So if you're working in an occupied residential bldg. and you have to shut
down a floor for 24 hrs., what precautions to do take?  Or more importantly,
what approach do you take with regard to impairments to the remainder of the
occupants and the building?  After explaining why you (not you but all) wait
24 hrs. and the other guy doesn't, and even showing why, assuming they
decide to go with you, do you have a written impairment plan to follow?  How
do you handle FD concerns?
I'm there right now and wondering.
TD


I ALWAYS use the 24 hour cure time and maybe longer, depending on
temperature and humidity.



24 hours are required by some of the insurance companies. It is a helpful
way to mitigate water damage. We observe them. Owner must provide fire
watch.., as required by 101.
 
When you look in whichever flavor of CPVC manual you have, be aware of the
temps this time of year. If I am remembering correctly, there is a temp and
size that you are not allowed to glue at all until the temp in the room is
at that level.

R/
Matt

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

For Technical Assistance, send an email to: [email protected]

To Unsubscribe, send an email to:[email protected]
(Put the word unsubscribe in the subject field)

Reply via email to