Re: Change Management question

2010-07-28 Thread Guillaume Rheault
Thanks Doug for taking the time to craft this reply. You are confirming my 
thought process.
I believe this is the first time your reply is not about ARS, but about an 
application, so we are breaking new ground here :-), so thanks again for your 
participation.

About the name for the Release Mgmt module, I guess we'll have to get used to 
and adapt to this terminology, and get rid off old conceptions.

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Mueller, Doug [doug_muel...@bmc.com]
Sent: Tuesday, July 27, 2010 6:10 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

**
Everyone,

Given that this discussion has wandered around for a while and in several 
different directions, I wanted to
put together a response.  I chose to remove the history of the discussion since 
there were several different
sets of includes with different depths and just start with a clean slate for 
the reply.

Issue 1 -- ITIL is a set of guidelines not an absolute

Step one in any discussion -- not unique to this discussion -- is to remember 
that ITIL is a set of guidelines
and is not absolute.  It does not have an answer to everything.  In the real 
world, there are things that are
simply not practical and it is important to interpret and allow for deviation.

It is a good set of guidelines and the goal is to follow the basic principles 
and directions that it encourages.

However, there are also times to deviate.  Let's take a specific example with 
the CMDB.

In ITIL v2, the CMDB specs said that things like Trouble Tickets and SLAs and 
the like all belonged within the
CMDB.  The problem is that these things are not configuration items (well, we 
could talk about SLAs, but
for sure Trouble Tickets).  BMC decided that the CMDB was for CONFIGURATION 
data and did not model
Trouble Tickets in the CMDB and insisted that they did not belong there.

I know we ran into a number of customers with "ITIL police" who insisted that 
we were doing things wrong
because Trouble Tickets did belong in the CMDB.  "It says so right here.".  
I was involved in many
discussions around this topic.

Well, it turns out, that by the time ITIL v3 came along, there was an 
understanding that Trouble Tickets really
didn't belong in the CMDB and you will find that they are not items that ITIL 
v3 advocates are in the CMDB.
There is now the CMS which BMC always called the Extended CMDB and Trouble 
Tickets are there but
stored in a Trouble Ticket data store.  This interpretation of what a CMDB is 
and is about is what BMC had
advocated from the start and as it turns out ITIL agreed and adjusted where if 
we had just followed the ITIL
rules at the time, it would have been the wrong direction.

Now, I am not indicating that there is the same issue going on in this 
situation (and in fact I don't), but I
always want to start any conversation with this note whenever there is a battle 
that forms up along the lines
of "ITIL SAYS".  Yes, but.


Issue 2 -- What are we trying to accomplish?

Now, let's return to this situation.  What are we trying to do?  What is the 
problem we are trying to solve?

-- Need to request, plan, and have the steps to execute a change to the 
environment
-- Need to request, plan, and orchestrate a set of changes and other activities 
in the environment

If I take these things, there is a difference in scope and process in these two 
goals.

The first is about making a very specific change.  To interact with the 
environment and change the
configuration in some way.  There are a specific set of steps that need to be 
performed.  You may need to
be aware of other changes to the same object and want to coordinate them.  But, 
in general, you are worried
about a point change to a specific object and not about the bigger picture of 
coordination of the entire
environment or infrastructure.

The second is about really more complete planning and coordination of one or 
more changes and potentially
other things in the environment to have a larger scope process.  You many need 
to make a series of
changes and have things like training or data conversion or any number of other 
things involved and scheduled
and synchronized.  There is the concept of a rollback plan (not part of change 
by the way) if there are
problems.  There is a concept that you may or may not get all changes and what 
to do about that (if one
thing out of 50 is not done are you OK or is that a failure).

Notice that the second item here is "bigger" than the first.  There is an 
entire layer of planning and
coordination that is not part of the first.  They don't intermix.  One is about 
"performing" the update.  The
other is about "coordinating" the update(s) and other activity.

If there is not some distinction between what is going on, why would there be a 
need for differe

Re: Change Management question

2010-07-27 Thread Mueller, Doug
Everyone,

Given that this discussion has wandered around for a while and in several 
different directions, I wanted to
put together a response.  I chose to remove the history of the discussion since 
there were several different
sets of includes with different depths and just start with a clean slate for 
the reply.

Issue 1 -- ITIL is a set of guidelines not an absolute

Step one in any discussion -- not unique to this discussion -- is to remember 
that ITIL is a set of guidelines
and is not absolute.  It does not have an answer to everything.  In the real 
world, there are things that are
simply not practical and it is important to interpret and allow for deviation.

It is a good set of guidelines and the goal is to follow the basic principles 
and directions that it encourages.

However, there are also times to deviate.  Let's take a specific example with 
the CMDB.

In ITIL v2, the CMDB specs said that things like Trouble Tickets and SLAs and 
the like all belonged within the
CMDB.  The problem is that these things are not configuration items (well, we 
could talk about SLAs, but
for sure Trouble Tickets).  BMC decided that the CMDB was for CONFIGURATION 
data and did not model
Trouble Tickets in the CMDB and insisted that they did not belong there.

I know we ran into a number of customers with "ITIL police" who insisted that 
we were doing things wrong
because Trouble Tickets did belong in the CMDB.  "It says so right here.".  
I was involved in many
discussions around this topic.

Well, it turns out, that by the time ITIL v3 came along, there was an 
understanding that Trouble Tickets really
didn't belong in the CMDB and you will find that they are not items that ITIL 
v3 advocates are in the CMDB.
There is now the CMS which BMC always called the Extended CMDB and Trouble 
Tickets are there but
stored in a Trouble Ticket data store.  This interpretation of what a CMDB is 
and is about is what BMC had
advocated from the start and as it turns out ITIL agreed and adjusted where if 
we had just followed the ITIL
rules at the time, it would have been the wrong direction.

Now, I am not indicating that there is the same issue going on in this 
situation (and in fact I don't), but I
always want to start any conversation with this note whenever there is a battle 
that forms up along the lines
of "ITIL SAYS".  Yes, but.


Issue 2 -- What are we trying to accomplish?

Now, let's return to this situation.  What are we trying to do?  What is the 
problem we are trying to solve?

-- Need to request, plan, and have the steps to execute a change to the 
environment
-- Need to request, plan, and orchestrate a set of changes and other activities 
in the environment

If I take these things, there is a difference in scope and process in these two 
goals.

The first is about making a very specific change.  To interact with the 
environment and change the
configuration in some way.  There are a specific set of steps that need to be 
performed.  You may need to
be aware of other changes to the same object and want to coordinate them.  But, 
in general, you are worried
about a point change to a specific object and not about the bigger picture of 
coordination of the entire
environment or infrastructure.

The second is about really more complete planning and coordination of one or 
more changes and potentially
other things in the environment to have a larger scope process.  You many need 
to make a series of
changes and have things like training or data conversion or any number of other 
things involved and scheduled
and synchronized.  There is the concept of a rollback plan (not part of change 
by the way) if there are
problems.  There is a concept that you may or may not get all changes and what 
to do about that (if one
thing out of 50 is not done are you OK or is that a failure).

Notice that the second item here is "bigger" than the first.  There is an 
entire layer of planning and
coordination that is not part of the first.  They don't intermix.  One is about 
"performing" the update.  The
other is about "coordinating" the update(s) and other activity.

If there is not some distinction between what is going on, why would there be a 
need for different processes
and flows -- whether ITIL or not.  There seems to be agreement that there are 
two different things going on
here and there needs to be a clear line between what is going on and why I 
would want to use one process
or the other.

Issue 3 -- What has BMC done?

With the distinction between the roles of the process above, it is pretty clear 
that there is a hierarchy in the
two items -- one is about "performing" and the other is about "coordinating the 
performing".

So, there needs to be two different processes because they are doing different 
things.

Performing is Change Management
Coordinating is Release Management

Note that BOTH solutions are tied together into the single overall concept of 
managing change within your
environment.  This is much like

Re: Change Management question

2010-07-27 Thread Rick Cook
That would be nice, wouldn't it!  I believe that there would be some areas
of disagreement between us and him.  I have no problem engaging in
discussions with people with opposing points of view, because I always feel
I can learn something.  If the Product Manager has the same attitude, we
would love to engage in some discussion here with him for the mutual benefit
of BMC and its customer base.  I won't call him out by name, but if someone
at BMC is watching, let him know we'd like to hear from him, OK?

Rick

On Tue, Jul 27, 2010 at 9:25 AM, Guillaume Rheault wrote:

> **
>  I still hope that the Change Mgmt product manager at BMC would chime in
> this discussion, in the same way that David and Doug have when questions
> about ARS pop-up , to at least explain why things were done a certain
> wayand what is the recommendation.
> As more companies use the OOTB applications and people in those companies
> become ITL v3 Foundation certified, this kind of discussions becomes more
> and more relevant.
>
> Guillaume
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Tuesday, July 27, 2010 9:18 AM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  ** The bottom line appears to be that the current construct of Release
> and Change is not as ITIL-compliant as BMC believes it to be, so you will
> have to choose whether you want to stick with ITIL or use the BMC Release
> package.  I have been told that no changes to the current product construct
> are in anyone's plans for at least the near term (2-3 years), FWIW.
>
>
> That being said, if one wants to use the product line the way it was
> constructed (Release --> Change/Activity --> Task), it would probably work
> just fine in supporting a company's Change and Release processes.  But if
> you try to force the ITIL model (Change --> Release --> Task) on it, it will
> not support that model very well.  A better alternative to that (IMHO) is to
> not use Release at all, but stick with the current Change/Activity --> Task
> methodology, which will work for most of the companies most of the time.
>
> Rick
>
> On Tue, Jul 27, 2010 at 12:03 AM, Mahendra Mahalkar <
> mahendra.mahal...@gmail.com> wrote:
>
>> ** Thanks to all listers participated in this thread as this discussion
>> really helped me to clear my concepts.
>>
>> Thanks & Regards,
>> Mahendra Mahalkar
>>
>>
>>
>>
>> On Mon, Jul 26, 2010 at 8:36 PM, strauss  wrote:
>>
>>> **
>>>
>>> As near as I can tell, Change Management is the process for continuous
>>> improvement (or evolution) through corrective changes to a service, and
>>> works at the component level of the services (CIs, assets, processes).
>>> Release and Deployment Management is more the process for quality assurance
>>> of all existing and planned services - with a more strategic approach.
>>>
>>>
>>>
>>> A few quotes from references on Change and Release Management might help,
>>> since the ITIL v3 diagrams and texts generally seem to place Change
>>> Management and Release Management adjacent to each other under Service
>>> Transition:
>>>
>>>
>>>
>>> Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3
>>> (2007):
>>>
>>> “Changes can be bundled into a release.”  P.238.
>>>
>>>
>>>
>>> Klosterboer, Larry, Implementing ITIL Change and Release Management
>>> (2009):
>>>
>>> “Release management is like an orchestra conductor, and change management
>>> is like the musicians.” P.6
>>>
>>> “Change management provides a disciplined approach to implementing IT
>>> changes. Decommissioning a service, upgrading an infrastructure component,
>>> and adopting a new delivery process are all examples of changes that should
>>> be tracked by the change management discipline.  Each change is considered
>>> in isolation and flows through a set of steps, including identification,
>>> documentation, assessment, authorization, execution, and evaluation.” P.6-7.
>>>
>>> “Release management provides a strategic approach to implementing an IT
>>> service.” P.7.
>>>
>>> “…an IT service is a set of components and service assets that work
>>> together to provide a unique benefit to the organization.  Before ITIL V3,
>>> many organizations used the term “IT system” instead of “IT service.

Re: Change Management question

2010-07-27 Thread Guillaume Rheault
I still hope that the Change Mgmt product manager at BMC would chime in this 
discussion, in the same way that David and Doug have when questions about ARS 
pop-up , to at least explain why things were done a certain wayand what is 
the recommendation.
As more companies use the OOTB applications and people in those companies 
become ITL v3 Foundation certified, this kind of discussions becomes more and 
more relevant.

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Tuesday, July 27, 2010 9:18 AM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** The bottom line appears to be that the current construct of Release and 
Change is not as ITIL-compliant as BMC believes it to be, so you will have to 
choose whether you want to stick with ITIL or use the BMC Release package.  I 
have been told that no changes to the current product construct are in anyone's 
plans for at least the near term (2-3 years), FWIW.

That being said, if one wants to use the product line the way it was 
constructed (Release --> Change/Activity --> Task), it would probably work just 
fine in supporting a company's Change and Release processes.  But if you try to 
force the ITIL model (Change --> Release --> Task) on it, it will not support 
that model very well.  A better alternative to that (IMHO) is to not use 
Release at all, but stick with the current Change/Activity --> Task 
methodology, which will work for most of the companies most of the time.

