After spending a year talking about Cx, I can't give you a warm and fuzzy
feeling that a commissioning agent is going to do much more than document
the errors, get the obvious corrected, and wouldn't surprise me if there are
issues logs with some skeletons buried in the As Builts and O&M's.

Same as so many threads on this Forum- there aren't enough skilled workers
to do everything that needs skill, and so those of us that "get it" are
frustrated cause we know we can all do better, and we try to accommodate the
appearance of Murphy at every step- and still be low bidder, or low enough
to get a chance at selling something besides just cheap.

I suspect this will be accentuated when we face 16+ bidders on most jobs
this year. 

Glc
The above certainly isn't an opinion from NFPA.

-----Original Message-----
From: [EMAIL PROTECTED]
[mailto:[EMAIL PROTECTED] On Behalf Of Ron Greenman
Sent: Tuesday, November 11, 2008 2:15 PM
To: [email protected]
Subject: Re: White papers and definition of roles

This si why a commissioning agent is necessary from the start of the
project throughout the life of the building is necessary. Of course
that costs money and guys that can afford buildings big enough to have
big time coordination problems have to be pretty rich and they,
"...didn't get rich by writing a lot of checks." (Bill Gates to Homer
Simpson just before the Microsoft goons "buy out" Homer's undefined
internet business.) Commissioners cost money and it appears to be far
cheaper (though it's not) to let the contractors fight it out.

