Posting this for a friend having technical difficulties ......

 

 

IBC section 903.3.5.2 is about the provision of secondary water supply
for high-rise buildings in certain seismic zones.  My question is, does
the definition of secondary water supply include separate underground
piping to feed the building or can the secondary water supply tie into
the primary underground piping prior to entering the building or
anywhere else on site.

 