All,
At DCPP, we are implementing a new process - putting a SAM in  our hot tool 
crib.
Answers to the questions below will be much appreciated.
Please reply all. Craig is not a member yet.
Thanks,
Monica Barnby
PG&E DCPP
Health Physicist
805 545 3566

From: Sutton, Craig
Sent: Tuesday, April 09, 2013 4:40 PM
To: Barnby, Monica
Subject: Powernet questions

Does your station survey all tools returned to the RCA tool room / tool crib 
for contamination?

IF so...
Does your station use a tool monitor / SAM as part of the survey process?

IF so...
What set point is used for the tool monitor / SAM?

Are surveys performed by RP Technicians or tool room craft?

IF RP Technicians...
Is this task routinely assigned or by request?

Are unsurveyed tools ever available for craft use or segregated until surveyed?



Respectfully,
Craig D. Sutton
Radioactive Materials Engineer
Pacific Gas & Electric Company
Diablo Canyon Power Plant
MS 104/2/216
PO Box 56
Avila Beach, CA 93424

P: 805.545.4208 | C: 805.748.0603 | [email protected]<mailto:[email protected]>