Can someone tell me how will the time be captured for the subcontracting (Service type) item please. Coz My gant chart should capture the lead time for procurement of the subcontracted item when I schedule the jobs. Instead, it schedules the first operation instantly after the second operation. There is something called finite material and finite capacity planing. Where do i select the checkbox for finite material planning.
Please suggest. -- With Regards, Mr. Vishtaspa Sethna Associate E.R.P. Consultant Godrej Infotech Ltd. Cell: +919718010823