Rick

On Tue, Jul 27, 2010 at 12:03 AM, Mahendra Mahalkar 
mailto:mahendra.mahal...@gmail.com>> wrote:
** Thanks to all listers participated in this thread as this discussion really 
helped me to clear my concepts.

Thanks & Regards,
Mahendra Mahalkar




On Mon, Jul 26, 2010 at 8:36 PM, strauss 
mailto:stra...@unt.edu>> wrote:
**
As near as I can tell, Change Management is the process for continuous 
improvement (or evolution) through corrective changes to a service, and works 
at the component level of the services (CIs, assets, processes).  Release and 
Deployment Management is more the process for quality assurance of all existing 
and planned services - with a more strategic approach.

A few quotes from references on Change and Release Management might help, since 
the ITIL v3 diagrams and texts generally seem to place Change Management and 
Release Management adjacent to each other under Service Transition:

Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3 (2007):
“Changes can be bundled into a release.”  P.238.

Klosterboer, Larry, Implementing ITIL Change and Release Management (2009):
“Release management is like an orchestra conductor, and change management is 
like the musicians.” P.6
“Change management provides a disciplined approach to implementing IT changes. 
Decommissioning a service, upgrading an infrastructure component, and adopting 
a new delivery process are all examples of changes that should be tracked by 
the change management discipline.  Each change is considered in isolation and 
flows through a set of steps, including identification, documentation, 
assessment, authorization, execution, and evaluation.” P.6-7.
“Release management provides a strategic approach to implementing an IT 
service.” P.7.
“…an IT service is a set of components and service assets that work together to 
provide a unique benefit to the organization.  Before ITIL V3, many 
organizations used the term “IT system” instead of “IT service.”  “System” 
places the focus on IT components, whereas “service” emphasizes value to the 
organization. P.7.
“Service transition consists of the short-term view of change management and 
the long-term view of release management.” P.7.

So, Release Management is Strategic, and Change Management is Operational.  
IMHO, the ITIL V3 model has now added so many overlapping functions to the V2 
model, probably to meet new oversight requirements, that it is no longer 
comprehendible.  It’s no wonder that the software vendors are finding it hard 
to instantiate the ITIL defined “processes” into coherent application modules.  
 I hate to say it, but ITIL is probably overdue for a complete redesign, with 
consolidation and simplification as its goals.

Christopher Strauss, Ph.D.
Call Tracking Administration Manager
University of North Texas Computing & IT Center
http://itsm.unt.edu/
From: Action Request System discussion list(ARSList) 
[mailto:arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>] On Behalf Of Rick Cook
Sent: Monday, July 26, 2010 7:03 AM

To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** I was talking to our local ITIL folks about this this morning, and their 
opinion was that BMC constructed the Release/Change relationship backward - 
that Change should be above Release.  I have heard 

Re: Change Management question

2010-07-27 Thread Rick Cook
The bottom line appears to be that the current construct of Release and
Change is not as ITIL-compliant as BMC believes it to be, so you will have
to choose whether you want to stick with ITIL or use the BMC Release
package.  I have been told that no changes to the current product construct
are in anyone's plans for at least the near term (2-3 years), FWIW.

That being said, if one wants to use the product line the way it was
constructed (Release --> Change/Activity --> Task), it would probably work
just fine in supporting a company's Change and Release processes.  But if
you try to force the ITIL model (Change --> Release --> Task) on it, it will
not support that model very well.  A better alternative to that (IMHO) is to
not use Release at all, but stick with the current Change/Activity --> Task
methodology, which will work for most of the companies most of the time.

Rick

On Tue, Jul 27, 2010 at 12:03 AM, Mahendra Mahalkar <
mahendra.mahal...@gmail.com> wrote:

> ** Thanks to all listers participated in this thread as this discussion
> really helped me to clear my concepts.
>
> Thanks & Regards,
> Mahendra Mahalkar
>
>
>
>
> On Mon, Jul 26, 2010 at 8:36 PM, strauss  wrote:
>
>> **
>>
>> As near as I can tell, Change Management is the process for continuous
>> improvement (or evolution) through corrective changes to a service, and
>> works at the component level of the services (CIs, assets, processes).
>> Release and Deployment Management is more the process for quality assurance
>> of all existing and planned services - with a more strategic approach.
>>
>>
>>
>> A few quotes from references on Change and Release Management might help,
>> since the ITIL v3 diagrams and texts generally seem to place Change
>> Management and Release Management adjacent to each other under Service
>> Transition:
>>
>>
>>
>> Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3
>> (2007):
>>
>> “Changes can be bundled into a release.”  P.238.
>>
>>
>>
>> Klosterboer, Larry, Implementing ITIL Change and Release Management
>> (2009):
>>
>> “Release management is like an orchestra conductor, and change management
>> is like the musicians.” P.6
>>
>> “Change management provides a disciplined approach to implementing IT
>> changes. Decommissioning a service, upgrading an infrastructure component,
>> and adopting a new delivery process are all examples of changes that should
>> be tracked by the change management discipline.  Each change is considered
>> in isolation and flows through a set of steps, including identification,
>> documentation, assessment, authorization, execution, and evaluation.” P.6-7.
>>
>> “Release management provides a strategic approach to implementing an IT
>> service.” P.7.
>>
>> “…an IT service is a set of components and service assets that work
>> together to provide a unique benefit to the organization.  Before ITIL V3,
>> many organizations used the term “IT system” instead of “IT service.”
>> “System” places the focus on IT components, whereas “service” emphasizes
>> value to the organization. P.7.
>>
>> “Service transition consists of the short-term view of change management
>> and the long-term view of release management.” P.7.
>>
>>
>>
>> So, Release Management is Strategic, and Change Management is
>> Operational.  IMHO, the ITIL V3 model has now added so many overlapping
>> functions to the V2 model, probably to meet new oversight requirements, that
>> it is no longer comprehendible.  It’s no wonder that the software vendors
>> are finding it hard to instantiate the ITIL defined “processes” into
>> coherent application modules.   I hate to say it, but ITIL is probably
>> overdue for a complete redesign, with consolidation and simplification as
>> its goals.
>>
>>
>>
>> Christopher Strauss, Ph.D.
>> Call Tracking Administration Manager
>> University of North Texas Computing & IT Center
>> http://itsm.unt.edu/
>>
>> *From:* Action Request System discussion list(ARSList) [mailto:
>> arsl...@arslist.org] *On Behalf Of *Rick Cook
>> *Sent:* Monday, July 26, 2010 7:03 AM
>>
>> *To:* arslist@ARSLIST.ORG
>> *Subject:* Re: Change Management question
>>
>>
>>
>> ** I was talking to our local ITIL folks about this this morning, and
>> their opinion was that BMC constructed the Release/Change relationship
>> backward - that Change should be above Release.  I have heard others say the
>> opposite, so maybe that's true, maybe not, 

Re: Change Management question

2010-07-26 Thread Mahendra Mahalkar
Thanks to all listers participated in this thread as this discussion really
helped me to clear my concepts.

Thanks & Regards,
Mahendra Mahalkar



On Mon, Jul 26, 2010 at 8:36 PM, strauss  wrote:

> **
>
> As near as I can tell, Change Management is the process for continuous
> improvement (or evolution) through corrective changes to a service, and
> works at the component level of the services (CIs, assets, processes).
> Release and Deployment Management is more the process for quality assurance
> of all existing and planned services - with a more strategic approach.
>
>
>
> A few quotes from references on Change and Release Management might help,
> since the ITIL v3 diagrams and texts generally seem to place Change
> Management and Release Management adjacent to each other under Service
> Transition:
>
>
>
> Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3
> (2007):
>
> “Changes can be bundled into a release.”  P.238.
>
>
>
> Klosterboer, Larry, Implementing ITIL Change and Release Management (2009):
>
> “Release management is like an orchestra conductor, and change management
> is like the musicians.” P.6
>
> “Change management provides a disciplined approach to implementing IT
> changes. Decommissioning a service, upgrading an infrastructure component,
> and adopting a new delivery process are all examples of changes that should
> be tracked by the change management discipline.  Each change is considered
> in isolation and flows through a set of steps, including identification,
> documentation, assessment, authorization, execution, and evaluation.” P.6-7.
>
> “Release management provides a strategic approach to implementing an IT
> service.” P.7.
>
> “…an IT service is a set of components and service assets that work
> together to provide a unique benefit to the organization.  Before ITIL V3,
> many organizations used the term “IT system” instead of “IT service.”
> “System” places the focus on IT components, whereas “service” emphasizes
> value to the organization. P.7.
>
> “Service transition consists of the short-term view of change management
> and the long-term view of release management.” P.7.
>
>
>
> So, Release Management is Strategic, and Change Management is Operational.
> IMHO, the ITIL V3 model has now added so many overlapping functions to the
> V2 model, probably to meet new oversight requirements, that it is no longer
> comprehendible.  It’s no wonder that the software vendors are finding it
> hard to instantiate the ITIL defined “processes” into coherent application
> modules.   I hate to say it, but ITIL is probably overdue for a complete
> redesign, with consolidation and simplification as its goals.
>
>
>
> Christopher Strauss, Ph.D.
> Call Tracking Administration Manager
> University of North Texas Computing & IT Center
> http://itsm.unt.edu/
>
> *From:* Action Request System discussion list(ARSList) [mailto:
> arsl...@arslist.org] *On Behalf Of *Rick Cook
> *Sent:* Monday, July 26, 2010 7:03 AM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>
>
> ** I was talking to our local ITIL folks about this this morning, and their
> opinion was that BMC constructed the Release/Change relationship backward -
> that Change should be above Release.  I have heard others say the opposite,
> so maybe that's true, maybe not, and there was agreement about there being
> sufficient wiggle room that a company could use it either way, but that got
> me wondering why BMC did it the way they did it.
>
> Then it hit me.  If they put Release between Change and Task, it would have
> broken up the Change module.  So they put it on top of Change.  The problem
> with that is that the way they have constructed the relationships limits the
> customer's ability to use it in a Change --> Release scenario, due to the
> fact that while Releases can be related to RFCs, they cannot be dependent
> upon them - the Parent/Child scenario only works when Release is on top.
> That makes the process of monitoring completion of all Releases under a
> Change a manual one.  It also makes Tasks almost unusable.  That's not a
> major problem for us due to some other process and tooling issues, but it
> will be for many.
>
> So against my better judgment, and with the understanding that it is not
> optimal from a scaling and efficiency perspective, I feel that we will end
> up using a Master RFC controlling one or more Releases, which would then
> optionally control one or more subordinate Changes.  I will submit an RFE to
> BMC to enhance the relationship options, but I don't see them changing that
> any time soon.
>
> Rick
>
> On Sat, Jul 2

Re: Change Management question

2010-07-26 Thread Rick Cook
Well, ITIL 3 is an ancillary requirement, but that's kind of moot, since
according to our ITIL guy, who actually writes the ITIL policies and proofs
the books and holds every cert there is, BMC did not construct this in an
ITIL v2 or v3-compliant way.  He says that Change should be the overarching
app, and that Release should be able to act as either a peer or subordinate
entity to Change.  When he explained why to me, I have to admit that it made
sense.  I think it may be that Change --> Task relationship, with which we
are all very familiar over several years/versions, has become too deeply
ingrained in our minds as an inseparable combination, and we have to open
our minds to the idea of doing things another way that doesn't use that
structure.

With all respect and appreciation to Chris and the quotes he gave taking the
opposing POV, it seems that BMC kind of took the lazy way out when they gave
us Release, in that they didn't want to upset the CM/Task application
combination, so rather than put Release in the middle where it belongs, they
put it on top.  So now we have to tell our customers that they can modify
the tool, modify their process, or accept the limitations of living in the
middle.

