Thanks Harry
 
Kind of getting you although probably not 100%
 
The production orders planned start date should be based on when the
material is available
If the material is delayed then the start date of the production orders
should be delayed and the user warned if they will miss the delivery date
 
I believe this is how the master planning is doing in AX (for single item)
if everything is still in the planned status. But once firmed then I think
AX master planning does not really give a good indication to the user 
 
Thanks
James
 
 


  _____  

From: Axapta-Knowledge-Village@yahoogroups.com
[mailto:[EMAIL PROTECTED] On Behalf Of Harry
Deshpande
Sent: 24 November 2008 12:22
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: RE: [Axapta-Knowledge-Village] Re: Grouping of production orders
for planning




Hi James

Planned prod orders during coverage are scheduled backward from delivery
date and during futures are scheduled forward from requirement date.

In theory planned prod orders at (only for products at level 0) can be
scheduled forward from some date however what do you want to do in case such
products cannot be manufactured before the delivery date?

Regards

Harry

From: Axapta-Knowledge-Village@yahoogroups.com
[mailto:[EMAIL PROTECTED] On Behalf Of James Flavell
Sent: Sunday, November 23, 2008 5:31 PM
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: RE: [Axapta-Knowledge-Village] Re: Grouping of production orders
for planning

Thanks Sayeed,

I think maybe I didnt make it clear that each production order is for
different items.  I dont think the grouping you are talking about works in
this case right?

Thanks
James

  _____  

From: Axapta-Knowledge-Village@yahoogroups.com
[mailto:[EMAIL PROTECTED] On Behalf Of ax_con
Sent: 23 November 2008 16:38
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: [Axapta-Knowledge-Village] Re: Grouping of production orders for
planning

HI James,

The planned production orders can be merged as one group, or one 
production order from the Planned orders form...but once these orders 
are firmed you can split them but cannot merge...

Hope this helps

Regards

Sayeed

--- In Axapta-Knowledge- <mailto:Axapta-Knowledge-Village%40yahoogroups.com>
[EMAIL PROTECTED], "James Flavell" 
<[EMAIL PROTECTED]> wrote:
>
> Good morning everyone
> 
> I am not a master planning or production expert so not sure if my
> requirement is available in std AX. If it is not I would for sure 
appreciate
> hearing from anyone who has considered or managed to address the
> requirement.
> 
> What I need to be able to do is group all production orders for a 
given
> sales order so that master planning plans them all for the same 
start date.
> So if I have 10 production orders that master planning treats them 
as one
> and works out the latest delivery date of any of the 10s components 
and then
> plans that all 10 will start at that time (even if for some of the
> production orders master planning can see they could start 
earlier). Of
> course following on from this would be to have all the planned 
purchase
> orders suggested based on the start date of the grouped production 
order etc
> 
> I believe this is quite a difficult thing to do but would like to 
know if
> there is anyway (std or otherwise)
> 
> Thanks
> James
>

 