On Mon, Jan 26, 2026 at 9:22 AM Peri Hartman via EV <[email protected]> wrote:
>
> Putting in a
> disconnect is an insignificant cost compared to a whole level 3
> installation.
> Peri

It's actually a big deal, if it's a 20 charger DCFC with 150kW chargers.
That's three Megawatts.  The Big City Fire would NOT allow us to
modify the code to give a 15 second
shutdown time.  Nope, it has to be hard cut all at once.  Three
megawatts off the grid with a big arc chute.

Not a good idea for a button any homeless dude can press.

---

The cost of a shutoff is tiny for L3 stations.  Big for L2 parking
garages with low power EV chargers.