Wednesday, March 21, 2012 7:52 PM
To: [email protected]
Subject: RE: Powernet: Quick Question (Outage Dose Goal Revision?)

Under these conditions Palo Verde would convene an ALARA Committee meeting and 
revise the outage dose goal upward; conversely, if conditions were much lower 
than anticipated we would use the same process to lower the goal.  Fortunately, 
we have done the latter numerous times.  The upward revision based on emergent 
work / scope change is also approved by the ALARA Committee as a stretch goal 
(amount estimated above the original estimate).  While the final reported RFO 
dose would include all work, the ALARA incentives offered to employees are 
based on the original dose estimation; thereby. not penalizing (and 
disincentivizing) them because of conditions beyond their control.


From: [email protected] [mailto:[email protected]] On Behalf Of 
[email protected]
Sent: Thursday, February 23, 2012 1:05 AM
To: [email protected]
Subject: Powernet: Quick Question (Outage Dose Goal Revision?)

At SONGS, the outage dose goal is set prior to the outage like all sites.  At 
the onset of the outage, we had  higher than expected dose rates (crud burst 
with new generators) and revised our outage dose goal accordingly.   Would your 
site have revised the outage goal is similar event occurred?

In addition, during the outage it has been determined that additional emergent 
work will be required to support increased inspections on our steam generators 
which is dose impacting.  Would your site revise your outage dose goal a second 
time based upon the increased emergent work expected?  Or would your site 
maintain your revised dose goal as is and track the emergent dose as separate 
goal?

Thanks,

"Stevie Ray" Vaughan
[email protected]
----------------------------------- Powernet - a service of the Health Physics 
Society Power Reactor Section Powernet archives at 
http://www.mail-archive.com/[email protected]/ Reply to: [email protected] If 
Questions, contact Mike Russell, CHP at [email protected]
--- NOTICE ---

This message is for the designated recipient only and may contain confidential, 
privileged or proprietary information.  If you have received it in error, 
please notify the sender immediately and delete the original and any copy or 
printout.  Unintended recipients are prohibited from making any other use of 
this e-mail.  Although we have taken reasonable precautions to ensure no 
viruses are present in this e-mail, we accept no liability for any loss or 
damage arising from the use of this e-mail or attachments, or for any delay or 
errors or omissions in the contents which result from e-mail transmission.


CONFIDENTIALITY NOTICE:  This electronic message contains
information which may be legally confidential and/or privileged and
does not in any case represent a firm ENERGY COMMODITY bid or offer
relating thereto which binds the sender without an additional
express written confirmation to that effect.  The information is
intended solely for the individual or entity named above and access
by anyone else is unauthorized.  If you are not the intended
recipient, any disclosure, copying, distribution, or use of the
contents of this information is prohibited and may be unlawful.  If
you have received this electronic transmission in error, please
reply immediately to the sender that you have received the message
in error, and delete it.  Thank you.

Reply via email to