Rick

On Mon, Jul 26, 2010 at 12:15 PM, Guillaume Rheault wrote:

> **
>  The way I would phrase it like this: Release Mgmt is the controlling
> application of Change Mgmt
> One benefit of using the release module is that you can have activities
> that do not require approvals; example of activities could be training,
> development of documentation, sending out communications, etc.
>
> Using the release module allows you to take advantage of the release app
> permissions, such as release viewer, release user, release master, and
> release configurator.
> You can have different reports specifically targeted for releases
>
> Think of the release module as a sort of project mgmt module built on ARS,
> with approvals, with access to the change records, etc.
>
> The other benefit would be to be compliant with ITIL v3, which may or may
> not be a big deal... it would be a bigger deal if your client wants to
> implement ITIL v3 as part of its program to improve its internal processes.
>
> Guillaume
>
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Monday, July 26, 2010 12:03 PM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  ** So the question boils down to this - please correct me if I'm wrong:
>
>
> If Change is being implemented to act as the master application to Release,
> what does that bring to the table functionally that using multiple levels of
> Change by itself doesn't do better?
>
> Rick
>
> On Mon, Jul 26, 2010 at 11:39 AM, Guillaume Rheault 
> wrote:
>
>> **
>>  I guess the problem relies on the fact that in ITIL v2 Release Mgmt  was
>> below Change Mgmt, and in ITIL v3 it's the other way around
>> I would have to verify this in ITIL v2 literature, which in my case is
>> somewhere gathering dust :-)
>>
>> On the web, I found this quite interesting:
>>
>> http://www.itlibrary.org/index.php?page=Release_Management
>>
>> Release Mgmt mission statement:
>>
>> "Implement changes to IT services taking a holistic (people, process,
>> technology) view which considers all aspects of a change including planning,
>> designing, building, testing, training, communications and deployment
>> activities."
>>
>> http://www.itlibrary.org/index.php?page=Change_Management
>>
>> Change Mgmt mission statement:
>>
>> "Coordinate and control all changes to IT services to minimize adverse
>> impacts of those changes to business operations and the users of IT
>> services."
>>
>> So in this sense, BMC has adopted the proper naming of the module, i.e.
>> Release Mgmt. Still, I would have preferred something like Change Project
>> Mgmt, since that immediately denotes a function/process that has a
>> controlling/managing natureand implementors would not have to butt heads
>> with ITIL v2 experts out there, on terminology.
>>
>> Guillaume
>>
>>  --
>>  *From:* Action Request System discussion list(ARSList) [
>> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
>>  *Sent:* Monday, July 26, 2010 11:30 AM
>>
>> *To:* arslist@ARSLIST.ORG
>> *Subject:* Re: Change Management question
>>
>>  ** So you guys can imagine my dilemma - I have one group of very
>> experienced, respected and trained people (you 

Re: Change Management question

2010-07-26 Thread Guillaume Rheault
The way I would phrase it like this: Release Mgmt is the controlling 
application of Change Mgmt
One benefit of using the release module is that you can have activities that do 
not require approvals; example of activities could be training, development of 
documentation, sending out communications, etc.

Using the release module allows you to take advantage of the release app 
permissions, such as release viewer, release user, release master, and release 
configurator.
You can have different reports specifically targeted for releases

Think of the release module as a sort of project mgmt module built on ARS, with 
approvals, with access to the change records, etc.

The other benefit would be to be compliant with ITIL v3, which may or may not 
be a big deal... it would be a bigger deal if your client wants to implement 
ITIL v3 as part of its program to improve its internal processes.

Guillaume



From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Monday, July 26, 2010 12:03 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** So the question boils down to this - please correct me if I'm wrong:

If Change is being implemented to act as the master application to Release, 
what does that bring to the table functionally that using multiple levels of 
Change by itself doesn't do better?

Rick

On Mon, Jul 26, 2010 at 11:39 AM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
I guess the problem relies on the fact that in ITIL v2 Release Mgmt  was below 
Change Mgmt, and in ITIL v3 it's the other way around
I would have to verify this in ITIL v2 literature, which in my case is 
somewhere gathering dust :-)

On the web, I found this quite interesting:

http://www.itlibrary.org/index.php?page=Release_Management

Release Mgmt mission statement:

"Implement changes to IT services taking a holistic (people, process, 
technology) view which considers all aspects of a change including planning, 
designing, building, testing, training, communications and deployment 
activities."

http://www.itlibrary.org/index.php?page=Change_Management

Change Mgmt mission statement:

"Coordinate and control all changes to IT services to minimize adverse impacts 
of those changes to business operations and the users of IT services."

So in this sense, BMC has adopted the proper naming of the module, i.e. Release 
Mgmt. Still, I would have preferred something like Change Project Mgmt, since 
that immediately denotes a function/process that has a controlling/managing 
natureand implementors would not have to butt heads with ITIL v2 experts 
out there, on terminology.

Guillaume


From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org<mailto:arslist@ARSLIST.ORG>] on behalf of Rick Cook 
[remedyr...@gmail.com<mailto:remedyr...@gmail.com>]
Sent: Monday, July 26, 2010 11:30 AM

To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** So you guys can imagine my dilemma - I have one group of very experienced, 
respected and trained people (you guys) telling me something that is 180 
degrees apart from what another group of experienced, respected, and trained 
people (my ITIL experts) are telling me.  And how the tool is set up, although 
it supports what you guys are saying, is deemed to be somewhat irrelevant by 
the other guys.


Welcome to ITIL, huh?

Rick

On Mon, Jul 26, 2010 at 11:06 AM, strauss 
mailto:stra...@unt.edu>> wrote:
**
As near as I can tell, Change Management is the process for continuous 
improvement (or evolution) through corrective changes to a service, and works 
at the component level of the services (CIs, assets, processes).  Release and 
Deployment Management is more the process for quality assurance of all existing 
and planned services - with a more strategic approach.

A few quotes from references on Change and Release Management might help, since 
the ITIL v3 diagrams and texts generally seem to place Change Management and 
Release Management adjacent to each other under Service Transition:

Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3 (2007):
“Changes can be bundled into a release.”  P.238.

Klosterboer, Larry, Implementing ITIL Change and Release Management (2009):
“Release management is like an orchestra conductor, and change management is 
like the musicians.” P.6
“Change management provides a disciplined approach to implementing IT changes. 
Decommissioning a service, upgrading an infrastructure component, and adopting 
a new delivery process are all examples of changes that should be tracked by 
the change management discipline.  Each change is considered in isolation and 
flows through a set of steps, including identification, documentation, 
assessment, authorization, execution,

Re: Change Management question

2010-07-26 Thread Rick Cook
So the question boils down to this - please correct me if I'm wrong:

If Change is being implemented to act as the master application to Release,
what does that bring to the table functionally that using multiple levels of
Change by itself doesn't do better?

Rick

On Mon, Jul 26, 2010 at 11:39 AM, Guillaume Rheault wrote:

> **
>  I guess the problem relies on the fact that in ITIL v2 Release Mgmt  was
> below Change Mgmt, and in ITIL v3 it's the other way around
> I would have to verify this in ITIL v2 literature, which in my case is
> somewhere gathering dust :-)
>
> On the web, I found this quite interesting:
>
> http://www.itlibrary.org/index.php?page=Release_Management
>
> Release Mgmt mission statement:
>
> "Implement changes to IT services taking a holistic (people, process,
> technology) view which considers all aspects of a change including planning,
> designing, building, testing, training, communications and deployment
> activities."
>
> http://www.itlibrary.org/index.php?page=Change_Management
>
> Change Mgmt mission statement:
>
> "Coordinate and control all changes to IT services to minimize adverse
> impacts of those changes to business operations and the users of IT
> services."
>
> So in this sense, BMC has adopted the proper naming of the module, i.e.
> Release Mgmt. Still, I would have preferred something like Change Project
> Mgmt, since that immediately denotes a function/process that has a
> controlling/managing natureand implementors would not have to butt heads
> with ITIL v2 experts out there, on terminology.
>
> Guillaume
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Monday, July 26, 2010 11:30 AM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  ** So you guys can imagine my dilemma - I have one group of very
> experienced, respected and trained people (you guys) telling me something
> that is 180 degrees apart from what another group of experienced, respected,
> and trained people (my ITIL experts) are telling me.  And how the tool is
> set up, although it supports what you guys are saying, is deemed to be
> somewhat irrelevant by the other guys.
>
>
> Welcome to ITIL, huh?
>
> Rick
>
> On Mon, Jul 26, 2010 at 11:06 AM, strauss  wrote:
>
>> **
>>
>> As near as I can tell, Change Management is the process for continuous
>> improvement (or evolution) through corrective changes to a service, and
>> works at the component level of the services (CIs, assets, processes).
>> Release and Deployment Management is more the process for quality assurance
>> of all existing and planned services - with a more strategic approach.
>>
>>
>>
>> A few quotes from references on Change and Release Management might help,
>> since the ITIL v3 diagrams and texts generally seem to place Change
>> Management and Release Management adjacent to each other under Service
>> Transition:
>>
>>
>>
>> Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3
>> (2007):
>>
>> “Changes can be bundled into a release.”  P.238.
>>
>>
>>
>> Klosterboer, Larry, Implementing ITIL Change and Release Management
>> (2009):
>>
>> “Release management is like an orchestra conductor, and change management
>> is like the musicians.” P.6
>>
>> “Change management provides a disciplined approach to implementing IT
>> changes. Decommissioning a service, upgrading an infrastructure component,
>> and adopting a new delivery process are all examples of changes that should
>> be tracked by the change management discipline.  Each change is considered
>> in isolation and flows through a set of steps, including identification,
>> documentation, assessment, authorization, execution, and evaluation.” P.6-7.
>>
>> “Release management provides a strategic approach to implementing an IT
>> service.” P.7.
>>
>> “…an IT service is a set of components and service assets that work
>> together to provide a unique benefit to the organization.  Before ITIL V3,
>> many organizations used the term “IT system” instead of “IT service.”
>> “System” places the focus on IT components, whereas “service” emphasizes
>> value to the organization. P.7.
>>
>> “Service transition consists of the short-term view of change management
>> and the long-term view of release management.” P.7.
>>
>>
>>
>> So, Release Management is Strategic, and Change Management is
>> Ope

Re: Change Management question

2010-07-26 Thread Guillaume Rheault
I guess the problem relies on the fact that in ITIL v2 Release Mgmt  was below 
Change Mgmt, and in ITIL v3 it's the other way around
I would have to verify this in ITIL v2 literature, which in my case is 
somewhere gathering dust :-)

On the web, I found this quite interesting:

http://www.itlibrary.org/index.php?page=Release_Management

Release Mgmt mission statement:

"Implement changes to IT services taking a holistic (people, process, 
technology) view which considers all aspects of a change including planning, 
designing, building, testing, training, communications and deployment 
activities."

http://www.itlibrary.org/index.php?page=Change_Management

Change Mgmt mission statement:

"Coordinate and control all changes to IT services to minimize adverse impacts 
of those changes to business operations and the users of IT services."

So in this sense, BMC has adopted the proper naming of the module, i.e. Release 
Mgmt. Still, I would have preferred something like Change Project Mgmt, since 
that immediately denotes a function/process that has a controlling/managing 
natureand implementors would not have to butt heads with ITIL v2 experts 
out there, on terminology.

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Monday, July 26, 2010 11:30 AM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** So you guys can imagine my dilemma - I have one group of very experienced, 
respected and trained people (you guys) telling me something that is 180 
degrees apart from what another group of experienced, respected, and trained 
people (my ITIL experts) are telling me.  And how the tool is set up, although 
it supports what you guys are saying, is deemed to be somewhat irrelevant by 
the other guys.

Welcome to ITIL, huh?

Rick

On Mon, Jul 26, 2010 at 11:06 AM, strauss 
mailto:stra...@unt.edu>> wrote:
**
As near as I can tell, Change Management is the process for continuous 
improvement (or evolution) through corrective changes to a service, and works 
at the component level of the services (CIs, assets, processes).  Release and 
Deployment Management is more the process for quality assurance of all existing 
and planned services - with a more strategic approach.

A few quotes from references on Change and Release Management might help, since 
the ITIL v3 diagrams and texts generally seem to place Change Management and 
Release Management adjacent to each other under Service Transition:

Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3 (2007):
“Changes can be bundled into a release.”  P.238.

Klosterboer, Larry, Implementing ITIL Change and Release Management (2009):
“Release management is like an orchestra conductor, and change management is 
like the musicians.” P.6
“Change management provides a disciplined approach to implementing IT changes. 
Decommissioning a service, upgrading an infrastructure component, and adopting 
a new delivery process are all examples of changes that should be tracked by 
the change management discipline.  Each change is considered in isolation and 
flows through a set of steps, including identification, documentation, 
assessment, authorization, execution, and evaluation.” P.6-7.
“Release management provides a strategic approach to implementing an IT 
service.” P.7.
“…an IT service is a set of components and service assets that work together to 
provide a unique benefit to the organization.  Before ITIL V3, many 
organizations used the term “IT system” instead of “IT service.”  “System” 
places the focus on IT components, whereas “service” emphasizes value to the 
organization. P.7.
“Service transition consists of the short-term view of change management and 
the long-term view of release management.” P.7.

