Russell,

The reason that some are saying consult your attorney is that depending
on the type of project, the trade contractor has a set of expectations
for the bid documents and your attorney can better define your right for
recovery of costs.

Depending on whether the project is a "private" or "public"; if
"private" then the contract documents should spell out what takes
preference, drawings, documents or code. 

First and foremost, the design of the automatic fire sprinkler system is
the responsibility of the design professional under most state
engineering laws and according to the SFPE "White Paper" a trade
contractor and/or design technician can only prepare fire protection
shop drawings in conformance with engineering design documents (bid
documents from the Owner) or in strict compliance with the NFPA
standards. 

If a "public" project then the Owner's design professional needed to
provide to the contractor, documents that are complete, clear and
accurately defines the scope of work as established in U.S. Supreme
Court, U. S.  v. Spearin, 248 U.S. 132 (1918). The court found that a
contractor has a right to expect the Owner to provide construction
documents that are complete, correct and accurate. Federal case law
supports the premise that contractors are not responsible for defects in
plans and specifications, and a contractor's duty to check plans does
not impose an obligation on the contractor to ensure the design will
meet its purpose.     

There are various facets of the law that varies by legal jurisdictions
and your attorney can best define the rights that the contractor hasto
recover cost and delays. 

Have a fire safe day!
  

Jim Davidson 
 
Davidson Associates 
302-994-9500

-----Original Message-----
From: [EMAIL PROTECTED]
[mailto:[EMAIL PROTECTED] On Behalf Of Russell
Sent: Thursday, December 04, 2008 11:01 AM
To: [email protected]
Subject: RE: Spec's. vs. Drawings

We generally approach projects with humility just to be sure we don't
get on
the wrong side of the AHJ whom we will most likely be working with in
the
future, including the general contractors. We have had some of the
contract
documents state the items that have precedence but that is most often
not
the situation. Probably 90% or more documents have spec's. that are
generic
and just pulled off a shelf and stuck into the project and are loaded
with
lots of things that are not even closely related to the project at hand.
We
will RFI some things sometimes considering the impact but in this case I
did
not feel an RFI was needed but after the system was completed is when
the
architect wanted to go by the spec's. and not the drawings. It's not a
big
deal to make the alterations so we are going to roll over just to keep
good
relations but this instance did bring up the question of is it on paper
or
just understood when there is nothing noted in the spec's. or on the
drawings stating the precedence without RFI'ing every item which may not
agree with each other which in some cases be quite a lot. Doing that, I
have
found, can make me come across to the G.C. and engineer as being very
picky
which gives them the feeling that we are going to be hard to get along
with.
This I work hard to make sure doesn't happen unless there's a lot of
money
involved!

Thanks all for the input.





Russell Rewis
Brown Automatic Sprinklers, Inc.
107C Hemlock Street
Valdosta, Georgia 31601
229-244-8130
[EMAIL PROTECTED]


_______________________________________________
Sprinklerforum mailing list
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
For Technical Assistance, send an email to:
[EMAIL PROTECTED]

To Unsubscribe, send an email
to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)


_______________________________________________
Sprinklerforum mailing list
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
For Technical Assistance, send an email to: [EMAIL PROTECTED]

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

Reply via email to