On Tue, Nov 11, 2008 at 10:56 AM, GAYLE KNOWLES <[EMAIL PROTECTED]> wrote:
>
> that's right, what Ron said.  And besides the fact, we all know where the
design problems are in all the different constructions and occupancies when
we prepare our bids.  The 3D is great if everyone sits done at the table
during the construction meetings and signs off on coordination drawings
showing elevations etc.  Doesn't do much good in bidding, when the
electrician decides to run his cable trays wherever he wants after the fact.
If your bid is that tight, counting on the electrician to run his trays "as
shown conceptually", you are out of luck.> Date: Tue, 11 Nov 2008 11:13:32
-0700> From: [EMAIL PROTECTED]> To: [email protected]>
Subject: RE: White papers and definition of roles> > Right on George. With
all the special systems I would expect more than> $2k difference in the
specialty equipment quotes and the prices should> be closer if you take away
the opportunity for innovation of design by> the bidders.> > Our prices are
higher on jobs requiring 3D or BIM. We find there is very> little
coordination and more "here is where we are so now you> (sprinkler) can go
around us. It's like a 3D retrofit. The only thing> that changes is we spend
more design time to come up with the same> product. Besides we FP
contractors have been doing 3D since the> beginning of time, it's just that
the presentation has been 2D.> > Ron Fletcher> Aero Automatic> Phoenix, AZ>
> -----Original Message-----> From:
[EMAIL PROTECTED]>
[mailto:[EMAIL PROTECTED] On Behalf Of George>
Church> Sent: Tuesday, November 11, 2008 7:00 AM> To:
[email protected]> Subject: RE: White papers and definition
of roles> > Ummm, maybe the two bidders had breakfast together on bid
morning?> Don't throw your elbow out patting yourself on the back.> >
Coincidence or a comp price is far more likely to produce bids within>
.001%> of each other than quality of the bid documents. > > Seriously, if
you'd given em a stocklist, a finished, coordinated dwg,> and a> rational
schedule, there'd be more difference in the price than this> just on> how
different companies allocate OH, backlog needs, lift pricing renting> vrs>
owning, mileage from office to site variance, mix of each contractor's>
design talent pool $ cost, workman's comp experience reflected in what>
could> be drastically different rates, skill of the two estimators, whether>
someone> got something last night- > There are so many variables, I'd
suspect a comp number before a headless> piping layout as the root cause for
the close resemblance.> > glc> > -----Original Message-----> From:
[EMAIL PROTECTED]>
[mailto:[EMAIL PROTECTED] On Behalf Of>
[EMAIL PROTECTED]> Sent: Tuesday, November 11, 2008 8:46 AM> To:
[email protected]> Subject: RE: White papers and definition
of roles> > Speaking of bid prices. We performed our first AutoCAD based 3D>
integration> of fire protection on a recent project. Our typical corporate>
deliverable> is the design criteria and a floor plan with equipment on it.
(I have> had a> couple complete installation level design requests but they
are rare in> this> industry) Typical criteria based design, no piping, or
heads or> anything> else. (because the contractor will do it for free).
Anyway, as we've> progressed into the 3D realm I've pushed to get fire
protection included> in> the 3D modeling. Convincing the powers that be that
by at least> including> mains and branch lines into the model and
coordinating their locations> and> elevations will aid the contractor during
installation, reduce his> design> time and reduce change orders and bring us
tighter bids as there is less> for> the imagination and more solid
information to work with.> > So they let us do the piping layout but no
heads, so we did the layout> in> the model dealing with equipment, steel and
other modeled obstructions.> > > Two weeks ago the project went out for
bids. We had 3 bidders. One> dropped> out due to various personal reasons
but the bids came back yesterday> from> the other two.> > The fire
protection bids on the project were within $2,000 of each> other.> Now that
may not sound like a big deal but understand the total above> ground> fire
protection is valued at almost $1.5 million dollars. > > For two bidders to
be that close is pretty unusual. But it validated> the> need for better
design other than the old floor plan with the note> "follow> NFPA 13" and
similar stuff.> > Hopefully we can continue this trend within our company. I
know this> would> be difficult for many companies because there is a lack of
qualified> people> who can actually layout a fire protection system and this
project ran> the> gamut of system types from wet, dry, pre-action,
foam-water deluge, low> expansion foam, dry chemical, CO2 and a proprietary,
IR triggered, high> speed, deluge curtain system (that is really cool by the
way). > > Now I'm hoping that our management sees the value in this effort
and> will> continue down this path. Convincing some to allow us to provide
more> than> the bare minimum of fire protection information is a tough
fight. For> whatever reason is has been for years. Maybe it has to do with
the lack> of> qualified people, some of it is based on economics, some of it
is> perceived> value, like I said, most AE firms feel the contractor
provides the> engineering effort for free so why do anything other than a
spec and> some> fancy notes.> > I actually had one PM complain that the
sprinkler contractors ALWAYS put> their pipe in the wrong place and it has
to be torn down and removed.> He> caught me on a good day so I graciously
(stop snickering) reminded him> of> the directive we typically give
sprinkler contractors: 1. coordinate> with> everyone and everything. But at
the same time all we give them is a> floor> plan of the building, no process
piping layouts (because there is no> such> animal), no steel plans, no duct
layouts, etc. So how can he coordinate> with things that don't exist or
haven't been designed yet? Hence my> sales> pitch for getting it in the
model and then giving that info to the> contractor. > > But this is one I
will put in the WIN column. They come far and few> between> so forgive me
while I savor the moment....................> > > > > Craig L. Prahl, CET >
Fire Protection Specialist> Mechanical Department> CH2MHILL> Lockwood
Greene> 1500 International Drive> PO Box 491, Spartanburg, SC 29304-0491>
Direct - 864.599.4102> Fax - 864.599.8439> [EMAIL PROTECTED]>
http://www.ch2m.com > > > -----Original Message-----> From:
[EMAIL PROTECTED]>
[mailto:[EMAIL PROTECTED] On Behalf Of Mark>
Sornsin> Sent: Monday, November 10, 2008 6:16 PM> To:
'[email protected]'> Subject: RE: White papers and definition
of roles> > Then there are those jurisdictions such as ND where you not only
don't> get> registered in a specific discipline, but complaints will not be>
investigated> unless there is a problem with the design. E.g., simply being
trained in> structural engineering and signing someone's sprinkler system
design is> not> a problem that will be investigated. It may violate the
engineers' code> of> ethics, but it won't see action from the State Board
unless there arises> some issue with the design. So if you're a PE not
trained in sprinkler> design, just get some non-PE designer to complete the
work and then you> can> seal it. Effectively there is no problem. If the
building burns as a> result> of improper design, then you've got a problem.>
> Of course, how many MEs even attempt to design a system? It's pretty>
difficult to hold an engineer to the fire when his "design" boils down> to>
"do it per code." I have had MEs ask me why I would ever attempt to>
provide> a complete sprinkler system design. They wonder, "doesn't that
expose> you> to more liability?" Gee, and here I thought design and the
associated> liability was the whole point of our profession.> > But that
leads us right back to Thom's point about doing whatever is> easiest. And
when an ME gets paid on a percentage of construction,> there's> no sense
putting time into a project and exposing himself to more> liability.>
Besides, his lack of effort will typically result in higher bid prices> and>
therefore higher fees. And the contractors don't want to rock the boat>
because the engineer may make their life more difficult. So the cycle>
continues.> > I ought to write an article...> > Mark A. Sornsin, PE> Fire
Protection Engineer> Ulteig Engineers, Inc.> 3350 38th Avenue S.> Fargo, ND
58104-7079> > [EMAIL PROTECTED]> >
_______________________________________________> Sprinklerforum mailing
list> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> For
Technical Assistance, send an email to:> [EMAIL PROTECTED]> > To
Unsubscribe, send an email> to:[EMAIL PROTECTED]>
(Put the word unsubscribe in the subject field)> >
_______________________________________________> Sprinklerforum mailing
list> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> For
Technical Assistance, send an email to:> [EMAIL PROTECTED]> > To
Unsubscribe, send an email> to:[EMAIL PROTECTED]>
(Put the word unsubscribe in the subject field)> >
_______________________________________________> Sprinklerforum mailing
list> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum> For
Technical Assistance, send an email to: [EMAIL PROTECTED]> > To
Unsubscribe, send an email to:[EMAIL PROTECTED]> (Put
the word unsubscribe in the subject
field)_______________________________________________
> Sprinklerforum mailing list
> http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
> For Technical Assistance, send an email to: [EMAIL PROTECTED]
>
> To Unsubscribe, send an email to:[EMAIL PROTECTED]
> (Put the word unsubscribe in the subject field)
>



-- 
Ron Greenman
at home....
_______________________________________________
Sprinklerforum mailing list
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
For Technical Assistance, send an email to: [EMAIL PROTECTED]

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

_______________________________________________
Sprinklerforum mailing list
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum
For Technical Assistance, send an email to: [EMAIL PROTECTED]

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

Reply via email to