The diagrams in NFPA 20 show the connection for the test header prior to the valve on the discharge side of the pump. However, the diagrams are located in the appendix and I can't seem to find any text reference to it within the standard. Coul; someone enlighten me if the is any and if so, where? I've called for this and am being challenged by an engineer. Thanks