But I have seen it work and so as the eternal optimist....On the other hand, to paraphrase a character from Blood Diamond: My heart tells me it is the answer, though my experience would suggest otherwise.
On Tue, Nov 11, 2008 at 12:05 PM, George Church <[EMAIL PROTECTED]> wrote: > After spending a year talking about Cx, I can't give you a warm and fuzzy > feeling that a commissioning agent is going to do much more than document > the errors, get the obvious corrected, and wouldn't surprise me if there are > issues logs with some skeletons buried in the As Builts and O&M's. > > Same as so many threads on this Forum- there aren't enough skilled workers > to do everything that needs skill, and so those of us that "get it" are > frustrated cause we know we can all do better, and we try to accommodate the > appearance of Murphy at every step- and still be low bidder, or low enough > to get a chance at selling something besides just cheap. > > I suspect this will be accentuated when we face 16+ bidders on most jobs > this year. > > Glc > The above certainly isn't an opinion from NFPA. > > -----Original Message----- > From: [EMAIL PROTECTED] > [mailto:[EMAIL PROTECTED] On Behalf Of Ron Greenman > Sent: Tuesday, November 11, 2008 2:15 PM > To: [email protected] > Subject: Re: White papers and definition of roles > > This si why a commissioning agent is necessary from the start of the > project throughout the life of the building is necessary. Of course > that costs money and guys that can afford buildings big enough to have > big time coordination problems have to be pretty rich and they, > "...didn't get rich by writing a lot of checks." (Bill Gates to Homer > Simpson just before the Microsoft goons "buy out" Homer's undefined > internet business.) Commissioners cost money and it appears to be far > cheaper (though it's not) to let the contractors fight it out. > > On Tue, Nov 11, 2008 at 10:56 AM, GAYLE KNOWLES <[EMAIL PROTECTED]> wrote: >> >> that's right, what Ron said. And besides the fact, we all know where the > design problems are in all the different constructions and occupancies when > we prepare our bids. The 3D is great if everyone sits done at the table > during the construction meetings and signs off on coordination drawings > showing elevations etc. Doesn't do much good in bidding, when the > electrician decides to run his cable trays wherever he wants after the fact. > If your bid is that tight, counting on the electrician to run his trays "as > shown conceptually", you are out of luck.> Date: Tue, 11 Nov 2008 11:13:32 > -0700> From: [EMAIL PROTECTED]> To: [email protected]> > Subject: RE: White papers and definition of roles> > Right on George. With > all the special systems I would expect more than> $2k difference in the > specialty equipment quotes and the prices should> be closer if you take away > the opportunity for innovation of design by> the bidders.> > Our prices are > higher on jobs requiring 3D or BIM. We find there is very> little > coordination and more "here is where we are so now you> (sprinkler) can go > around us. It's like a 3D retrofit. The only thing> that changes is we spend > more design time to come up with the same> product. Besides we FP > contractors have been doing 3D since the> beginning of time, it's just that > the presentation has been 2D.> > Ron Fletcher> Aero Automatic> Phoenix, AZ> >> -----Original Message-----> From: > [EMAIL PROTECTED]> > [mailto:[EMAIL PROTECTED] On Behalf Of George> > Church> Sent: Tuesday, November 11, 2008 7:00 AM> To: > [email protected]> Subject: RE: White papers and definition > of roles> > Ummm, maybe the two bidders had breakfast together on bid > morning?> Don't throw your elbow out patting yourself on the back.> > > Coincidence or a comp price is far more likely to produce bids within> > .001%> of each other than quality of the bid documents. > > Seriously, if > you'd given em a stocklist, a finished, coordinated dwg,> and a> rational > schedule, there'd be more difference in the price than this> just on> how > different companies allocate OH, backlog needs, lift pricing renting> vrs> > owning, mileage from office to site variance, mix of each contractor's> > design talent pool $ cost, workman's comp experience reflected in what> > could> be drastically different rates, skill of the two estimators, whether> > someone> got something last night- > There are so many variables, I'd > suspect a comp number before a headless> piping layout as the root cause for > the close resemblance.> > glc> > -----Original Message-----> From: > [EMAIL PROTECTED]> > [mailto:[EMAIL PROTECTED] On Behalf Of> > [EMAIL PROTECTED]> Sent: Tuesday, November 11, 2008 8:46 AM> To: > [email protected]> Subject: RE: White papers and definition > of roles> > Speaking of bid prices. We performed our first AutoCAD based 3D> > integration> of fire protection on a recent project. Our typical corporate> > deliverable> is the design criteria and a floor plan with equipment on it. > (I have> had a> couple complete installation level design requests but they > are rare in> this> industry) Typical criteria based design, no piping, or > heads or> anything> else. (because the contractor will do it for free). > Anyway, as we've> progressed into the 3D realm I've pushed to get fire > protection included> in> the 3D modeling. Convincing the powers that be that > by at least> including> mains and branch lines into the model and > coordinating their locations> and> elevations will aid the contractor during > installation, reduce his> design> time and reduce change orders and bring us > tighter bids as there is less> for> the imagination and more solid > information to work with.> > So they let us do the piping layout but no > heads, so we did the layout> in> the model dealing with equipment, steel and > other modeled obstructions.> > > Two weeks ago the project went out for > bids. We had 3 bidders. One> dropped> out due to various personal reasons > but the bids came back yesterday> from> the other two.> > The fire > protection bids on the project were within $2,000 of each> other.> Now that > may not sound like a big deal but understand the total above> ground> fire > protection is valued at almost $1.5 million dollars. > > For two bidders to > be that close is pretty unusual. But it validated> the> need for better > design other than the old floor plan with the note> "follow> NFPA 13" and > similar stuff.