I don't suppose you have a picture?

On 12/3/2010 7:48 AM, [email protected] wrote:
We did a church several with exposed construction.  We had the painter paint 
the pipe, fittings and hangers the same color as the ceiling.  This was a 
sloped ceiling and there was no way to enlist sidewalls and run the pipe up the 
slope along the beam.  We had to run horizontal branch lines between the beams 
to get the spacing right.

The Arch. Wasn't happy but fortunately understood code requirements outweighed 
his creative preference.

When it was complete we were all surprised how well the system just blended 
into the background.  Unless you really looked for it, the sprinkler system was 
virtually invisible to the casual glance.

Craig L. Prahl, CET
Fire Protection
CH2MHILL
Lockwood Greene
1500 International Drive
Spartanburg, SC  29304-0491
Direct - 864.599.4102
Fax - 864.599.8439
CH2MHILL Extension  74102
[email protected]



-----Original Message-----
From: [email protected] 
[mailto:[email protected]] On Behalf Of Greg McGahan
Sent: Thursday, December 02, 2010 6:05 PM
To: [email protected]; [email protected]
Subject: Re: difficult one

Impossible to seal off - it is open on the sides to a Lobby basically.
He is a stickler for sure for what he wants the way he wants it. He
wanted us to run the pipe on the roof within the tapered insulation... I
said sure, but we would not warranty it.

Its going to be a fight.

On 12/2/2010 4:50 PM, Travis Mack, SET wrote:
I believe that even with a deluge system you have to install heads per the 
listing. So you couldn't do his method anyway.

Tell him to seal it all off and use FM200. That may cost a fortune but you have 
to pay for what you want.
Travis Mack, SET
MFP Design, LLC
www.mfpdesign.com

Sent on the Sprint® Now Network from my BlackBerry®

-----Original Message-----
From: Greg McGahan<[email protected]>
Sender: [email protected]
Date: Thu, 02 Dec 2010 16:46:25
To:<[email protected]>
Reply-To: [email protected]
Subject: difficult one

The situations is this:

Preface - I have already exhausted the "you can't because" in trying to
convince him to run two lines exposed in this space.

Light Hazard
Corridor / Lobby  with a center section Sloped, exposed construction 8
in on 12in - 20' in width
On each side the ceiling drops about 4' to smooth flat ceilings

The architect wants to find a way to eliminate exposed pipe. He prefers
to use sidewalls on the vertical 4' sides which I told him we could not do..
His question is can he install detection at the peak, use sidewalls as
described above with a deluge valve.

Does anyone have any other creative ideas for this situation?

Thanks,
Greg


--
Greg C. McGahan Living Water Fire Protection, LLC. 1160 McKenzie Road Cantonment, FL 32533 850-937-1850 Fax 850-937-1852
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

For Technical Assistance, send an email to: [email protected]

To Unsubscribe, send an email to:[email protected]
(Put the word unsubscribe in the subject field)

Reply via email to