So, Release Management is Strategic, and Change Management is Operational.  
IMHO, the ITIL V3 model has now added so many overlapping functions to the V2 
model, probably to meet new oversight requirements, that it is no longer 
comprehendible.  It’s no wonder that the software vendors are finding it hard 
to instantiate the ITIL defined “processes” into coherent application modules.  
 I hate to say it, but ITIL is probably overdue for a complete redesign, with 
consolidation and simplification as its goals.

Christopher Strauss, Ph.D.
Call Tracking Administration Manager
University of North Texas Computing & IT Center
http://itsm.unt.edu/
From: Action Request System discussion list(ARSList) 
[mailto:arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>] On Behalf Of Rick Cook
Sent: Monday, July 26, 2010 7:03 AM

To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** I was talking to our local ITIL folks about this this morning, and their 
opinion was that BMC constructed the Release/Change relationship backward - 
that Chang

Re: Change Management question

2010-07-26 Thread strauss
That's why I included the citations.

Christopher Strauss, Ph.D.
Call Tracking Administration Manager
University of North Texas Computing & IT Center
http://itsm.unt.edu/
From: Action Request System discussion list(ARSList) 
[mailto:arsl...@arslist.org] On Behalf Of Rick Cook
Sent: Monday, July 26, 2010 10:31 AM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** So you guys can imagine my dilemma - I have one group of very experienced, 
respected and trained people (you guys) telling me something that is 180 
degrees apart from what another group of experienced, respected, and trained 
people (my ITIL experts) are telling me.  And how the tool is set up, although 
it supports what you guys are saying, is deemed to be somewhat irrelevant by 
the other guys.

Welcome to ITIL, huh?

Rick

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-26 Thread Rick Cook
So you guys can imagine my dilemma - I have one group of very experienced,
respected and trained people (you guys) telling me something that is 180
degrees apart from what another group of experienced, respected, and trained
people (my ITIL experts) are telling me.  And how the tool is set up,
although it supports what you guys are saying, is deemed to be somewhat
irrelevant by the other guys.

Welcome to ITIL, huh?

Rick

On Mon, Jul 26, 2010 at 11:06 AM, strauss  wrote:

> **
>
> As near as I can tell, Change Management is the process for continuous
> improvement (or evolution) through corrective changes to a service, and
> works at the component level of the services (CIs, assets, processes).
> Release and Deployment Management is more the process for quality assurance
> of all existing and planned services - with a more strategic approach.
>
>
>
> A few quotes from references on Change and Release Management might help,
> since the ITIL v3 diagrams and texts generally seem to place Change
> Management and Release Management adjacent to each other under Service
> Transition:
>
>
>
> Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3
> (2007):
>
> “Changes can be bundled into a release.”  P.238.
>
>
>
> Klosterboer, Larry, Implementing ITIL Change and Release Management (2009):
>
> “Release management is like an orchestra conductor, and change management
> is like the musicians.” P.6
>
> “Change management provides a disciplined approach to implementing IT
> changes. Decommissioning a service, upgrading an infrastructure component,
> and adopting a new delivery process are all examples of changes that should
> be tracked by the change management discipline.  Each change is considered
> in isolation and flows through a set of steps, including identification,
> documentation, assessment, authorization, execution, and evaluation.” P.6-7.
>
> “Release management provides a strategic approach to implementing an IT
> service.” P.7.
>
> “…an IT service is a set of components and service assets that work
> together to provide a unique benefit to the organization.  Before ITIL V3,
> many organizations used the term “IT system” instead of “IT service.”
> “System” places the focus on IT components, whereas “service” emphasizes
> value to the organization. P.7.
>
> “Service transition consists of the short-term view of change management
> and the long-term view of release management.” P.7.
>
>
>
> So, Release Management is Strategic, and Change Management is Operational.
> IMHO, the ITIL V3 model has now added so many overlapping functions to the
> V2 model, probably to meet new oversight requirements, that it is no longer
> comprehendible.  It’s no wonder that the software vendors are finding it
> hard to instantiate the ITIL defined “processes” into coherent application
> modules.   I hate to say it, but ITIL is probably overdue for a complete
> redesign, with consolidation and simplification as its goals.
>
>
>
> Christopher Strauss, Ph.D.
> Call Tracking Administration Manager
> University of North Texas Computing & IT Center
> http://itsm.unt.edu/
>
> *From:* Action Request System discussion list(ARSList) [mailto:
> arsl...@arslist.org] *On Behalf Of *Rick Cook
> *Sent:* Monday, July 26, 2010 7:03 AM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>
>
> ** I was talking to our local ITIL folks about this this morning, and their
> opinion was that BMC constructed the Release/Change relationship backward -
> that Change should be above Release.  I have heard others say the opposite,
> so maybe that's true, maybe not, and there was agreement about there being
> sufficient wiggle room that a company could use it either way, but that got
> me wondering why BMC did it the way they did it.
>
>
> Then it hit me.  If they put Release between Change and Task, it would have
> broken up the Change module.  So they put it on top of Change.  The problem
> with that is that the way they have constructed the relationships limits the
> customer's ability to use it in a Change --> Release scenario, due to the
> fact that while Releases can be related to RFCs, they cannot be dependent
> upon them - the Parent/Child scenario only works when Release is on top.
> That makes the process of monitoring completion of all Releases under a
> Change a manual one.  It also makes Tasks almost unusable.  That's not a
> major problem for us due to some other process and tooling issues, but it
> will be for many.
>
> So against my better judgment, and with the understanding that it is not
> optimal from a scaling and efficiency perspective, I feel that we will end
> up using a

Re: Change Management question

2010-07-26 Thread strauss
As near as I can tell, Change Management is the process for continuous 
improvement (or evolution) through corrective changes to a service, and works 
at the component level of the services (CIs, assets, processes).  Release and 
Deployment Management is more the process for quality assurance of all existing 
and planned services - with a more strategic approach.

A few quotes from references on Change and Release Management might help, since 
the ITIL v3 diagrams and texts generally seem to place Change Management and 
Release Management adjacent to each other under Service Transition:

Van Bon, Jan, ed.  Foundations of IT Service Management Based on ITIL V3 (2007):
"Changes can be bundled into a release."  P.238.

Klosterboer, Larry, Implementing ITIL Change and Release Management (2009):
"Release management is like an orchestra conductor, and change management is 
like the musicians." P.6
"Change management provides a disciplined approach to implementing IT changes. 
Decommissioning a service, upgrading an infrastructure component, and adopting 
a new delivery process are all examples of changes that should be tracked by 
the change management discipline.  Each change is considered in isolation and 
flows through a set of steps, including identification, documentation, 
assessment, authorization, execution, and evaluation." P.6-7.
"Release management provides a strategic approach to implementing an IT 
service." P.7.
"...an IT service is a set of components and service assets that work together 
to provide a unique benefit to the organization.  Before ITIL V3, many 
organizations used the term "IT system" instead of "IT service."  "System" 
places the focus on IT components, whereas "service" emphasizes value to the 
organization. P.7.
"Service transition consists of the short-term view of change management and 
the long-term view of release management." P.7.

So, Release Management is Strategic, and Change Management is Operational.  
IMHO, the ITIL V3 model has now added so many overlapping functions to the V2 
model, probably to meet new oversight requirements, that it is no longer 
comprehendible.  It's no wonder that the software vendors are finding it hard 
to instantiate the ITIL defined "processes" into coherent application modules.  
 I hate to say it, but ITIL is probably overdue for a complete redesign, with 
consolidation and simplification as its goals.

Christopher Strauss, Ph.D.
Call Tracking Administration Manager
University of North Texas Computing & IT Center
http://itsm.unt.edu/
From: Action Request System discussion list(ARSList) 
[mailto:arsl...@arslist.org] On Behalf Of Rick Cook
Sent: Monday, July 26, 2010 7:03 AM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** I was talking to our local ITIL folks about this this morning, and their 
opinion was that BMC constructed the Release/Change relationship backward - 
that Change should be above Release.  I have heard others say the opposite, so 
maybe that's true, maybe not, and there was agreement about there being 
sufficient wiggle room that a company could use it either way, but that got me 
wondering why BMC did it the way they did it.

Then it hit me.  If they put Release between Change and Task, it would have 
broken up the Change module.  So they put it on top of Change.  The problem 
with that is that the way they have constructed the relationships limits the 
customer's ability to use it in a Change --> Release scenario, due to the fact 
that while Releases can be related to RFCs, they cannot be dependent upon them 
- the Parent/Child scenario only works when Release is on top.  That makes the 
process of monitoring completion of all Releases under a Change a manual one.  
It also makes Tasks almost unusable.  That's not a major problem for us due to 
some other process and tooling issues, but it will be for many.

So against my better judgment, and with the understanding that it is not 
optimal from a scaling and efficiency perspective, I feel that we will end up 
using a Master RFC controlling one or more Releases, which would then 
optionally control one or more subordinate Changes.  I will submit an RFE to 
BMC to enhance the relationship options, but I don't see them changing that any 
time soon.

Rick
On Sat, Jul 24, 2010 at 10:59 AM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
For the complex situation you described, I think the following scenario is the 
best:

Release --> Change/Activity --> Task

Approvals can be configured for releases, so you won't be missing that initial 
approval.

Also as you know, you can relate task templates to change templates, to 
"standardize" the work to be done

Guillaume


From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org&l

Re: Change Management question

2010-07-26 Thread Guillaume Rheault
Rick,

This is a great discussion, one that trully reflects the intent and purpose of 
this list.
One thing that IMHO you need to stress to the client if you go that route, is 
that if somebody for the client organization reads the Change Mgmt user guide, 
and finds what the OOTB use of the release mgmt module is intended to be, 
he/she may question the implementation that you are leading. That will be 
specially true if they intend to develop their training material based on the 
OOTB documentation, which is a common thing.

David Easter,

Any reason why the BMC choose such a poor name for this release mgmt module? 
From a marketing and even ITIL perspective, it seems backwards
It seems to me a name like Change Project Mgmt, or something along thosee lines 
would have been more appropriate, since the intention was, presumably, to have 
a module that would manage a collection of changes (that require approval) and 
activities (that don't require approval). Having a poor name is rather 
counterproductive

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Monday, July 26, 2010 8:02 AM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** I was talking to our local ITIL folks about this this morning, and their 
opinion was that BMC constructed the Release/Change relationship backward - 
that Change should be above Release.  I have heard others say the opposite, so 
maybe that's true, maybe not, and there was agreement about there being 
sufficient wiggle room that a company could use it either way, but that got me 
wondering why BMC did it the way they did it.

Then it hit me.  If they put Release between Change and Task, it would have 
broken up the Change module.  So they put it on top of Change.  The problem 
with that is that the way they have constructed the relationships limits the 
customer's ability to use it in a Change --> Release scenario, due to the fact 
that while Releases can be related to RFCs, they cannot be dependent upon them 
- the Parent/Child scenario only works when Release is on top.  That makes the 
process of monitoring completion of all Releases under a Change a manual one.  
It also makes Tasks almost unusable.  That's not a major problem for us due to 
some other process and tooling issues, but it will be for many.

So against my better judgment, and with the understanding that it is not 
optimal from a scaling and efficiency perspective, I feel that we will end up 
using a Master RFC controlling one or more Releases, which would then 
optionally control one or more subordinate Changes.  I will submit an RFE to 
BMC to enhance the relationship options, but I don't see them changing that any 
time soon.

Rick

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-26 Thread Rick Cook
I was talking to our local ITIL folks about this this morning, and their
opinion was that BMC constructed the Release/Change relationship backward -
that Change should be above Release.  I have heard others say the opposite,
so maybe that's true, maybe not, and there was agreement about there being
sufficient wiggle room that a company could use it either way, but that got
me wondering why BMC did it the way they did it.

Then it hit me.  If they put Release between Change and Task, it would have
broken up the Change module.  So they put it on top of Change.  The problem
with that is that the way they have constructed the relationships limits the
customer's ability to use it in a Change --> Release scenario, due to the
fact that while Releases can be related to RFCs, they cannot be dependent
upon them - the Parent/Child scenario only works when Release is on top.
That makes the process of monitoring completion of all Releases under a
Change a manual one.  It also makes Tasks almost unusable.  That's not a
major problem for us due to some other process and tooling issues, but it
will be for many.

So against my better judgment, and with the understanding that it is not
optimal from a scaling and efficiency perspective, I feel that we will end
up using a Master RFC controlling one or more Releases, which would then
optionally control one or more subordinate Changes.  I will submit an RFE to
BMC to enhance the relationship options, but I don't see them changing that
any time soon.

