The diagrams in NFPA 20 show the connection for the test header prior
to the valve on the discharge side of the pump. However, the diagrams
are located in the appendix and I can't seem to find any text
reference to it within the standard. Coul; someone enlighten me if
the is any and if so, where? I've called for this and am being
challenged by an engineer. Thanks
Todd G. Williams, PE
Fire Protection Design/Consulting
Stonington, Connecticut
www.fpdc.com
860.535.2080