Being a user of the AutoSprink program, I have been doing 3D drawings for
about the last 4 years.  I find it does help out quite a bit in certain
aspects of the design process.  However, on these "Navis" projects, I am
finding that the design budget is about 3-4x the cost (therefore time) of
doing regular 2D drawings and having coordination meetings.  I have spoken
with several colleagues that are involved in 3D projects and find that 3-4x
number seems to be the going multiplier for this 3D setup.

Also, it is vital that the architect be available during all 3D coordination
meetings.  I am working on one project where there have been arguments over
a small area with 2' of space above the ceiling and 4' of junk to go in
there.  This one area has been going on for 7 weeks now.  The architect is
not available during the coordination meetings and the RFI process can be
very long.

Overall, I think Ron hit it on the head.  It is basically a 3D retrofit for
the sprinkler guy.  We try to set boundaries of where we will put piping.
But, when the HVAC needs to get into our space, we are typically req'd to
move.

I believe in a few years, all new construction will be 3D drawings.
Hopefully, the kinks will be worked out by then.

T

-----Original Message-----
From: [EMAIL PROTECTED]
[mailto:[EMAIL PROTECTED] On Behalf Of Steve Leyton
Sent: Tuesday, November 11, 2008 12:35 PM
To: [email protected]
Subject: RE: White papers and definition of roles and 3D and whatnot

3D coordination is right where sprinkler design software was 12-15 years
ago - an emerging technology.   As a consultant firm that does a lot of
work with architectural clients, we are being asked more and more to draw in
3D or have 3D capability; its use so far has been primarily as a
coordination tool by the construction teams working off of our design
teams' documents.   As such, we still haven't made a binding commitment
to Revit or any other particular program, and Navis remains the coordination
platform of choice because you can easily load conventional 2D CAD files and
make it spin.  

Speaking just for myself and based on our experiences to date, I would
characterize 3D as purely a garbage-in-garbage-out exercise.   We have a
large and very complicated hospital project in construction now, a 3-floor
tenant improvement for which the scope of sprinkler work is to add drops to
existing shell branch piping installed about 4 years ago.
The work was "coordinated" in 3D by a "3D consultant".   Which means two
skateboarders with Cheetos stains on their fingers in this case.   They
identified countless "conflicts" that weren't and missed several others that
were, leading to dozens of hours of paperwork for both design and
construction team members to sort out RFI's, sketches and field
conditions.   It was, in a word, a FIASCO.   We have another much
smaller project, also going into construction, where we and the other trades
have managed to thread the needle in several exceptionally tight situations
and it has gone smoothly.  Not surprisingly, this work was managed by one of
the subs, and not by an outside "consultant" (insert self-deprecating joke
HERE). 

It is unquestionably the platform of the future and when used by a
knowledgeable technician can be a powerful tool.   But there's a
honeymoon period that we need to move on from, in which certain
opportunistic engineers and CAD technicians are representing their services
as something more - sometimes much more - than they can actually deliver.

Steve Leyton
Protection Design & Consulting
San Diego, CA


-----Original Message-----
From: [EMAIL PROTECTED]
[mailto:[EMAIL PROTECTED] On Behalf Of GAYLE KNOWLES
Sent: Tuesday, November 11, 2008 10:57 AM
To: sprinklerforum
Subject: RE: White papers and definition of roles


that's right, what Ron said.  And besides the fact, we all know where the
design problems are in all the different constructions and occupancies when
we prepare our bids.  The 3D is great if everyone sits done at the table
during the construction meetings and signs off on coordination drawings
showing elevations etc.  Doesn't do much good in bidding, when the
electrician decides to run his cable trays wherever he wants after the fact.
If your bid is that tight, counting on the electrician to run his trays "as
shown conceptually", you are out of luck.> 

Date: Tue, 11 Nov 2008 11:13:32 -0700>
From: [EMAIL PROTECTED]> To: [email protected]>
Subject: RE: White papers and definition of roles> > 

Right on George. With all the special systems I would expect more than> $2k
difference in the specialty equipment quotes and the prices should> be
closer if you take away the opportunity for innovation of design by> the
bidders.> > Our prices are higher on jobs requiring 3D or BIM. We find there
is very> little coordination and more "here is where we are so now you>
(sprinkler) can go around us. It's like a 3D retrofit. The only thing> that
changes is we spend more design time to come up with the same> product.
Besides we FP contractors have been doing 3D since
the> beginning of time, it's just that the presentation has been 2D.

 

__________ Information from ESET NOD32 Antivirus, version of virus signature
database 3603 (20081111) __________

The message was checked by ESET NOD32 Antivirus.

http://www.eset.com
 
_______________________________________________
Sprinklerforum mailing list
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
For Technical Assistance, send an email to: [EMAIL PROTECTED]

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

__________ NOD32 3603 (20081111) Information __________

This message was checked by NOD32 antivirus system.
http://www.eset.com


_______________________________________________
Sprinklerforum mailing list
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
For Technical Assistance, send an email to: [EMAIL PROTECTED]

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

Reply via email to