Rick

On Sat, Jul 24, 2010 at 10:59 AM, Guillaume Rheault wrote:

> **
>  For the complex situation you described, I think the following scenario
> is the best:
>
> Release --> Change/Activity --> Task
>
> Approvals can be configured for releases, so you won't be missing that
> initial approval.
>
> Also as you know, you can relate task templates to change templates, to
> "standardize" the work to be done
>
> Guillaume
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Friday, July 23, 2010 3:59 PM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  ** Well, having Release at the top allows things to flow Release -->
> Change/Activity --> Task.  Putting Release below Change eliminates the
> ability to use Tasks, since they can't be directly subordinate to a Release.
>
>
> So our options for a dependent (i.e. Parent/Child) flow are:
>
> Release --> Change/Activity --> Task
> --OR--
> Change --> Task
> --OR--
> Release --> Change(s)
>
> Do I have that right?
>
> Rick
>   _attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_
>

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-24 Thread Guillaume Rheault
For the complex situation you described, I think the following scenario is the 
best:

Release --> Change/Activity --> Task

Approvals can be configured for releases, so you won't be missing that initial 
approval.

Also as you know, you can relate task templates to change templates, to 
"standardize" the work to be done

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Friday, July 23, 2010 3:59 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** Well, having Release at the top allows things to flow Release --> 
Change/Activity --> Task.  Putting Release below Change eliminates the ability 
to use Tasks, since they can't be directly subordinate to a Release.

So our options for a dependent (i.e. Parent/Child) flow are:

Release --> Change/Activity --> Task
--OR--
Change --> Task
--OR--
Release --> Change(s)

Do I have that right?

Rick

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-23 Thread Roger Justice

And you can do it the way we did it before Release.
Change -> Change(s)-> Task 






-Original Message-
From: Rick Cook 
To: arslist 
Sent: Fri, Jul 23, 2010 3:59 pm
Subject: Re: Change Management question


** Well, having Release at the top allows things to flow Release --> 
Change/Activity --> Task.  Putting Release below Change eliminates the ability 
to use Tasks, since they can't be directly subordinate to a Release.

So our options for a dependent (i.e. Parent/Child) flow are:

Release --> Change/Activity --> Task
--OR--
Change --> Task
--OR--
Release --> Change(s)

Do I have that right?

Rick


On Fri, Jul 23, 2010 at 3:00 PM, Guillaume Rheault  wrote:

** 

Chris, good point. In the end, the main issue that needs to br definrd and 
standardized is the usage of the application.
The BMC Remedy Change Mgmt and Release Mgmt are loosely coupled OOTB, so 
various ways of usage can be defined, and that is usually the most difficult 
part in change mgmt implementations. Once you standardize usage, you can create 
business rules to lock down the app (customization really), to enforce such 
usage. 

Guillaume



From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of strauss [stra...@unt.edu]
Sent: Friday, July 23, 2010 2:53 PM


To: arslist@ARSLIST.ORG
Subject: Re: Change Management question






** 
Could the proper sequence be that an initial RFC would be considered for 
enterprise application versus local, and if approved for the enterprise you 
would create a parent Release for it, followed by additional child (to the 
Release) Infrastructure Changes and Activities for the rest of the enterprise?  
Or if the RFC was going to stand alone, for local application, then it still 
might be appropriate to create a parent release and add more Changes or at 
least Activities that were going to be necessary in conjunction with the action 
on the original RFC.
 
Larry Klosterboer’s book “Implementing ITIL Change and Release Management” is 
the newest guide I have found, but it is not specific to BMC ITSM (from IBM 
Press) so you have to figure out how to apply the generic concepts in your 
environment.
 
Christopher Strauss, Ph.D.
Call Tracking Administration Manager
University of North Texas Computing & IT Center
http://itsm.unt.edu/ 
 

From: Action Request System discussion list(ARSList) 
[mailto:arsl...@arslist.org] On Behalf Of Guillaume Rheault
Sent: Friday, July 23, 2010 1:29 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

 
** 

hi Rick,

I understand the situation. But that parent change could be a release entry 
too. My understanding of the philiosphy behind the BMC Release Mgmt module is 
that the release entry is intended to be the parent of changes, i.e. the actual 
implementation changes to production... So the starting point is the release, 
not the change. From the release, you create child changes that are scheduled 
within the release. So it seems we have a terminology/nomenclature issue here, 
since most people would think the release is downstream of the change, when in 
fact it is not, it is upstream.

Guillaume



From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Friday, July 23, 2010 2:19 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** The customer intends to have the Parent RFC as an initial point of approval 
and dispatch.  So Parent Company says "All installations need to patch their 
Windows OS with patches A, B, and C between Aug 1 and Aug 20".  Then when 
that's approved at the corporate level, each local NOC will create a child RFC 
and the related Release records to actually accomplish that and schedule it at 
their local level in a way, within the larger approved time window, in which 
doing that coordinates with the other planned outages and maintenance for their 
installation.

>From an approval level, the Parent approvals only take it up to Scheduled, and 
>then the Child approvals take over until they all are completed.  So from a 
>corporate level, I can look at the Parent RFC and from it, see the status of 
>all of the Child RFCs and associated Release records.

So think of it as having local control and accountability over the 
implementation of a global mandate.  Make sense?

Rick

On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault  wrote:
** 


from a process perspective, it seems to me having a a release with the child 
changes is sufficient...Release records can have approvals defined too with the 
approval server OOTB.
I don't see the benefit of the parent change

Guillaume



From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]

Sent: Friday, July 23, 2010 1:34 PM 


To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

 

** Thanks, Guillaume. 



The OOB Ch

Re: Change Management question

2010-07-23 Thread Rick Cook
Well, having Release at the top allows things to flow Release -->
Change/Activity --> Task.  Putting Release below Change eliminates the
ability to use Tasks, since they can't be directly subordinate to a Release.

So our options for a dependent (i.e. Parent/Child) flow are:

Release --> Change/Activity --> Task
--OR--
Change --> Task
--OR--
Release --> Change(s)

Do I have that right?

Rick

On Fri, Jul 23, 2010 at 3:00 PM, Guillaume Rheault wrote:

> **
>  Chris, good point. In the end, the main issue that needs to br definrd
> and standardized is the usage of the application.
> The BMC Remedy Change Mgmt and Release Mgmt are loosely coupled OOTB, so
> various ways of usage can be defined, and that is usually the most difficult
> part in change mgmt implementations. Once you standardize usage, you can
> create business rules to lock down the app (customization really), to
> enforce such usage.
>
> Guillaume
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of strauss [stra...@unt.edu]
> *Sent:* Friday, July 23, 2010 2:53 PM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  **
>
> Could the proper sequence be that an initial RFC would be considered for
> enterprise application versus local, and if approved for the enterprise you
> would create a parent Release for it, followed by additional child (to the
> Release) Infrastructure Changes and Activities for the rest of the
> enterprise?  Or if the RFC was going to stand alone, for local application,
> then it still might be appropriate to create a parent release and add more
> Changes or at least Activities that were going to be necessary in
> conjunction with the action on the original RFC.
>
>
>
> Larry Klosterboer’s book “Implementing ITIL Change and Release Management”
> is the newest guide I have found, but it is not specific to BMC ITSM (from
> IBM Press) so you have to figure out how to apply the generic concepts in
> your environment.
>
>
>
> Christopher Strauss, Ph.D.
> Call Tracking Administration Manager
> University of North Texas Computing & IT Center
> http://itsm.unt.edu/
>
>
>
> *From:* Action Request System discussion list(ARSList) [mailto:
> arsl...@arslist.org] *On Behalf Of *Guillaume Rheault
> *Sent:* Friday, July 23, 2010 1:29 PM
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>
>
> **
>
> hi Rick,
>
> I understand the situation. But that parent change could be a release entry
> too. My understanding of the philiosphy behind the BMC Release Mgmt module
> is that the release entry is intended to be the parent of changes, i.e. the
> actual implementation changes to production... So the starting point is the
> release, not the change. From the release, you create child changes that are
> scheduled within the release. So it seems we have a terminology/nomenclature
> issue here, since most people would think the release is downstream of the
> change, when in fact it is not, it is upstream.
>
> Guillaume
>   ----------
>
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Friday, July 23, 2010 2:19 PM
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
> ** The customer intends to have the Parent RFC as an initial point of
> approval and dispatch.  So Parent Company says "All installations need to
> patch their Windows OS with patches A, B, and C between Aug 1 and Aug 20".
> Then when that's approved at the corporate level, each local NOC will create
> a child RFC and the related Release records to actually accomplish that and
> schedule it at their local level in a way, within the larger approved time
> window, in which doing that coordinates with the other planned outages and
> maintenance for their installation.
>
> From an approval level, the Parent approvals only take it up to Scheduled,
> and then the Child approvals take over until they all are completed.  So
> from a corporate level, I can look at the Parent RFC and from it, see the
> status of all of the Child RFCs and associated Release records.
>
> So think of it as having local control and accountability over the
> implementation of a global mandate.  Make sense?
>
> Rick
>
> On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault 
> wrote:
>
> **
>
> from a process perspective, it seems to me having a a release with the
> child changes is sufficient...Release records can have approvals defined too
> with the approval server OOTB.
> I don't see the benefit of the parent c

Re: Change Management question

2010-07-23 Thread Guillaume Rheault
Chris, good point. In the end, the main issue that needs to br definrd and 
standardized is the usage of the application.
The BMC Remedy Change Mgmt and Release Mgmt are loosely coupled OOTB, so 
various ways of usage can be defined, and that is usually the most difficult 
part in change mgmt implementations. Once you standardize usage, you can create 
business rules to lock down the app (customization really), to enforce such 
usage.

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of strauss [stra...@unt.edu]
Sent: Friday, July 23, 2010 2:53 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

**
Could the proper sequence be that an initial RFC would be considered for 
enterprise application versus local, and if approved for the enterprise you 
would create a parent Release for it, followed by additional child (to the 
Release) Infrastructure Changes and Activities for the rest of the enterprise?  
Or if the RFC was going to stand alone, for local application, then it still 
might be appropriate to create a parent release and add more Changes or at 
least Activities that were going to be necessary in conjunction with the action 
on the original RFC.

Larry Klosterboer’s book “Implementing ITIL Change and Release Management” is 
the newest guide I have found, but it is not specific to BMC ITSM (from IBM 
Press) so you have to figure out how to apply the generic concepts in your 
environment.

Christopher Strauss, Ph.D.
Call Tracking Administration Manager
University of North Texas Computing & IT Center
http://itsm.unt.edu/

From: Action Request System discussion list(ARSList) 
[mailto:arsl...@arslist.org] On Behalf Of Guillaume Rheault
Sent: Friday, July 23, 2010 1:29 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

**
hi Rick,

I understand the situation. But that parent change could be a release entry 
too. My understanding of the philiosphy behind the BMC Release Mgmt module is 
that the release entry is intended to be the parent of changes, i.e. the actual 
implementation changes to production... So the starting point is the release, 
not the change. From the release, you create child changes that are scheduled 
within the release. So it seems we have a terminology/nomenclature issue here, 
since most people would think the release is downstream of the change, when in 
fact it is not, it is upstream.

Guillaume

From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Friday, July 23, 2010 2:19 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question
** The customer intends to have the Parent RFC as an initial point of approval 
and dispatch.  So Parent Company says "All installations need to patch their 
Windows OS with patches A, B, and C between Aug 1 and Aug 20".  Then when 
that's approved at the corporate level, each local NOC will create a child RFC 
and the related Release records to actually accomplish that and schedule it at 
their local level in a way, within the larger approved time window, in which 
doing that coordinates with the other planned outages and maintenance for their 
installation.

>From an approval level, the Parent approvals only take it up to Scheduled, and 
>then the Child approvals take over until they all are completed.  So from a 
>corporate level, I can look at the Parent RFC and from it, see the status of 
>all of the Child RFCs and associated Release records.

So think of it as having local control and accountability over the 
implementation of a global mandate.  Make sense?

Rick
On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
from a process perspective, it seems to me having a a release with the child 
changes is sufficient...Release records can have approvals defined too with the 
approval server OOTB.
I don't see the benefit of the parent change

Guillaume

From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org<mailto:arslist@ARSLIST.ORG>] on behalf of Rick Cook 
[remedyr...@gmail.com<mailto:remedyr...@gmail.com>]
Sent: Friday, July 23, 2010 1:34 PM

To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** Thanks, Guillaume.


The OOB Change Calendar has already been identified as an issue, due to its 
limitations on time periods.  We are looking at options there.  Collision and 
Impact aren't really going to be used by the customer at first, though as their 
CM processes mature and their CI data gets more complete, they intend to get 
there.  And we intend to attach the affected CIs to the child RFCs, not the 
Parent, though we're open to relating them to the Release records instead if 
that works better.