> > Hopefully we can continue this trend within our company. I > know this> would> be difficult for many companies because there is a lack of > qualified> people> who can actually layout a fire protection system and this > project ran> the> gamut of system types from wet, dry, pre-action, > foam-water deluge, low> expansion foam, dry chemical, CO2 and a proprietary, > IR triggered, high> speed, deluge curtain system (that is really cool by the > way). > > Now I'm hoping that our management sees the value in this effort > and> will> continue down this path. Convincing some to allow us to provide > more> than> the bare minimum of fire protection information is a tough > fight. For> whatever reason is has been for years. Maybe it has to do with > the lack> of> qualified people, some of it is based on economics, some of it > is> perceived> value, like I said, most AE firms feel the contractor > provides the> engineering effort for free so why do anything other than a > spec and> some> fancy notes.> > I actually had one PM complain that the > sprinkler contractors ALWAYS put> their pipe in the wrong place and it has > to be torn down and removed.> He> caught me on a good day so I graciously > (stop snickering) reminded him> of> the directive we typically give > sprinkler contractors: 1. coordinate> with> everyone and everything. But at > the same time all we give them is a> floor> plan of the building, no process > piping layouts (because there is no> such> animal), no steel plans, no duct > layouts, etc. So how can he coordinate> with things that don't exist or > haven't been designed yet? Hence my> sales> pitch for getting it in the > model and then giving that info to the> contractor. > > But this is one I > will put in the WIN column. They come far and few> between> so forgive me > while I savor the moment....................> > > > > Craig L. Prahl, CET > > Fire Protection Specialist> Mechanical Department> CH2MHILL> Lockwood > Greene> 1500 International Drive> PO Box 491, Spartanburg, SC 29304-0491> > Direct - 864.599.4102> Fax - 864.599.8439> [EMAIL PROTECTED]> > http://www.ch2m.com > > > -----Original Message-----> From: > [EMAIL PROTECTED]> > [mailto:[EMAIL PROTECTED] On Behalf Of Mark> > Sornsin> Sent: Monday, November 10, 2008 6:16 PM> To: > '[email protected]'> Subject: RE: White papers and definition > of roles> > Then there are those jurisdictions such as ND where you not only > don't> get> registered in a specific discipline, but complaints will not be> > investigated> unless there is a problem with the design. E.g., simply being > trained in> structural engineering and signing someone's sprinkler system > design is> not> a problem that will be investigated. It may violate the > engineers' code> of> ethics, but it won't see action from the State Board > unless there arises> some issue with the design. So if you're a PE not > trained in sprinkler> design, just get some non-PE designer to complete the > work and then you> can> seal it. Effectively there is no problem. If the > building burns as a> result> of improper design, then you've got a problem.> >> Of course, how many MEs even attempt to design a system? It's pretty> > difficult to hold an engineer to the fire when his "design" boils down> to> > "do it per code." I have had MEs ask me why I would ever attempt to> > provide> a complete sprinkler system design. They wonder, "doesn't that > expose> you> to more liability?" Gee, and here I thought design and the > associated> liability was the whole point of our profession.> > But that > leads us right back to Thom's point about doing whatever is> easiest. And > when an ME gets paid on a percentage of construction,> there's> no sense > putting time into a project and exposing himself to more> liability.> > Besides, his lack of effort will typically result in higher bid prices> and> > therefore higher fees. And the contractors don't want to rock the boat> > because the engineer may make their life more difficult. So the cycle> > continues.> > I ought to write an article...> > Mark A. Sornsin, PE> Fire > Protection Engineer> Ulteig Engineers, Inc.> 3350 38th Avenue S.> Fargo, ND > 58104-7079> > [EMAIL PROTECTED]> > > _______________________________________________> Sprinklerforum mailing > list> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> For > Technical Assistance, send an email to:> [EMAIL PROTECTED]> > To > Unsubscribe, send an email> to:[EMAIL PROTECTED]> > (Put the word unsubscribe in the subject field)> > > _______________________________________________> Sprinklerforum mailing > list> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> For > Technical Assistance, send an email to:> [EMAIL PROTECTED]> > To > Unsubscribe, send an email> to:[EMAIL PROTECTED]> > (Put the word unsubscribe in the subject field)> > > _______________________________________________> Sprinklerforum mailing > list> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> For > Technical Assistance, send an email to: [EMAIL PROTECTED]> > To > Unsubscribe, send an email to:[EMAIL PROTECTED]> (Put > the word unsubscribe in the subject > field)_______________________________________________ >> Sprinklerforum mailing list >> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum >> For Technical Assistance, send an email to: [EMAIL PROTECTED] >> >> To Unsubscribe, send an email to:[EMAIL PROTECTED] >> (Put the word unsubscribe in the subject field) >> > > > > -- > Ron Greenman > at home.... > _______________________________________________ > Sprinklerforum mailing list > http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum > For Technical Assistance, send an email to: [EMAIL PROTECTED] > > To Unsubscribe, send an email to:[EMAIL PROTECTED] > (Put the word unsubscribe in the subject field) > > _______________________________________________ > Sprinklerforum mailing list > http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum > For Technical Assistance, send an email to: [EMAIL PROTECTED] > > To Unsubscribe, send an email to:[EMAIL PROTECTED] > (Put the word unsubscribe in the subject field) > -- Ron Greenman at home.... _______________________________________________ Sprinklerforum mailing list http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum For Technical Assistance, send an email to: [EMAIL PROTECTED] To Unsubscribe, send an email to:[EMAIL PROTECTED] (Put the word unsubscribe in the subject field)