So is what you are saying 

Re: Change Management question

2010-07-23 Thread Rick Cook
Wow, I just read the CM User Guide again, and you're right - Release is
designed to be the parent of Changes and Activities.  A quote from page 42:
"A release is a collection of related authorized changes to an IT service
that are tested and introduced into the live environment together."

OK, then.  We have some paradigm-shifting to do on the part of the
customer.  I think I will wait until Monday to do that - don't want to spoil
anyone's weekend.  [?]

Rick

On Fri, Jul 23, 2010 at 2:29 PM, Guillaume Rheault wrote:

> **
>  hi Rick,
>
> I understand the situation. But that parent change could be a release entry
> too. My understanding of the philiosphy behind the BMC Release Mgmt module
> is that the release entry is intended to be the parent of changes, i.e. the
> actual implementation changes to production... So the starting point is the
> release, not the change. From the release, you create child changes that are
> scheduled within the release. So it seems we have a terminology/nomenclature
> issue here, since most people would think the release is downstream of the
> change, when in fact it is not, it is upstream.
>
> Guillaume
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Friday, July 23, 2010 2:19 PM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  ** The customer intends to have the Parent RFC as an initial point of
> approval and dispatch.  So Parent Company says "All installations need to
> patch their Windows OS with patches A, B, and C between Aug 1 and Aug 20".
> Then when that's approved at the corporate level, each local NOC will create
> a child RFC and the related Release records to actually accomplish that and
> schedule it at their local level in a way, within the larger approved time
> window, in which doing that coordinates with the other planned outages and
> maintenance for their installation.
>
>
> From an approval level, the Parent approvals only take it up to Scheduled,
> and then the Child approvals take over until they all are completed.  So
> from a corporate level, I can look at the Parent RFC and from it, see the
> status of all of the Child RFCs and associated Release records.
>
> So think of it as having local control and accountability over the
> implementation of a global mandate.  Make sense?
>
> Rick
>
> On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault wrote:
>
>> **
>>  from a process perspective, it seems to me having a a release with the
>> child changes is sufficient...Release records can have approvals defined too
>> with the approval server OOTB.
>> I don't see the benefit of the parent change
>>
>> Guillaume
>>
>>  ----------
>>  *From:* Action Request System discussion list(ARSList) [
>> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
>>  *Sent:* Friday, July 23, 2010 1:34 PM
>>
>> *To:* arslist@ARSLIST.ORG
>> *Subject:* Re: Change Management question
>>
>>  ** Thanks, Guillaume.
>>
>>
>> The OOB Change Calendar has already been identified as an issue, due to
>> its limitations on time periods.  We are looking at options there.
>> Collision and Impact aren't really going to be used by the customer at
>> first, though as their CM processes mature and their CI data gets more
>> complete, they intend to get there.  And we intend to attach the affected
>> CIs to the child RFCs, not the Parent, though we're open to relating them to
>> the Release records instead if that works better.
>>
>> So is what you are saying that the only subordinate records from a Parent
>> RFC should be Release records, not other RFCs?  Does using that in a
>> 3-tiered scenario cause other problems from a functional standpoint?  As
>> long as we can tie the records together (which we can) and have Approval
>> gates for all of them (which we can), and maintain controls over who updates
>> each (which we can), the Change Calendar is of little real consequence,
>> since we'll be giving the CAB a printed report anyway.
>>
>> Rick
>>
>> On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault 
>> wrote:
>>
>>> **
>>>  Rick,
>>>
>>> Having "parent" or "master" changes that  have days or months for
>>> implementation may not be a good idea, because it is going to mess up your
>>> change calendars, whether your OOTB ITSM change calendar, or any other
>>> calenda (BTW, take a look at the Kinetic ca

Re: Change Management question

2010-07-23 Thread Guillaume Rheault
Rick,

I found the evidence of my assumption of Release being the starting point, the 
top object if you will.
On page 42 of the "BMC Remedy Change Management 7.5.00 User’s Guide", it is 
stated:

.A release is a collection of related authorized changes to an IT service
that are tested and introduced into the live environment together.
..

Tracking and managing change and deployment activities
.

You may want to review the whole process you described in your earlier post

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Guillaume Rheault [guilla...@dcshq.com]
Sent: Friday, July 23, 2010 2:29 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

**
hi Rick,

I understand the situation. But that parent change could be a release entry 
too. My understanding of the philiosphy behind the BMC Release Mgmt module is 
that the release entry is intended to be the parent of changes, i.e. the actual 
implementation changes to production... So the starting point is the release, 
not the change. From the release, you create child changes that are scheduled 
within the release. So it seems we have a terminology/nomenclature issue here, 
since most people would think the release is downstream of the change, when in 
fact it is not, it is upstream.

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Friday, July 23, 2010 2:19 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** The customer intends to have the Parent RFC as an initial point of approval 
and dispatch.  So Parent Company says "All installations need to patch their 
Windows OS with patches A, B, and C between Aug 1 and Aug 20".  Then when 
that's approved at the corporate level, each local NOC will create a child RFC 
and the related Release records to actually accomplish that and schedule it at 
their local level in a way, within the larger approved time window, in which 
doing that coordinates with the other planned outages and maintenance for their 
installation.

>From an approval level, the Parent approvals only take it up to Scheduled, and 
>then the Child approvals take over until they all are completed.  So from a 
>corporate level, I can look at the Parent RFC and from it, see the status of 
>all of the Child RFCs and associated Release records.

So think of it as having local control and accountability over the 
implementation of a global mandate.  Make sense?

Rick

On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
from a process perspective, it seems to me having a a release with the child 
changes is sufficient...Release records can have approvals defined too with the 
approval server OOTB.
I don't see the benefit of the parent change

Guillaume


From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org<mailto:arslist@ARSLIST.ORG>] on behalf of Rick Cook 
[remedyr...@gmail.com<mailto:remedyr...@gmail.com>]
Sent: Friday, July 23, 2010 1:34 PM

To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** Thanks, Guillaume.


The OOB Change Calendar has already been identified as an issue, due to its 
limitations on time periods.  We are looking at options there.  Collision and 
Impact aren't really going to be used by the customer at first, though as their 
CM processes mature and their CI data gets more complete, they intend to get 
there.  And we intend to attach the affected CIs to the child RFCs, not the 
Parent, though we're open to relating them to the Release records instead if 
that works better.

So is what you are saying that the only subordinate records from a Parent RFC 
should be Release records, not other RFCs?  Does using that in a 3-tiered 
scenario cause other problems from a functional standpoint?  As long as we can 
tie the records together (which we can) and have Approval gates for all of them 
(which we can), and maintain controls over who updates each (which we can), the 
Change Calendar is of little real consequence, since we'll be giving the CAB a 
printed report anyway.

Rick

On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
Rick,

Having "parent" or "master" changes that  have days or months for 
implementation may not be a good idea, because it is going to mess up your 
change calendars, whether your OOTB ITSM change calendar, or any other calenda 
(BTW, take a look at the Kinetic calendar, it is awesome and really simple to 
set up), unless you filter out this "parent" changes by the change type or 
something else. Other things that will be messed up are is the new 7.5 
collision dete

Re: Change Management question

2010-07-23 Thread strauss
Could the proper sequence be that an initial RFC would be considered for 
enterprise application versus local, and if approved for the enterprise you 
would create a parent Release for it, followed by additional child (to the 
Release) Infrastructure Changes and Activities for the rest of the enterprise?  
Or if the RFC was going to stand alone, for local application, then it still 
might be appropriate to create a parent release and add more Changes or at 
least Activities that were going to be necessary in conjunction with the action 
on the original RFC.

Larry Klosterboer's book "Implementing ITIL Change and Release Management" is 
the newest guide I have found, but it is not specific to BMC ITSM (from IBM 
Press) so you have to figure out how to apply the generic concepts in your 
environment.

Christopher Strauss, Ph.D.
Call Tracking Administration Manager
University of North Texas Computing & IT Center
http://itsm.unt.edu/

From: Action Request System discussion list(ARSList) 
[mailto:arsl...@arslist.org] On Behalf Of Guillaume Rheault
Sent: Friday, July 23, 2010 1:29 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

**
hi Rick,

I understand the situation. But that parent change could be a release entry 
too. My understanding of the philiosphy behind the BMC Release Mgmt module is 
that the release entry is intended to be the parent of changes, i.e. the actual 
implementation changes to production... So the starting point is the release, 
not the change. From the release, you create child changes that are scheduled 
within the release. So it seems we have a terminology/nomenclature issue here, 
since most people would think the release is downstream of the change, when in 
fact it is not, it is upstream.

Guillaume

From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Friday, July 23, 2010 2:19 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question
** The customer intends to have the Parent RFC as an initial point of approval 
and dispatch.  So Parent Company says "All installations need to patch their 
Windows OS with patches A, B, and C between Aug 1 and Aug 20".  Then when 
that's approved at the corporate level, each local NOC will create a child RFC 
and the related Release records to actually accomplish that and schedule it at 
their local level in a way, within the larger approved time window, in which 
doing that coordinates with the other planned outages and maintenance for their 
installation.

>From an approval level, the Parent approvals only take it up to Scheduled, and 
>then the Child approvals take over until they all are completed.  So from a 
>corporate level, I can look at the Parent RFC and from it, see the status of 
>all of the Child RFCs and associated Release records.

So think of it as having local control and accountability over the 
implementation of a global mandate.  Make sense?

Rick
On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
from a process perspective, it seems to me having a a release with the child 
changes is sufficient...Release records can have approvals defined too with the 
approval server OOTB.
I don't see the benefit of the parent change

Guillaume

From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org<mailto:arslist@ARSLIST.ORG>] on behalf of Rick Cook 
[remedyr...@gmail.com<mailto:remedyr...@gmail.com>]
Sent: Friday, July 23, 2010 1:34 PM

To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** Thanks, Guillaume.


The OOB Change Calendar has already been identified as an issue, due to its 
limitations on time periods.  We are looking at options there.  Collision and 
Impact aren't really going to be used by the customer at first, though as their 
CM processes mature and their CI data gets more complete, they intend to get 
there.  And we intend to attach the affected CIs to the child RFCs, not the 
Parent, though we're open to relating them to the Release records instead if 
that works better.

So is what you are saying that the only subordinate records from a Parent RFC 
should be Release records, not other RFCs?  Does using that in a 3-tiered 
scenario cause other problems from a functional standpoint?  As long as we can 
tie the records together (which we can) and have Approval gates for all of them 
(which we can), and maintain controls over who updates each (which we can), the 
Change Calendar is of little real consequence, since we'll be giving the CAB a 
printed report anyway.

Rick
On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
Rick,

Having "parent" or "master" changes that  have days or months for 
impleme

Re: Change Management question

2010-07-23 Thread Guillaume Rheault
hi Rick,

I understand the situation. But that parent change could be a release entry 
too. My understanding of the philiosphy behind the BMC Release Mgmt module is 
that the release entry is intended to be the parent of changes, i.e. the actual 
implementation changes to production... So the starting point is the release, 
not the change. From the release, you create child changes that are scheduled 
within the release. So it seems we have a terminology/nomenclature issue here, 
since most people would think the release is downstream of the change, when in 
fact it is not, it is upstream.

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Friday, July 23, 2010 2:19 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** The customer intends to have the Parent RFC as an initial point of approval 
and dispatch.  So Parent Company says "All installations need to patch their 
Windows OS with patches A, B, and C between Aug 1 and Aug 20".  Then when 
that's approved at the corporate level, each local NOC will create a child RFC 
and the related Release records to actually accomplish that and schedule it at 
their local level in a way, within the larger approved time window, in which 
doing that coordinates with the other planned outages and maintenance for their 
installation.

>From an approval level, the Parent approvals only take it up to Scheduled, and 
>then the Child approvals take over until they all are completed.  So from a 
>corporate level, I can look at the Parent RFC and from it, see the status of 
>all of the Child RFCs and associated Release records.

So think of it as having local control and accountability over the 
implementation of a global mandate.  Make sense?

Rick

On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
from a process perspective, it seems to me having a a release with the child 
changes is sufficient...Release records can have approvals defined too with the 
approval server OOTB.
I don't see the benefit of the parent change

Guillaume


From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org<mailto:arslist@ARSLIST.ORG>] on behalf of Rick Cook 
[remedyr...@gmail.com<mailto:remedyr...@gmail.com>]
Sent: Friday, July 23, 2010 1:34 PM

To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** Thanks, Guillaume.


The OOB Change Calendar has already been identified as an issue, due to its 
limitations on time periods.  We are looking at options there.  Collision and 
Impact aren't really going to be used by the customer at first, though as their 
CM processes mature and their CI data gets more complete, they intend to get 
there.  And we intend to attach the affected CIs to the child RFCs, not the 
Parent, though we're open to relating them to the Release records instead if 
that works better.

So is what you are saying that the only subordinate records from a Parent RFC 
should be Release records, not other RFCs?  Does using that in a 3-tiered 
scenario cause other problems from a functional standpoint?  As long as we can 
tie the records together (which we can) and have Approval gates for all of them 
(which we can), and maintain controls over who updates each (which we can), the 
Change Calendar is of little real consequence, since we'll be giving the CAB a 
printed report anyway.

Rick

On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
Rick,

Having "parent" or "master" changes that  have days or months for 
implementation may not be a good idea, because it is going to mess up your 
change calendars, whether your OOTB ITSM change calendar, or any other calenda 
(BTW, take a look at the Kinetic calendar, it is awesome and really simple to 
set up), unless you filter out this "parent" changes by the change type or 
something else. Other things that will be messed up are is the new 7.5 
collision detection and impact analysis. I am running into this specific 
situation right now and it is not clean... it is actually cludgy. I advise you 
to stay away from that scenario as much as possible from day one.

I agree with Roger that these kind of parent changes should find their place in 
the release module somehow, and not in the change module. This implies of 
course using another module, training,etc, but in the end it will be much 
cleaner from a process, data and reporting perspectives.

Guillaume


From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org<mailto:arslist@ARSLIST.ORG>] on behalf of Rick Cook 
[remedyr...@gmail.com<mailto:remedyr...@gmail.com>]
Sent: Thursday, July 22, 2010 11:36 AM
To: arslist@

Re: Change Management question

2010-07-23 Thread Rick Cook
The customer intends to have the Parent RFC as an initial point of approval
and dispatch.  So Parent Company says "All installations need to patch their
Windows OS with patches A, B, and C between Aug 1 and Aug 20".  Then when
that's approved at the corporate level, each local NOC will create a child
RFC and the related Release records to actually accomplish that and schedule
it at their local level in a way, within the larger approved time window, in
which doing that coordinates with the other planned outages and maintenance
for their installation.

>From an approval level, the Parent approvals only take it up to Scheduled,
and then the Child approvals take over until they all are completed.  So
from a corporate level, I can look at the Parent RFC and from it, see the
status of all of the Child RFCs and associated Release records.

So think of it as having local control and accountability over the
implementation of a global mandate.  Make sense?

Rick

On Fri, Jul 23, 2010 at 2:11 PM, Guillaume Rheault wrote:

> **
>  from a process perspective, it seems to me having a a release with the
> child changes is sufficient...Release records can have approvals defined too
> with the approval server OOTB.
> I don't see the benefit of the parent change
>
> Guillaume
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Friday, July 23, 2010 1:34 PM
>
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  ** Thanks, Guillaume.
>
>
> The OOB Change Calendar has already been identified as an issue, due to its
> limitations on time periods.  We are looking at options there.  Collision
> and Impact aren't really going to be used by the customer at first, though
> as their CM processes mature and their CI data gets more complete, they
> intend to get there.  And we intend to attach the affected CIs to the child
> RFCs, not the Parent, though we're open to relating them to the Release
> records instead if that works better.
>
> So is what you are saying that the only subordinate records from a Parent
> RFC should be Release records, not other RFCs?  Does using that in a
> 3-tiered scenario cause other problems from a functional standpoint?  As
> long as we can tie the records together (which we can) and have Approval
> gates for all of them (which we can), and maintain controls over who updates
> each (which we can), the Change Calendar is of little real consequence,
> since we'll be giving the CAB a printed report anyway.
>
> Rick
>
> On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault wrote:
>
>> **
>>  Rick,
>>
>> Having "parent" or "master" changes that  have days or months for
>> implementation may not be a good idea, because it is going to mess up your
>> change calendars, whether your OOTB ITSM change calendar, or any other
>> calenda (BTW, take a look at the Kinetic calendar, it is awesome and really
>> simple to set up), unless you filter out this "parent" changes by the change
>> type or something else. Other things that will be messed up are is the new
>> 7.5 collision detection and impact analysis. I am running into this specific
>> situation right now and it is not clean... it is actually cludgy. I advise
>> you to stay away from that scenario as much as possible from day one.
>>
>> I agree with Roger that these kind of parent changes should find their
>> place in the release module somehow, and not in the change module. This
>> implies of course using another module, training,etc, but in the end it will
>> be much cleaner from a process, data and reporting perspectives.
>>
>> Guillaume
>>
>>  --
>> *From:* Action Request System discussion list(ARSList) [
>> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
>> *Sent:* Thursday, July 22, 2010 11:36 AM
>> *To:* arslist@ARSLIST.ORG
>> *Subject:* Re: Change Management question
>>
>>  ** We intend to log the actual work in Release, but we want local RFCs
>> to track the scheduling of the change, which would have different acceptable
>> maintenance windows at each location.  So the parent change would give, say,
>> a 30 day window for implementation, and each child RFC logs where within
>> that window the individual location will do their change.  Does that seem
>> like a sound structure, Roger, or should everything underneath the parent
>> RFC be based in Release?
>>
>>
>> Rick
>>
>> On Thu, Jul 22, 2010 at 11:30 AM, Roger Justice wrote:
>>
>>> ** 

Re: Change Management question

2010-07-23 Thread Rick Cook
We are on 7.5 patch 4, and I see "Release" in the Relationship Type on the
Change form, and see "Infrastructure Change" in the Relationship Type field
on a Release record.

Rick

On Fri, Jul 23, 2010 at 1:38 PM, Roger Justice  wrote:

> ** I tried to create a child Release to a Change and it is not lited as an
> option on the Change Relationships tab. This was ITSM 7.6 no Patch.
>
>
>
> -Original Message-
> From: Rick Cook 
> To: arslist 
> Sent: Fri, Jul 23, 2010 1:34 pm
> Subject: Re: Change Management question
>
> ** Thanks, Guillaume.
>
> The OOB Change Calendar has already been identified as an issue, due to its
> limitations on time periods.  We are looking at options there.  Collision
> and Impact aren't really going to be used by the customer at first, though
> as their CM processes mature and their CI data gets more complete, they
> intend to get there.  And we intend to attach the affected CIs to the child
> RFCs, not the Parent, though we're open to relating them to the Release
> records instead if that works better.
>
> So is what you are saying that the only subordinate records from a Parent
> RFC should be Release records, not other RFCs?  Does using that in a
> 3-tiered scenario cause other problems from a functional standpoint?  As
> long as we can tie the records together (which we can) and have Approval
> gates for all of them (which we can), and maintain controls over who updates
> each (which we can), the Change Calendar is of little real consequence,
> since we'll be giving the CAB a printed report anyway.
>
> Rick
>
> On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault wrote:
>
>> **
>>  Rick,
>>
>> Having "parent" or "master" changes that  have days or months for
>> implementation may not be a good idea, because it is going to mess up your
>> change calendars, whether your OOTB ITSM change calendar, or any other
>> calenda (BTW, take a look at the Kinetic calendar, it is awesome and really
>> simple to set up), unless you filter out this "parent" changes by the change
>> type or something else. Other things that will be messed up are is the new
>> 7.5 collision detection and impact analysis. I am running into this specific
>> situation right now and it is not clean... it is actually cludgy. I advise
>> you to stay away from that scenario as much as possible from day one.
>>
>> I agree with Roger that these kind of parent changes should find their
>> place in the release module somehow, and not in the change module. This
>> implies of course using another module, training,etc, but in the end it will
>> be much cleaner from a process, data and reporting perspectives.
>>
>> Guillaume
>>
>>  --
>> *From:* Action Request System discussion list(ARSList) [
>> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
>> *Sent:* Thursday, July 22, 2010 11:36 AM
>> *To:* arslist@ARSLIST.ORG
>> *Subject:* Re: Change Management question
>>
>>  ** We intend to log the actual work in Release, but we want local RFCs
>> to track the scheduling of the change, which would have different acceptable
>> maintenance windows at each location.  So the parent change would give, say,
>> a 30 day window for implementation, and each child RFC logs where within
>> that window the individual location will do their change.  Does that seem
>> like a sound structure, Roger, or should everything underneath the parent
>> RFC be based in Release?
>>
>>
>> Rick
>>
>> On Thu, Jul 22, 2010 at 11:30 AM, Roger Justice wrote:
>>
>>> ** This would be better handled by Release. I know that the parent in
>>> either case cannot be closed until the children changes are completed.
>>>
>>>
>>>
>>>   -Original Message-
>>> From: Rick Cook 
>>> To: arslist 
>>> Sent: Thu, Jul 22, 2010 11:26 am
>>> Subject: Change Management question
>>>
>>>** We are looking to use CM (7.5) like this:  One Project or Release
>>> RFC that would dictate what needed to be done at multiple locations.  Then
>>> subordinate RFCs would be created at each location to handle the exact
>>> scheduling and implementation.  My question is whether the Parent/Child RFC
>>> process works like the RFC/Task process, in that closing the last task in an
>>> RFC auto-closes it and/or if the Parent RFC is prevented from being closed
>>> until all of the children are closed.
&g

Re: Change Management question

2010-07-23 Thread Guillaume Rheault
from a process perspective, it seems to me having a a release with the child 
changes is sufficient...Release records can have approvals defined too with the 
approval server OOTB.
I don't see the benefit of the parent change

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Friday, July 23, 2010 1:34 PM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** Thanks, Guillaume.

The OOB Change Calendar has already been identified as an issue, due to its 
limitations on time periods.  We are looking at options there.  Collision and 
Impact aren't really going to be used by the customer at first, though as their 
CM processes mature and their CI data gets more complete, they intend to get 
there.  And we intend to attach the affected CIs to the child RFCs, not the 
Parent, though we're open to relating them to the Release records instead if 
that works better.

So is what you are saying that the only subordinate records from a Parent RFC 
should be Release records, not other RFCs?  Does using that in a 3-tiered 
scenario cause other problems from a functional standpoint?  As long as we can 
tie the records together (which we can) and have Approval gates for all of them 
(which we can), and maintain controls over who updates each (which we can), the 
Change Calendar is of little real consequence, since we'll be giving the CAB a 
printed report anyway.

Rick

On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault 
mailto:guilla...@dcshq.com>> wrote:
**
Rick,

Having "parent" or "master" changes that  have days or months for 
implementation may not be a good idea, because it is going to mess up your 
change calendars, whether your OOTB ITSM change calendar, or any other calenda 
(BTW, take a look at the Kinetic calendar, it is awesome and really simple to 
set up), unless you filter out this "parent" changes by the change type or 
something else. Other things that will be messed up are is the new 7.5 
collision detection and impact analysis. I am running into this specific 
situation right now and it is not clean... it is actually cludgy. I advise you 
to stay away from that scenario as much as possible from day one.

I agree with Roger that these kind of parent changes should find their place in 
the release module somehow, and not in the change module. This implies of 
course using another module, training,etc, but in the end it will be much 
cleaner from a process, data and reporting perspectives.

Guillaume


From: Action Request System discussion list(ARSList) 
[arsl...@arslist.org<mailto:arslist@ARSLIST.ORG>] on behalf of Rick Cook 
[remedyr...@gmail.com<mailto:remedyr...@gmail.com>]
Sent: Thursday, July 22, 2010 11:36 AM
To: arslist@ARSLIST.ORG<mailto:arslist@ARSLIST.ORG>
Subject: Re: Change Management question

** We intend to log the actual work in Release, but we want local RFCs to track 
the scheduling of the change, which would have different acceptable maintenance 
windows at each location.  So the parent change would give, say, a 30 day 
window for implementation, and each child RFC logs where within that window the 
individual location will do their change.  Does that seem like a sound 
structure, Roger, or should everything underneath the parent RFC be based in 
Release?


Rick

On Thu, Jul 22, 2010 at 11:30 AM, Roger Justice 
mailto:rjust2...@aol.com>> wrote:
** This would be better handled by Release. I know that the parent in either 
case cannot be closed until the children changes are completed.



-Original Message-
From: Rick Cook mailto:remedyr...@gmail.com>>
To: arslist mailto:arslist@ARSLIST.ORG>>
Sent: Thu, Jul 22, 2010 11:26 am
Subject: Change Management question

** We are looking to use CM (7.5) like this:  One Project or Release RFC that 
would dictate what needed to be done at multiple locations.  Then subordinate 
RFCs would be created at each location to handle the exact scheduling and 
implementation.  My question is whether the Parent/Child RFC process works like 
the RFC/Task process, in that closing the last task in an RFC auto-closes it 
and/or if the Parent RFC is prevented from being closed until all of the 
children are closed.

Just trying to get a handle on the degree of dependence or control the parent 
RFC has on the subordinate RFC, and vice versa.

Rick
_attend WWRUG10 www.wwrug.com<http://www.wwrug.com/> ARSlist: "Where the 
Answers Are"_
_attend WWRUG10 www.wwrug.com<http://www.wwrug.com> ARSlist: "Where the Answers 
Are"_

_attend WWRUG10 www.wwrug.com<http://www.wwrug.com> ARSlist: "Where the Answers 
Are"_
_attend WWRUG10 www.wwrug.com<http://www.wwrug.com> ARSlist: "Where the Answers 
Are"_

_attend WWRUG10 www.wwrug.com 

Re: Change Management question

2010-07-23 Thread Roger Justice
I tried to create a child Release to a Change and it is not lited as an option 
on the Change Relationships tab. This was ITSM 7.6 no Patch.





-Original Message-
From: Rick Cook 
To: arslist 
Sent: Fri, Jul 23, 2010 1:34 pm
Subject: Re: Change Management question


** Thanks, Guillaume.

The OOB Change Calendar has already been identified as an issue, due to its 
limitations on time periods.  We are looking at options there.  Collision and 
Impact aren't really going to be used by the customer at first, though as their 
CM processes mature and their CI data gets more complete, they intend to get 
there.  And we intend to attach the affected CIs to the child RFCs, not the 
Parent, though we're open to relating them to the Release records instead if 
that works better.

So is what you are saying that the only subordinate records from a Parent RFC 
should be Release records, not other RFCs?  Does using that in a 3-tiered 
scenario cause other problems from a functional standpoint?  As long as we can 
tie the records together (which we can) and have Approval gates for all of them 
(which we can), and maintain controls over who updates each (which we can), the 
Change Calendar is of little real consequence, since we'll be giving the CAB a 
printed report anyway.

Rick


On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault  wrote:

** 

Rick, 

Having "parent" or "master" changes that  have days or months for 
implementation may not be a good idea, because it is going to mess up your 
change calendars, whether your OOTB ITSM change calendar, or any other calenda 
(BTW, take a look at the Kinetic calendar, it is awesome and really simple to 
set up), unless you filter out this "parent" changes by the change type or 
something else. Other things that will be messed up are is the new 7.5 
collision detection and impact analysis. I am running into this specific 
situation right now and it is not clean... it is actually cludgy. I advise you 
to stay away from that scenario as much as possible from day one.

I agree with Roger that these kind of parent changes should find their place in 
the release module somehow, and not in the change module. This implies of 
course using another module, training,etc, but in the end it will be much 
cleaner from a process, data and reporting perspectives.

Guillaume



From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Thursday, July 22, 2010 11:36 AM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question



** We intend to log the actual work in Release, but we want local RFCs to track 
the scheduling of the change, which would have different acceptable maintenance 
windows at each location.  So the parent change would give, say, a 30 day 
window for implementation, and each child RFC logs where within that window the 
individual location will do their change.  Does that seem like a sound 
structure, Roger, or should everything underneath the parent RFC be based in 
Release?



Rick


On Thu, Jul 22, 2010 at 11:30 AM, Roger Justice  wrote:

** This would be better handled by Release. I know that the parent in either 
case cannot be closed until the children changes are completed.







-Original Message-
From: Rick Cook 
To: arslist 
Sent: Thu, Jul 22, 2010 11:26 am
Subject: Change Management question





** We are looking to use CM (7.5) like this:  One Project or Release RFC that 
would dictate what needed to be done at multiple locations.  Then subordinate 
RFCs would be created at each location to handle the exact scheduling and 
implementation.  My question is whether the Parent/Child RFC process works like 
the RFC/Task process, in that closing the last task in an RFC auto-closes it 
and/or if the Parent RFC is prevented from being closed until all of the 
children are closed.

Just trying to get a handle on the degree of dependence or control the parent 
RFC has on the subordinate RFC, and vice versa.

Rick

_attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_ 
_attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_

_attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_ 




_attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_ 


_attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_ 

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-23 Thread Rick Cook
Thanks, Guillaume.

The OOB Change Calendar has already been identified as an issue, due to its
limitations on time periods.  We are looking at options there.  Collision
and Impact aren't really going to be used by the customer at first, though
as their CM processes mature and their CI data gets more complete, they
intend to get there.  And we intend to attach the affected CIs to the child
RFCs, not the Parent, though we're open to relating them to the Release
records instead if that works better.

So is what you are saying that the only subordinate records from a Parent
RFC should be Release records, not other RFCs?  Does using that in a
3-tiered scenario cause other problems from a functional standpoint?  As
long as we can tie the records together (which we can) and have Approval
gates for all of them (which we can), and maintain controls over who updates
each (which we can), the Change Calendar is of little real consequence,
since we'll be giving the CAB a printed report anyway.

Rick

On Fri, Jul 23, 2010 at 1:22 PM, Guillaume Rheault wrote:

> **
>  Rick,
>
> Having "parent" or "master" changes that  have days or months for
> implementation may not be a good idea, because it is going to mess up your
> change calendars, whether your OOTB ITSM change calendar, or any other
> calenda (BTW, take a look at the Kinetic calendar, it is awesome and really
> simple to set up), unless you filter out this "parent" changes by the change
> type or something else. Other things that will be messed up are is the new
> 7.5 collision detection and impact analysis. I am running into this specific
> situation right now and it is not clean... it is actually cludgy. I advise
> you to stay away from that scenario as much as possible from day one.
>
> I agree with Roger that these kind of parent changes should find their
> place in the release module somehow, and not in the change module. This
> implies of course using another module, training,etc, but in the end it will
> be much cleaner from a process, data and reporting perspectives.
>
> Guillaume
>
>  --
> *From:* Action Request System discussion list(ARSList) [
> arsl...@arslist.org] on behalf of Rick Cook [remedyr...@gmail.com]
> *Sent:* Thursday, July 22, 2010 11:36 AM
> *To:* arslist@ARSLIST.ORG
> *Subject:* Re: Change Management question
>
>  ** We intend to log the actual work in Release, but we want local RFCs to
> track the scheduling of the change, which would have different acceptable
> maintenance windows at each location.  So the parent change would give, say,
> a 30 day window for implementation, and each child RFC logs where within
> that window the individual location will do their change.  Does that seem
> like a sound structure, Roger, or should everything underneath the parent
> RFC be based in Release?
>
>
> Rick
>
> On Thu, Jul 22, 2010 at 11:30 AM, Roger Justice  wrote:
>
>> ** This would be better handled by Release. I know that the parent in
>> either case cannot be closed until the children changes are completed.
>>
>>
>>
>>   -Original Message-
>> From: Rick Cook 
>> To: arslist 
>> Sent: Thu, Jul 22, 2010 11:26 am
>> Subject: Change Management question
>>
>>** We are looking to use CM (7.5) like this:  One Project or Release
>> RFC that would dictate what needed to be done at multiple locations.  Then
>> subordinate RFCs would be created at each location to handle the exact
>> scheduling and implementation.  My question is whether the Parent/Child RFC
>> process works like the RFC/Task process, in that closing the last task in an
>> RFC auto-closes it and/or if the Parent RFC is prevented from being closed
>> until all of the children are closed.
>>
>> Just trying to get a handle on the degree of dependence or control the
>> parent RFC has on the subordinate RFC, and vice versa.
>>
>> Rick
>>  _attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_
>>  _attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_
>
>
> _attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_
>   _attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_
>

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-23 Thread Guillaume Rheault
Rick,

Having "parent" or "master" changes that  have days or months for 
implementation may not be a good idea, because it is going to mess up your 
change calendars, whether your OOTB ITSM change calendar, or any other calenda 
(BTW, take a look at the Kinetic calendar, it is awesome and really simple to 
set up), unless you filter out this "parent" changes by the change type or 
something else. Other things that will be messed up are is the new 7.5 
collision detection and impact analysis. I am running into this specific 
situation right now and it is not clean... it is actually cludgy. I advise you 
to stay away from that scenario as much as possible from day one.

I agree with Roger that these kind of parent changes should find their place in 
the release module somehow, and not in the change module. This implies of 
course using another module, training,etc, but in the end it will be much 
cleaner from a process, data and reporting perspectives.

Guillaume


From: Action Request System discussion list(ARSList) [arsl...@arslist.org] on 
behalf of Rick Cook [remedyr...@gmail.com]
Sent: Thursday, July 22, 2010 11:36 AM
To: arslist@ARSLIST.ORG
Subject: Re: Change Management question

** We intend to log the actual work in Release, but we want local RFCs to track 
the scheduling of the change, which would have different acceptable maintenance 
windows at each location.  So the parent change would give, say, a 30 day 
window for implementation, and each child RFC logs where within that window the 
individual location will do their change.  Does that seem like a sound 
structure, Roger, or should everything underneath the parent RFC be based in 
Release?

Rick

On Thu, Jul 22, 2010 at 11:30 AM, Roger Justice 
mailto:rjust2...@aol.com>> wrote:
** This would be better handled by Release. I know that the parent in either 
case cannot be closed until the children changes are completed.



-Original Message-
From: Rick Cook mailto:remedyr...@gmail.com>>
To: arslist mailto:arslist@ARSLIST.ORG>>
Sent: Thu, Jul 22, 2010 11:26 am
Subject: Change Management question

** We are looking to use CM (7.5) like this:  One Project or Release RFC that 
would dictate what needed to be done at multiple locations.  Then subordinate 
RFCs would be created at each location to handle the exact scheduling and 
implementation.  My question is whether the Parent/Child RFC process works like 
the RFC/Task process, in that closing the last task in an RFC auto-closes it 
and/or if the Parent RFC is prevented from being closed until all of the 
children are closed.

Just trying to get a handle on the degree of dependence or control the parent 
RFC has on the subordinate RFC, and vice versa.

Rick
_attend WWRUG10 www.wwrug.com<http://www.wwrug.com/> ARSlist: "Where the 
Answers Are"_
_attend WWRUG10 www.wwrug.com<http://www.wwrug.com> ARSlist: "Where the Answers 
Are"_

_attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-22 Thread Rick Cook
We intend to log the actual work in Release, but we want local RFCs to track
the scheduling of the change, which would have different acceptable
maintenance windows at each location.  So the parent change would give, say,
a 30 day window for implementation, and each child RFC logs where within
that window the individual location will do their change.  Does that seem
like a sound structure, Roger, or should everything underneath the parent
RFC be based in Release?

Rick

On Thu, Jul 22, 2010 at 11:30 AM, Roger Justice  wrote:

> ** This would be better handled by Release. I know that the parent in
> either case cannot be closed until the children changes are completed.
>
>
>
> -Original Message-
> From: Rick Cook 
> To: arslist 
> Sent: Thu, Jul 22, 2010 11:26 am
> Subject: Change Management question
>
> ** We are looking to use CM (7.5) like this:  One Project or Release RFC
> that would dictate what needed to be done at multiple locations.  Then
> subordinate RFCs would be created at each location to handle the exact
> scheduling and implementation.  My question is whether the Parent/Child RFC
> process works like the RFC/Task process, in that closing the last task in an
> RFC auto-closes it and/or if the Parent RFC is prevented from being closed
> until all of the children are closed.
>
> Just trying to get a handle on the degree of dependence or control the
> parent RFC has on the subordinate RFC, and vice versa.
>
> Rick
> _attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_
>  _attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"


Re: Change Management question

2010-07-22 Thread Roger Justice
This would be better handled by Release. I know that the parent in either case 
cannot be closed until the children changes are completed.





-Original Message-
From: Rick Cook 
To: arslist 
Sent: Thu, Jul 22, 2010 11:26 am
Subject: Change Management question


** We are looking to use CM (7.5) like this:  One Project or Release RFC that 
would dictate what needed to be done at multiple locations.  Then subordinate 
RFCs would be created at each location to handle the exact scheduling and 
implementation.  My question is whether the Parent/Child RFC process works like 
the RFC/Task process, in that closing the last task in an RFC auto-closes it 
and/or if the Parent RFC is prevented from being closed until all of the 
children are closed.

Just trying to get a handle on the degree of dependence or control the parent 
RFC has on the subordinate RFC, and vice versa.

Rick
_attend WWRUG10 www.wwrug.com ARSlist: "Where the Answers Are"_ 

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug10 www.wwrug.com ARSlist: "Where the Answers Are"